Awards Honor the Best and Brightest in Highway Quality
Innovations in highway quality from Arizona to New Jersey were honored
in September in Minneapolis, Minnesota, at the presentation of the National
Partnership for Highway Quality’s (NPHQ) 2003 National Achievement
Awards. “NPHQ encourages the use of quality practices that will
usher in a new era of roadway investment and performance to improve
safety and service for highway users,” says NPHQ Executive Director
Bob Templeton. “It was clear that from design to delivery, the
2003 winners raised the bar in key quality areas.”
NPHQ’s National Achievement Award went to the New Jersey Department
of Transportation (NJDOT), J.H. Reid General Contractor, and Parsons
Brinckerhoff-FG, Inc., for their work on the US Route 9 Bridge over
Nacote Creek. New Jersey faced the challenge of replacing a deteriorated
76.2-m (250-ft) drawbridge built in 1922 with a new five-span, 152.4-m
(500-ft) bridge. The new bridge has a 7.62-m (25-ft) vertical clearance
and two new approach roadways. To achieve a high-quality product, NJDOT
used the Load and Resistance Factor Design method, as well as high-performance
concrete for the prestressed beams. Nontoxic composite materials were
used for the bridge’s fender system, which protects the bridge
from collisions. “Multiple hallmarks of quality distinguished
this project, including stringent internal quality reviews,” noted
Templeton. “As an outcome, there were only two change orders executed
during construction, both the result of unforeseen ground conditions
where piles were to be driven.”
| 
|
 |
| NJDOT used the Load and Resistance Factor Design method
to construct the new US Route 9 Bridge over Nacote Creek. |
The new bridge over Nacote Creek has a 7.62-m
(25-ft) vertical clearance and two new approach roadways. |
The Michigan Department of Transportation (MDOT), Nagel Construction
Company, and the URS Corporation won Special Recognition for a Small
Project for the reconstruction of the 28th Street at Broadmoor Avenue
intersection in Grand Rapids and Kentwood. This intersection ranks as
one of the most congested in West Michigan, with 85,000 vehicles using
it daily. Careful planning was required to limit the project’s
impact on traffic flow and the many shopping centers and other businesses
in the area. MDOT worked closely with all the stakeholders on designing
a project staging plan, studying area utility lines, and planning alternative
routes, among other tasks. An accelerated construction schedule included
20-hour work days, 6 days a week. The project came in at $154,000 under
budget and opened to traffic 12 days ahead of schedule. “The team
worked around the clock to get the work done well and as efficiently
as possible,” said Suzette Peplinski, manager of MDOT’s
Transportation Service Center in Grand Rapids.
| 

|
| The Houston Gateway project replaced four
bridges spanning the US 59-Southwest freeway. |
Special Recognition for a Structure Project was awarded to the Texas
Department of Transportation (TxDOT) and Williams Brothers Construction
Company for their US 59–Southwest Freeway initiative, known as
the Houston Gateway. The project widened nearly a mile of the below-grade
freeway, which runs to and from downtown Houston and has an average
daily traffic count of 241,000 vehicles. As part of the project, four
bridges spanning the freeway had to be replaced. The steel for new tied-arch
bridges was constructed in place over the existing bridges and then
each old bridge was demolished using controlled explosions on five separate
weekends.
|
The National Partnership for
Highway Quality (NPHQ) brings together State, Federal, and highway
industry leaders to encourage the use of quality practices that
will improve safety and service for highway users. Members include
the Federal Highway Administration, American Association of State
Highway and Transportation Officials, American Public Works Association,
Foundation for Pavement Preservation, National Institute for Certification
in Engineering Technologies, and a number of roadway construction
trade associations. |
|

|
| This photo shows the reconstruction of the
28th Street at Broadmoor Avenue intersection in Grand Rapids and
Kentwood, Michigan. |
The $36.5 million reconstruction was completed 30 days ahead of schedule
with a cost savings of $420,000, despite encountering such hurdles as
Tropical Storm Allison. The storm dumped more than 38 inches of rain
in one weekend, filling the freeway with an estimated 100 million gallons
of floodwater from Houston’s bayous. The project team met the
challenge and had the freeway cleared, cleaned, and reopened in time
for the Monday morning rush hour.
The Arizona Department of Transportation; Sundt Construction, Inc.;
and the URS Corporation received the Gold Award for their US 93-Boulders
Reconstruction Project. The team’s task was to widen 12.06-km
(7.5-mi) of this narrow, winding roadway, which travels through Mohave
Desert terrain, from a two-lane road to a four-lane divided highway.
One of the project’s hallmarks was environmental stewardship:
nearly 20,000 cacti and other flora were salvaged, preserved in nurseries,
and replanted after the construction work was done. Almost 3,000 boulders
in the area were also salvaged and replaced by the project team. Extensive
accommodations were also made for wildlife: the Desert Tortoise, for
example, had its own protection and mobility plan during construction.
Also a Gold Winner were the Maryland State Highway Administration,
IA Construction, and the Wilson T. Ballard Company for the Canal Parkway
Project in Cumberland. The $48 million, two-lane parkway extends for
2.9-km (1.8-mi) and has opened access to the region, sparked public
and private investment in Cumberland, and solved a 60-year bottleneck
of traffic. Partnerships were key to the project’s success, with
stakeholders including the National Park Service, CSX Transportation,
the U.S. Army Corps of Engineers, City of Cumberland, and the Canal
Place Preservation and Development Authority. The project finished on
time and under budget, while incorporating such context-sensitive design
elements as the construction of a bicycle and pedestrian trail.
Five State winners were also honored at the awards ceremony (see sidebar).
For more information on NPHQ or the 2003 awards, contact Bob Templeton
at 512-301-9899 (fax: 512-301-9897; email: btemplenphq@aol.com)
or visit www.nphq.org.
|
NPHQ State Award Winners
- Georgia Department of Transportation; Shepherd Construction
Co., Inc.; and E.R. Snell Contractor, Inc., for the I-285 Resurfacing
Project.
- Kentucky Transportation Cabinet; Hinkle Contracting; Central
Rock Mineral, Co.; and H.W. Lochner, Inc., for the Reconstruction
of Paris Pike.
- North Carolina Department of Transportation and the S.T.
Wooten Corporation for the White Oak River Bridge Replacement.
- Ohio Department of Transportation, the Kokosing Construction
Company, and Parsons Brinckerhoff Ohio, Inc., for the Interstate
70 Reconstruction.
- Oregon Department of Transportation and J.C. Compton, Inc.,
for the Oregon 99W Brutscher Street to Main Street Project in
Newberg.
|
Back to Articles in this Issue
|