Highway Planning and Project Development Process
Click on the image to view the full size version.

Step
- Develop Unified Planning Work Program (8 months)
- * Develop 20-year Long-Range Plan (conformity determination at least every 3 years) (2 years) Planning Qs/ Cost template
- * Develop TIP (conformity determination at least every 2 years) (1 year) Cost template
- * STIP (Incorporate TIPs into STIP) (1 year) Cost template
- * Project Level conformity determination/ Complete NEPA process (CE, EA/ FONSI, EIS / ROD) (1 - 5 years) Cost template
- * Authorization for Final Design (1 year) Cost template
- * Authorization for Right-of-Way Acquisitions (2 years) Cost template
- * Authorization for Construction (P.S. & E. approval (highway); full funding grant agreement (transit)) (1 year) Cost template
- * Project Construction (1 - 5 years) Cost template
- * Operations (life of the facility) Cost template
Legend
- TIP Transportation Improvement Program
- STIP Statewide Transportation Improvement Program
- NEPA National Environmental Policy Act
- CE Categorical Exclusion
- EA Environmental Assessment
- FONSI Finding Of No Significant Impact
- EIS Environmental Impact Statement
- ROD Record of Decision
- P. S. & E. Plans, Specifications, and Estimates
- Planning Qs Planning Questions
* Cost Estimate Check
|