Sample Listing of Major Project Deliverables
Word Version (26 kb)
(Beginning after the NEPA Decision Document and continuing through commencement of final design)
| Activity |
Start Date |
Completion Date |
Progress / Remarks |
| Assign Interim FHWA Major Project Oversight Manager | | | |
| Select Permanent Major Project Oversight Manager | | | |
| Identify State DOT Project Managers | | | |
| Establishment of an overall Agreement or Charter between the FHWA and the State DOT | | | |
Prepare General Engineering Consultant (GEC) Statement of Work (If a GEC is used) | | | |
Procure General Engineering Consultant (GEC) (If a GEC is used) | | | |
| Establish Entire Project Management Team | | | |
| Prepare and Implement Project Management Plan | | | |
| Finalize Ownership Agreements | | | |
| Develop/Adjust Stewardship and Oversight Agreements | | | |
| Validate Total Project Cost Estimate | | | |
| Validate Project Schedule | | | |
| Prepare draft Initial Finance Plan | | | |
| Develop Specific Design and Construction Procurement Process | | | |
| Procure Section Design Consultants | | | |
| Finalize Initial Finance Plan prior to the first construction authorization or Request For Proposal (RFP) for Design/Build Projects | | | |
|