Highway Planning and Project Development Process

Click on the image to view the full size version.

Highway Planning and Project Development Process as described below

Step

  1. Develop Unified Planning Work Program (8 months)
  2. * Develop 20-year Long-Range Plan (conformity determination at least every 3 years) (2 years) Planning Qs/ Cost template
  3. * Develop TIP (conformity determination at least every 2 years) (1 year) Cost template
  4. * STIP (Incorporate TIPs into STIP) (1 year) Cost template
  5. * Project Level conformity determination/ Complete NEPA process (CE, EA/ FONSI, EIS / ROD) (1 - 5 years) Cost template
  6. * Authorization for Final Design (1 year) Cost template
  7. * Authorization for Right-of-Way Acquisitions (2 years) Cost template
  8. * Authorization for Construction (P.S. & E. approval (highway); full funding grant agreement (transit)) (1 year) Cost template
  9. * Project Construction (1 - 5 years) Cost template
  10. * Operations (life of the facility) Cost template

Legend

  • TIP Transportation Improvement Program
  • STIP Statewide Transportation Improvement Program
  • NEPA National Environmental Policy Act
  • CE Categorical Exclusion
  • EA Environmental Assessment
  • FONSI Finding Of No Significant Impact
  • EIS Environmental Impact Statement
  • ROD Record of Decision
  • P. S. & E. Plans, Specifications, and Estimates
  • Planning Qs Planning Questions

* Cost Estimate Check

More Information

Contacts

Jim Sinnette
Office of Program Administration
202-366-0479
E-mail Jim

 
 
This page last modified on 03/22/07
 

FHWA
United States Department of Transportation - Federal Highway Administration