Skip to contentUnited States Department of Transportation - Federal Highway AdministrationSearch FHWAFeedback

Construction

C-54 C. Contractor Selection

  1. Project Development Assembles Team with Region Coordination
  2. Develop RFP with Selection Criteria and Weights
  3. Project Team Determines Bid Items and Quantities
  4. Advertise RFP
  5. Pre-Proposal Contractor Meetings
  6. Team Members Individually Score Proposals
  7. Section Meeting Ranking by Consensus
  8. Optional Interview
  9. Team Award Recommendation
  10. Deputy Director Approval
  11. Award Design Contract
  12. Project Development Team Reviews Weighting Criteria
  13. Project Development Team Reviews Status of CMGC Program
  14. Interview All Contractors Selection by Team Consensus
  15. Re-advertise RFP or Process as Design-Bid-Build

[start]
1 go to 2
2 branches to either 3, 12, or 13

If 2 branched to 3
3 go to 4
4 go to 5
5 go to 6
6 go to 7
7 go to 8
8 branches to either 9 or 14

If 2 branched to 12
12 go to 4

If 8 branched to 9
9 go to 10

If 8 branched to 14
14 go to 9
10 branches to either 11 or 15
[end]

Contact

Jerry Yakowenko
Office of Program Administration
202-366-1562
E-mail Jerry

 
 
Updated: 04/07/2011
 

FHWA