6 Risk Allocations and Management

One shortcoming of the VDOT oversight budget is that it does not provide contingency funds. Over the first year of the project, various issues would have been far easier to address if contingency funds were available to VDOT. These include:

  • Special studies associated with ambiguities in the contractual project scope
  • Community desire for additional soundwall protection
  • Fairfax County concerns regarding access to iNova Hospital
  • MOT issues
  • Permit requirements from third parties such as Fairfax County Park Authority, MWAA, and Norfolk Southern Railroad

Ultimately, VDOT was forced to request additional funds from the Commonwealth Transportation Board to address these issues.

Risk items are perhaps best viewed in terms of issues. These represent scope items that are ambiguous with regard to responsibility and inclusion in the contractual scope, as well as items that were unanticipated but are now seen as necessary to advancing the project.

The project team is still refining its approach to addressing and solving these issues, and many remain unresolved at this point. Exhibit 10 presents the Issues Log (Fluor's PCO log).:

Exhibit 10 I-495 HOT Lanes Work Order and PCO Tracking Log
Fluor-Lane PCO # VDOT Work Order # VDOT Tracking # Description
1 1 1A Replace I-495 NB bridge over Chain Bridge Rd. - Initial MOT Study
1   1B Replace I-495 NB bridge over Chain Bridge Rd. - Design
1   1C Replace I-495 NB bridge over Chain Bridge Rd. - Construction
42   2A Disapprove Bridge-mounted Sign Structures - Design Costs
42   2B Disapprove Bridge-mounted Sign Structures - Construction Costs
2   3 Continuous Lighting
3   4 ITS - Fiber Optic Cable
5   5 Bike/Pedestrian Extensions
9   6 VES - Vehicle Enforcement Systems
10   7 VOD - Vehicle Occupancy Detection
11   8 HOT OC Location
12   9 Phase VIII Deferred Items
13   10 Bridge Width at LRTP - B603/B654
14   11 Retaining Wall at Macerich/Parcel 092 - Tyson's Corner
15   12 Existing Drainage Rehab Debate per TR 3.4C
17   13 Parcels 134 & 047 - Fairview Property - ROW/Savings Allowance Issue
19   14 Westpark T-Connector over I-495 - B648 widening
25   15 Future DMS and static signs - request from ITS/Tolling working group session
31   16 Design Waiver #9 Denial - HOT Ramps at I-66
37   17 Phase VIII Ops - IJR issue with I-95/I-395
43   18 MWAA Access Rights at Dulles Toll Road
57   19 Existing Drainage Upsize from 15" to 18" per TR 3.4
59   20 Existing Drainage Rehab Issues on Phase VIII Ramps
60   21 Fairfax County Noise Waiver
63   22 Modification to Sign Headers Due to CBE Branding
66   23 Phase VIII As-built Conflicts - Utility?
67   24 Withholding ROW Approval due to Utility Easements not shown
68   25 Phase VIII As-Built Conflicts - Foundations?
69   26 Recovery of estimating and engineering cost - ARCA Ex. N Att. 1.5D 108.9.3
70   27 VDOT 29/Gallows Rd Project Interface
73   28 Noise Barrier 13D
74   29 Noise Barrier 13A & 13E
75   30 Phase VIII Archeological Find
76   31 Direct Communications between VDOT and Fluor-Lane
77   32 Regional Signing Plan
78   33 Attenuators
79   34 Toll Gantry Design
80   35 2-foot Barrier Offset
81   36 Modify Noise Barrier Heights
82   37 NVRPA and W&OD Bridge Widths
83   38 Re-Analysis of Soundwalls
85   41 Refurbish B602 Wakefield Pedestrian Overpass
84   42 Phase VIII Parapet Height
<< Previous Contents Next >>

Contact

Jerry Yakowenko
Office of Program Administration
202-366-1562
E-mail Jerry

 
 
Updated: 04/07/2011
 

FHWA
United States Department of Transportation - Federal Highway Administration