Exhibit 1a - Total Cost Estimates by Annual Financial Plan
(Estimates in Billions of Dollars)
Financial Plan Total Cost Estimates Work Completed as of End of Fiscal Year Shown Work Uncompleted Amount Over Initial Estimates
FY 1998 Plan Estimate (Base Year)$1.6 Billion Initial Cost Estimate$0.2 (12%)$1.4 
FY 1999 Plan Estimate$1.8 Billion Revised Estimate$0.6 (33%)$1.0$0.2
FY 2000 Plan Estimate$2.0 Billion Current Estimate$0.9 (44%)$0.7$0.4

Return to Document

Exhibit 2b - Cumulative Project Expenditures vs Initial Financial Plan Estimates
(does not include debt service repayments during construction period)
  Actual Expenditures
(through end of FY 2000 in billions of dollars)
Projected Expenditures
(through end of FY 2003 in billions of dollars)
  FY 1998 FY 1999 FY 2000 FY 2001 FY 2002 FY 2003
Expenditure (At or Under Budget)$0.10$0.50$0.90$1.30$1.55$1.60
Expenditure (Above Budget)$0.10$0.10$0$0.10$0.25$0.40
Budgeted as of FY 1998 Plan (Base Year)$0.10$0.50$0.90$1.30$1.55$1.60

Return to Document

More Information

Contacts

Carl Gottschall
Innovative Program Delivery Office
202-366-4104
E-mail Carl

 
 
This page last modified on 03/22/07
 

FHWA
United States Department of Transportation - Federal Highway Administration