Sample Listing of Major Project Deliverables

Word Version (26 kb)

(Beginning after the NEPA Decision Document and continuing through commencement of final design)
Activity Start Date Completion Date Progress / Remarks
Assign Interim FHWA Major Project Oversight Manager   
Select Permanent Major Project Oversight Manager   
Identify State DOT Project Managers   
Establishment of an overall Agreement or Charter between the FHWA and the State DOT   
Prepare General Engineering Consultant (GEC) Statement of Work
(If a GEC is used)
   
Procure General Engineering Consultant (GEC)
(If a GEC is used)
   
Establish Entire Project Management Team   
Prepare and Implement Project Management Plan   
Finalize Ownership Agreements   
Develop/Adjust Stewardship and Oversight Agreements   
Validate Total Project Cost Estimate   
Validate Project Schedule   
Prepare draft Initial Finance Plan   
Develop Specific Design and Construction Procurement Process   
Procure Section Design Consultants   
Finalize Initial Finance Plan prior to the first construction authorization or Request For Proposal (RFP) for Design/Build Projects   
Word files can be viewed with the Word Viewer 2003

More Information

Contacts

Jim Sinnette
Office of Program Administration
202-366-0479
E-mail Jim

 
 
This page last modified on 03/22/07
 

FHWA
United States Department of Transportation - Federal Highway Administration