U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000


Skip to content
Facebook iconYouTube iconTwitter iconFlickr iconLinkedInInstagram

Federal Highway Administration Research and Technology
Coordinating, Developing, and Delivering Highway Transportation Innovations

Report
This report is an archived publication and may contain dated technical, contact, and link information
Publication Number: FHWA-HRT-01-167
Date: April 2005

Structural Factors of Jointed Plain and Concrete Pavements: SPS-2 - Initial Evaluation and Analysis

Previous | Table of Contents | Next

CHAPTER 5. SPS-2 PROJECT STATUS SUMMARIES

This chapter summarizes key site information, pavement design factors, and monitoring data availability for each of the SPS-2 projects. For each SPS-2 project, the following are presented:

The SPS-2 projects are presented in the following alphabetical order:

Arizona SPS-2

The Arizona SPS-2 project site is located in the eastbound lanes of Interstate 10 (I-10) in southwestern Arizona, approximately 56 km west of Phoenix. I-10 is a rural interstate; in 1992 the AADT was 15,900. The initial annual ESALs was estimated at 1,052,626. The SPS-2 project was constructed as part of the rehabilitation of I-10. The typical pavement design consists of two 3.66-m-wide lanes, an outside shoulder width of 3.05 m, and an inside shoulder width of 1.22 m. The SPS-2 test sections were constructed on a portion of I-10 that is relatively straight and flat.

Bending plate WIM equipment was installed in the fall of 1993. Calibration was completed on January 24, 1994.

Construction of the SPS-2 site started in June 1993 with the removal of the existing pavement. Construction of individual test sections was completed and the area was opened to traffic on October 1, 1993.

All required core sections were constructed. Nine supplemental State test sections were constructed. Table 39 summarizes key project information and data available for all the sections.

Table 39. Arizona SPS-2 project summary.

Project level information and data availability        Construction date:   10/01/1993

Climate - DNF Data Availability Average Values As planned?

CLM: 17 years

AWS: 6 years

FI: 0°C days, Precip. 232 mm

FI: 0°C days, Precip. 199mm

Yes
Traffic WIM: 6 years 1,052,625 ESALs/year (>200,00) Yes
Subgrade type Coarse-grained soil for all. As designed? Yes

Flexural strength
14-day MPa

Design value Actual Averages Within 10%?

3.8
6.2

3.94
5.77

Yes
Yes

PCC tests available On average 99% completed for core sections

 

Section level key design factors and monitoring data availability

Key pavement design factors Monitoring data availability, No. of tests
ID Slab Thick. mm Base type With Drain Lane Width m As Design ? IRI FWD Distress Meet Min. Req'd?
  Actual Design Manual Photo. Faulting
0213 201 203 AGG No   Yes 4 6 3 1 3 No
0214 211   AGG No   Yes 5 7 3 1 3 No
0215* 287 279 AGG No   Yes 12 28 12 1 12 No
0216 284   AGG No   Yes 5 6 2 1 2 No
0217 206 203 LCB No   Yes 5 6 2 1 2 No
0218 211   LCB No   Yes 5 6 2 1 2 No
0219 274 279 LCB No   Yes 5 7 2 1 2 No
0220 287   LCB No   Yes 5 6 3 1 3 No
0221 208 203 PATB Yes   Yes 5 6 3 1 3 No
0222 218   PATB Yes   Yes 5 6 3 1 3 No
0223 282 279 PATB Yes   Yes 5 5 3 1 3 No
0224 272   PATB Yes   Yes 5 6 3 1 3 No
Overall- Good, except for 0222 Overall- Fair, late initial surveys.
Supplemental Sections - Total 9 sections, 7 PCC and 2 AC
0260 216 mm AC on 102 mm DGAB 5 3 0 1 NA
0261 216 mm AC on 102 mm DGAB 5 5 0 1 NA
0262 203 mm undoweled JPC (3.8 MPa) on DGAB, 4.27 m 5 4 3 1 3
0263 203 mm undoweled JPC (3.8 MPa) on DGAB, 4.27 m 5 1 3 1 3
0264 279 mm undoweled JPC (3.8 MPa) on DGAB, 3.66 m 5 2 3 1 3
0265 279 mm undoweled JPC (3.8 MPa) on DGAB, 3.66 m lane 5 3 3 1 3
0266 318 mm doweled JPC (3.8 MPa) on BTB, 4.27 m lane 5 1 3 1 3
0267 279 mm doweled JPC (3.8 MPa) on BTB, 4.27 m lane 5 1 3 1 3
0268 203 mm doweled JPC (3.8 MPa) on BTB, 4.27 m lane 5 1 3 1 3
  Overall - Good, except for 0260, 0261.

Note: * Indicates seasonal monitoring section(s)
Min. Req'd - Initial survey age less than 1 year and all long-term monitoring intervals less than 3 years for all monitoring types
Bolded and italic letters represent constructed values that are either not as designed or outside the
design range. For slab thickness, the design range is set at (design value +/- 12.7 mm)

Key Observations and Deviations

The following key observations were noted in the project construction report:

Project Status Summary

Overall, this project site is in excellent shape. The appendices to this report also contain a significant amount of monitoring data. The following summarizes the status of this project:


Data availability-Excellent overall.

The Arizona SPS-2 site does not appear to exhibit significant problems that will cause difficulty in performance analysis.

Arkansas SPS-2

The Arkansas SPS-2 project site is located in the westbound lanes of I-30 in west central Arkansas, just to the west of the I-70/I-30 interchange. I-30 is classified as a rural interstate; in 1993 the AADT was 18,000, with 45 percent heavy trucks. The estimated initial annual ESALs is 2,069,550. The SPS-2 project was included in the reconstruction of I-30. Of the 12 test sections required for the SPS-2 project, 3 were located in original construction fill areas, 6 were located in original construction cut areas, and 3 sections were at grade. The typical roadway for this project consists of two 3.66-m-wide lanes, an outside asphalt shoulder width of 3.05 m, and an inside shoulder width of 1.22 m.

Construction of the SPS-2 site began in November 1993 with the removal of the existing pavement. Construction of individual test sections was completed on October 1, 1995, and the project site was opened to traffic on November 1, 1995.

All required core sections were constructed, and no supplemental State test sections were constructed at this site. Table 40 summarizes key project information and data available for all the sections.

Table 40. Arkansas SPS-2 project summary.

Project level information and data availability        Construction date:   10/01/1995

Climate - DNF Data Availability Average Values As planned?

CLM: 17 years

AWS: 0 year

FI: 0°C days, Precip. 232 mm

NA

Yes
Traffic WIM: NA NA -
Subgrade type Fine-grained soil for all. As designed? Varies

Flexural strength
14-day MPa

Design value Actual Averages Within 10%?

3.8
6.2

3.94
5.77

Yes
No

PCC tests available On average 99% completed for core sections

 

Section level key design factors and monitoring data availability

Key pavement design factors Monitoring data availability, No. of tests
ID Slab Thick. mm Base type With Drain Lane Width m As Design ? IRI FWD Distress Meet Min. Req'd?
  Actual Design Manual Photo. Faulting
0213 188 203 AGG No 4.27 No 1 2 1 0 1 No
0214 211   AGG No 3.66 Yes 1 1 1 0 1 No
0215* 284 279 AGG No 3.66 Yes 1 2 1 0 1 No
0216 277   AGG No 4.27 Yes 1 2 1 0 1 No
0217 191 203 LCB No 4.27 Yes 1 2 1 0 1 No
0218 188   LCB No 3.66 No 1 2 1 0 1 No
0219 282 279 LCB No 3.66 Yes 1 1 1 0 1 No
0220 272   LCB No 4.27 Yes 1 2 1 0 1 No
0221 208 203 PATB Yes 4.27 Yes 1 1 1 0 1 No
0222 213   PATB Yes 3.66 Yes 1 1 1 0 1 No
0223 277 279 PATB Yes 3.66 Yes 1 1 1 0 1 No
0224 277   PATB Yes 4.27 Yes 1 1 1 0 1 No
Overall- Good, except for 0213 and 0218. Overall- Fair, late initial surveys.

Note: * Indicates seasonal monitoring section(s)
Bolded and Italic letters represent constructed values that are either not as designed or outside the design range. For slab thickness, the design range is set at (design value +/- 12.7 mm)

Key Observations and Deviations

The following key observations and deviations were noted in the project construction and deviation report:

Project Status Summary

This project site was well constructed overall, but is in fair-to-poor shape mainly due to very limited performance monitoring data, traffic data, PCC materials testing data, and

AWS data. There are no supplemental sections at this site. The following summarizes the status of this project:

The Arkansas SPS-2 site does not appear to have significant problems that will cause difficulty in performance analysis if construction, traffic, AWS, and monitoring data become available.

Colorado SPS-2

The Colorado SPS-2 project site is located in the eastbound lanes of I-76 in central Colorado, approximately 32 km northeast of Denver. I-76 is a rural interstate; in 1988 the AADT was 8,400, with 16 percent heavy trucks. The initial annual ESALs are estimated at 347,646. Six SPS-2 test sections were included in the phase 1 section of I-76, which was constructed on a new alignment (sections 080217, 080220, 080221, 080222, 080223, and 080224). The remaining six sections (sections 080213, 080214, 080215, 080216, 080218, and 080219) were located within the phase 2 section of I-76, which was being reconstructed. The 136th Street interchange bisects this SPS-2 site. However, no appreciable difference in traffic loading is expected due to the presence of this interchange.

All sections are on a tangent. The vertical grade averages +1.4 percent in the direction of traffic. Six sections were located in a cut (sections 080217, 080218, 080219, 080220, 080223, and 080224), while all other sections were located on fills. The typical roadway for this project consists of two 3.66-m-wide lanes, an outside shoulder width of 3.05 m, and an inside shoulder width of 1.22 m.

Construction of the SPS-2 site began on July 1, 1993, and was completed on November 1, 1993. The phase 1 work (new alignment) was opened to traffic on October 7, 1993. The phase 2 work (I-76 reconstruction) began after phase 1 was opened to traffic. Phase 2 sections were opened to traffic on January 5, 1994.

All required core sections were constructed. One supplemental State test section was also constructed. Table 41 summarizes key project information and data availability for all the sections.

Table 41. Colorado SPS-2 project summary.

Project level information and data availability        Construction date:   10/01/1993

Climate - DNF Data Availability Average Values As planned?

CLM: 17 years

AWS: 5 years

FI: 327 0°C days, Precip. 370 mm

FI: 394 0°C days, Precip. 232 mm

Yes
Traffic WIM: 3 years 347,646 ESALs/year (>200,000) Yes
Subgrade type Fine-grained soil for all. As designed? Varies

Flexural strength
14-day MPa

Design value Actual Averages Within 10%?

3.8
6.2

3.94
5.77

Yes
Yes

PCC tests available On average 94% completed for core sections

 

Section level key design factors and monitoring data availability

Key pavement design factors Monitoring data availability, No. of tests
ID Slab Thick. mm Base type With Drain Lane Width m As Design ? IRI FWD Distress Meet Min. Req'd?
  Actual Design Manual Photo. Faulting
0213 221 203 AGG No 4.27 No 3 5 2 2 3 Not quite
0214 213   AGG No 3.66 Yes 3 5 2 2 3 Not quite
0215 290 279 AGG No 3.66 Yes 3 5 2 2 3 Not quite
0216 300   AGG No 4.27 No 3 5 2 2 3 Not quite
0217 218 203 LCB No 4.27 No 3 3 2 2 3 Not quite
0218 196   LCB No 3.66 Yes 3 4 2 2 3 Not quite
0219 282 279 LCB No 3.66 Yes 3 4 2 2 3 Not quite
0220 282   LCB No 4.27 Yes 3 3 2 2 3 Not quite
0221 211 203 PATB Yes 4.27 Yes 3 4 2 2 3 Not quite
0222 221   PATB Yes 3.66 No 3 4 2 2 3 Not quite
0223 300 279 PATB Yes 3.66 No 3 4 2 2 3 Not quite
0224 297   PATB Yes 4.27 No 3 4 2 2 3 Not quite
Overall- Fair. Six sections outside design range. Good, except for late initial faulting surveys.
 
Supplemental Sections - 1 PCC section.
0259 279 mm JPC (4.5 MPa) on subgrade and 3.66 m lanes. 3 3 2 2 3 Not quite
   
Overall - Good

Note: * Indicates seasonal monitoring section(s)
Bolded and Italic letters represent constructed values that are either not as designed or outside the design range. For slab thickness, the design range is set at (design value +/- 12.7 mm)

Key Observations and Deviations

The following key observations were noted in the project construction report:

Project Status Summary

Overall, this project site is in excellent shape. The appendices to this report contain a significant amount of monitoring data. The following summarizes the status of this project:

The Colorado SPS-2 site does not appear to exhibit significant problems that will cause difficulty in performance analysis.

Delaware SPS-2

The Delaware SPS-2 project site is located in the southbound lanes of U.S. 113 in central Delaware, between Milford and Georgetown. U.S. 113 is a rural principal arterial; in 1989 the AADT was 10,708, with 10 percent heavy trucks. The initial annual ESALs are estimated at 234,000. The SPS-2 project was included in the addition of two southbound lanes to an initial two-lane roadway. The two new southbound lanes were separated from the existing northbound lanes by a 7.92- to 12.8-m-wide median. Route S-625 and another access road bisect this SPS-2 site. The traffic from these routes is expected to have little impact on the SPS-2 site. There is no record of WIM installation at this site.

The roadway typically consists of two 3.66-m-wide lanes, an outside shoulder width of 3.05 m, and an inside shoulder width of 1.22 m. The subgrade consists of sand and silty sand. Test sections were constructed on shallow cuts or fills. The cut sections ranged up to 1.52 m in depth. Several wetland areas exist adjacent to the mainline pavement, where the water table is at or near the surface for an extended time period.

This project was completed and opened to traffic on May 1, 1996. All required core sections were constructed, and two supplemental State test sections were constructed. Table 42 summarizes key project information and data available for all the sections.

Table 42. Delaware SPS-2 project summary.

Project level information and data availability        Construction date:   05/01/1996

Climate - WF Data Availability Average Values As planned?

CLM: 17 years

AWS: 0 year

FI: 103°C days, Precip. 1,144 mm

NA

Yes
Traffic WIM: 0 year N/A N/A
Subgrade type Fine-grained soil for all. As designed? Varies

Flexural strength
14-day MPa

Design value Actual Averages Within 10%?

3.8
6.2

4.53
5.22

No
No

PCC tests available On average 94% completed for core sections

 

Section level key design factors and monitoring data availability

Key pavement design factors Monitoring data availability, No. of tests
ID Slab Thick. mm Base type With Drain Lane Width m As Design ? IRI FWD Distress Meet Min. Req'd?
  Actual Design Manual Photo. Faulting
0213 211 203 AGG No 3.66 Yes 6 3 3 0 4 Yes
0214 224   AGG No 4.27 No 6 2 2 0 3 Yes
0215 297 279 AGG No 4.27 No 6 2 2 0 3 Yes
0216 279   AGG No 3.66 Yes 6 2 2 0 3 Yes
0217 234 203 LCB No 3.66 No 6 2 2 0 3 Yes
0218 226   LCB No 4.27 No 6 2 2 0 3 Yes
0219 287 279 LCB No 4.27 Yes 6 2 2 0 3 Yes
0220 307   LCB No 3.66 No 6 2 2 0 3 Yes
0221 208 203 PATB Yes 3.66 Yes 6 2 2 0 4 Yes
0222 211   PATB Yes 4.27 Yes 6 2 2 0 3 Yes
0223 300 279 PATB Yes 4.27 No 6 2 2 0 3 Yes
0224 315   PATB Yes 3.66 No 6 2 2 0 3 Yes
Overall- Fair. Seven sections outside design range. Good, except for late initial faulting surveys.
 
Supplemental Sections - 1 PCC section.
0259 279 mm JPC (20.7 MPa f'c) on 203 mm DGAB; 3.66 m lane; steel dowels 6 2 2 0 3 Yes
0260 254 mm JPC (20.7 MPa f'c) on 203 mm DGAB; 3.66 m lane; steel dowels 6 2 2 0 3 Yes
   
Overall - Excellent

Note: * Indicates seasonal monitoring section(s)
Bolded and Italic letters represent constructed values that are either not as designed or outside the design range. For slab thickness, the design range is set at (design value +/- 12.7 mm)


Key Observations and Deviations

The following key observations were noted in the project construction report:

The following deviations from SPS-2 guidelines were noted in the project deviation report:

Project Status Summary

Overall, this project site is in fair shape. The supplemental sections also contain a significant amount of monitoring data. The following summarizes the status of this project:

Data from the Delaware SPS-2 site will require special analysis techniques to adjust for various design factors that were not constructed as planned.

Iowa SPS-2

The Iowa SPS-2 project site is located in the northbound lanes of U.S. 65 in central Iowa, northeast of Des Moines. U.S. 65 is an urban/principal arterial; in 1994 the AADT was 17,400, with 16 percent trucks. The estimated initial ESALs for the section is approximately 600,000. The SPS-2 project was included in the relocation of U.S. 65 in both the northbound and southbound lanes.

The typical roadway consists of two 3.66-m-wide lanes, an outside asphalt shoulder width of 3.05 m, and an inside shoulder width of 1.22 m. The SPS-2 sections were constructed on a portion of U.S. 65 that included both tangent and superelevated sections. All sections were constructed on a tangent except sections 190215 and 190216. These sections were constructed on the high side of a horizontal curve with a superelevation rate of 2.5 percent. Vertical grades throughout the project area range from -2.6 percent to +2.2 percent. Sections 1902215 through 190220 were constructed on fill sections ranging from near 0 to 11.58 m in height. Sections 190221 through 190224 were constructed on cut sections ranging from 0.91 to 7.01 m.

WIM and AVC equipment were installed in June 1995 on U.S. 65, approximately 1.61 km north of the junction with IA-163 (state highway). Reconstruction was completed in 1994 during a period of relatively wet weather conditions. The project site was opened to traffic on December 1, 1994.

All required core sections were constructed. An additional supplemental State test section was also constructed. Table 43 summarizes key project information and data available for all the sections.

Table 43. Iowa SPS-2 project summary.

Project level information and data availability        Construction date:   08/01/1994

Climate - WF Data Availability Average Values As planned?

CLM: 17 years

AWS: 3 years

FI: 580 °C days, Precip. 900 mm

NA

Yes
Traffic WIM: 1 year 56,400 ESALs/year (<200,000) No
Subgrade type Fine-grained soil for all. As designed? Varies

Flexural strength
14-day MPa

Design value Actual Averages Within 10%?

3.8
6.2

3.22
5.19

No
No

PCC tests available On average 98% completed for core sections

 

Section level key design factors and monitoring data availability

Key pavement design factors Monitoring data availability, No. of tests
ID Slab Thick. mm Base type With Drain Lane Width m As Design ? IRI FWD Distress Meet Min. Req'd?
  Actual Design Manual Photo. Faulting
0213 216 203 AGG No 4.27 Yes 5 2 2 1 3 Yes
0214 213   AGG No 3.66 Yes 5 1 1 1 2 Yes
0215 300 279 AGG No 3.66 No 5 1 2 1 3 Yes
0216 295   AGG No 4.27 No 5 1 2 1 3 Yes
0217 196 203 LCB No 4.27 Yes 5 2 2 1 3 Yes
0218 208   LCB No 3.66 Yes 5 2 2 1 3 Yes
0219 284 279 LCB No 3.66 Yes 5 1 2 1 3 Yes
0220 290   LCB No 4.27 Yes 5 2 2 1 3 Yes
0221 239 203 PATB Yes 4.27 No 5 2 2 1 3 Yes
0222 211   PATB Yes 3.66 Yes 4 1 1 1 3 Yes
0223 297 279 PATB Yes 3.66 No 5 1 1 1 3 Yes
0224 295   PATB Yes 4.27 No 5 1 1 1 2 Yes
Overall- Fair. Seven sections outside design range. Good, but late initial faulting survey for 0219
Supplemental Sections - 1 PCC section.
0259 279 mm JPC; 4.27 m wide lane 5 1 1 1 2 Yes
  
Overall - Good.

Note: * Indicates seasonal monitoring section(s)
Bolded and Italic letters represent constructed values that are either not as designed or outside the design range. For slab thickness, the design range is set at (design value +/- 12.7 mm)

Key Observations and Deviations

The following key observations were noted in the project construction report:

Project Status Summary

Overall, this project site is in fair shape. The appendices to this report contain a significant amount of monitoring data. The following summarizes the status of this project:

Data from the Iowa SPS-2 site will require special analysis techniques to adjust for various design factors that were not constructed as planned.

Kansas SPS-2

The Kansas SPS-2 project site is located in the westbound lanes of I-70 in central Kansas, east of Abilene. I-70 is a rural interstate; the estimated AADT is 13,750, with 21.4 percent trucks. The initial annual ESALs in the design lane are estimated at 639,131. The roadway typically consists of two 3.66-m-wide lanes, an outside shoulder width of 3.05 m, and an inside shoulder width of 1.22 m. The SPS-2 project was included in the reconstruction of I-70. The existing pavement was concrete. The SPS-2 test sections were constructed on a tangent section of I-70 with vertical grades ranging from -2.48 percent to +2.11 percent. All test sections were constructed on fills.

An onsite weather monitoring station had not been installed before completion of the project. However, installation was scheduled to occur by 1994. A Toledo Model 9430TM high-speed WIM system was installed onsite.

Construction of this SPS-2 project was completed on July 1, 1992. The project site was opened to traffic on August 1, 1992. All required core sections were constructed. A supplemental State test section was also constructed. Table 44 summarizes key project information and data available for all the sections.

Table 44. Kansas SPS-2 project summary.

Project level information and data availability        Construction date:   07/01/1992

Climate - DF Data Availability Average Values As planned?

CLM: 17 years

AWS: 4 years

FI: 259°C days, Precip. 819 mm

FI: 254°C days, Precip. 698 mm

No
Traffic WIM: 1 year 639,131 ESALs/year (<200,000) Yes
Subgrade type Fine-grained soil for all. As designed? Varies

Flexural strength
14-day MPa

Design value Actual Averages Within 10%?

3.8
6.2

4.23
5.81

No
Yes

PCC tests available On average 98% completed for core sections

 

Section level key design factors and monitoring data availability

Key pavement design factors Monitoring data availability, No. of tests
ID Slab Thick. mm Base type With Drain Lane Width m As Design ? IRI FWD Distress Meet Min. Req'd?
  Actual Design Manual Photo. Faulting
0213 196 203 AGG No 3.66 Yes 7 5 2 2 2 No
0214 188   AGG No 4.27 No 8 6 2 2 2 No
0215 282 279 AGG No 4.27 Yes 8 7 2 2 2 No
0216 287   AGG No 3.66 Yes 8 5 2 2 2 No
0217 198 203 LCB No 3.66 Yes 8 5 2 2 2 No
0218 201   LCB No 4.27 Yes 8 6 2 2 2 No
0219 287 279 LCB No 4.27 Yes 8 5 2 2 2 No
0220 279   LCB No 3.66 Yes 8 5 2 2 2 No
0221 216 203 PATB Yes 3.66 Yes 8 5 2 2 1 No
0222 211   PATB Yes 4.27 Yes 8 5 2 2 2 No
0223 282 279 PATB Yes 4.27 Yes 8 5 2 2 2 No
0224 277   PATB Yes 3.66 Yes 8 5 2 2 2 No
Overall- Excellent, except for 0202. Good, except for deficient faulting data.
 
Supplemental Sections - 1 PCC section.
0259 305 mm doweled JPC (4.1 MPa mix) on 152 mm stabilized base and 152 mm modified Flyash subgrade, 3.66 m lane. 7 2 2 2 1 No
   Overall, Excellent, except for 0202.
Overall - Good, except for deficient faulting data.

Note: * Indicates seasonal monitoring section(s)
Bolded and Italic letters represent constructed values that are either not as designed or outside the design range. For slab thickness, the design range is set at (design value +/- 12.7 mm)

Key Observations and Deviations

The following key observations were noted in the project construction report:

Project Status Summary

Overall, this project site is in good shape. The appendices to this report contain a significant amount of monitoring data (except for faulting surveys). The following summarizes the status of this project:

The Kansas SPS-2 site exhibits some significant problems (data unavailable and construction deviations) that will cause difficulty in performance analysis.

Michigan SPS-2

The Michigan SPS-2 project site is located in the northbound and southbound lanes of U.S. 23 in southeastern Michigan, approximately 16 km west of Toledo. U.S. 23 is a rural principal arterial; in 1989 the AADT was 35,000, with 22 percent heavy trucks. The initial year ESALs was estimated at 1,346,045. The SPS-2 project was included in the reconstruction of 9.7 km of U.S. 23 in both the northbound and southbound lanes. Consear Road, a low-volume county road, bisects this SPS-2 site. Traffic counts taken in the northbound lanes reveal that traffic south of this interchange is 7 percent higher than traffic north of this interchange (AVC data only).

The roadway typically consists of two 3.66-m-wide lanes, an outside asphalt shoulder width of 3.05 m, and an inside shoulder width of 1.22 m. The SPS-2 sections were constructed on a portion of U.S. 23 that is relatively straight and flat. Vertical grades throughout the project area range from 0.00 percent to +0.55 percent. Most of the sections were constructed on shallow fills. However, sections 260214, 260218, and 260219 were constructed on deeper fills. All sections except 260214, 260218, and 260219 were constructed in tangent sections. Section 260214 was constructed in a superelevation transition area, while sections 260218 and 260219 were constructed on a full superelevation of 0.037 m/m.

WIM and AVC equipment were installed on U.S. 23 south of Consear Road. Only AVC equipment was installed north of Consear Road.

Reconstruction of U.S. 23 began in April 1993 with removal of the existing pavement layers. Construction of the subgrade progressed from mid-May through mid-June, and placement and compaction of the embankment was completed by mid-June. Undercuts were completed in Sections 260216, 260022, and 260223 due to unstable soil conditions revealed during proofrolling. These undercuts were 11 m wide and 0.3 m deep, but only extended for a partial length of each section. The undercuts were backfilled with embankment borrow clay. Base and subbase layer construction began by mid-June and was completed by mid-September 1993. Concrete paving commenced on September 13, 1993 (excluding control section) and was completed on September 21, 1993. The project site was opened to traffic in November 1993.

All required core sections were constructed, and one supplemental State test section was constructed. Table 45 summarizes key project information and data available for all the sections.

Table 45. Michigan SPS-2 project summary.

Project level information and data availability        Construction date:   11/01/1993

Climate - DF Data Availability Average Values As planned?

CLM: 17 years

AWS: 3 years

FI: 259°C days, Precip. 819 mm

FI: 254°C days, Precip. 698 mm

Yes
Traffic WIM: 5 years 1.346.0451 ESALs/year (>200,000) Yes
Subgrade type Fine-grained soil for all. As designed? Varies

Flexural strength
14-day MPa

Design value Actual Averages Within 10%?

3.8
6.2

4.27
6.71

No
Yes

PCC tests available On average 82% completed for core sections

 

Section level key design factors and monitoring data availability

Key pavement design factors Monitoring data availability, No. of tests
ID Slab Thick. mm Base type With Drain Lane Width m As Design ? IRI FWD Distress Meet Min. Req'd?
  Actual Design Manual Photo. Faulting
0213 218 203 AGG No 4.27 No 9 5 5 1 5 Yes
0214 226   AGG No 3.66 No 9 4 4 1 5 Yes
0215 284 279 AGG No 3.66 Yes 9 4 4 1 5 Yes
0216 290   AGG No 4.27 Yes 9 5 5 1 5 Yes
0217 216 203 LCB No 4.27 Yes 7 4 4 1 4 Yes
0218 180   LCB No 3.66 No 8 3 3 1 3 Yes
0219 277 279 LCB No 3.66 Yes 9 4 4 1 5 Yes
0220 282   LCB No 4.27 Yes 8 4 4 1 5 Yes
0221 208 203 PATB Yes 4.27 Yes 8 5 5 1 6 Yes
0222 213   PATB Yes 3.66 Yes 9 4 4 1 5 Yes
0223 279 279 PATB Yes 3.66 Yes 9 4 4 1 5 Yes
0224 284   PATB Yes 4.27 Yes 9 4 4 1 5 Yes
Overall- Excellent, except for 0202. Good, except for deficient faulting data.
 
Supplemental Sections - 1 PCC section.
0259 267 mm JRC on 102 mm OGDB on 76 mm aggregate base. 9 4 4 1 4 Yes
    
Overall - Excellent

Note: * Indicates seasonal monitoring section(s)
Bolded and Italic letters represent constructed values that are either not as designed or outside the design range. For slab thickness, the design range is set at (design value +/- 12.7 mm)

Key Observations and Deviations

For sections 260213 through 260220, the moisture content of the subgrade was not maintained within the range of 85 to 120 percent of the optimum moisture content. Moderate-to-severe desiccation cracks (up to 50.8 mm width and 254 mm depth) developed in the subgrade, which was compacted dry of optimum since the completed embankment was exposed to hot and dry weather conditions before construction of the overlying base or subbase layers. This occurred on all sections except those constructed with PATB. Cracking did not occur on PATB sections because the DGAB was placed soon after completion of the embankment.

Michigan DOT required the contractor to scarify the desiccated subgrade sections and recompact severely desiccated subgrade to SPS-2 requirements.

Project Status Summary

Overall, this project site is in good shape except for the concrete strength (the high and low strengths are practically the same after 1 year). The appendices to this report contain a significant amount of monitoring data. The following summarizes the status of this project:

Data from the Michigan SPS-2 site will require special analysis techniques to adjust for various design factors that were not constructed as planned.

Nevada SPS-2

The Nevada SPS-2 project site is located in north central Nevada, approximately 8 km west of Battle Mountain, in the outer eastbound lane of I-80. The SPS-2 sections extend from station 1596+65 to station 64+50 (milepost 223.7). The initial annual ESALs were estimated to be 812,944.

The construction work on this segment of I-80 consisted of removing the existing AC surfacing, cement-treated base (CTB), DGAB, and embankment. The original subgrade was stabilized with lime, and the embankment was replaced. The SHRP structural sections were then placed on top of the embankment. The terrain surrounding the test sections is generally flat with minimal ground cover.

All required core sections were constructed. One supplemental State section was also constructed. Table 46 summarizes key project information and data available for all the sections.

Table 46. Nevada SPS-2 project summary.

Project level information and data availability        Construction date:   11/01/1993

Climate - DF Data Availability Average Values As planned?

CLM: 17 years

AWS: 5 years

FI: 276°C days, Precip. 819 mm

FI: 181°C days, Precip. 698 mm

Yes
Traffic WIM: 1 year 1.346.0451 ESALs/year (>200,000) Yes
Subgrade type Fine-grained soil for all. As designed? Varies

Flexural strength
14-day MPa

Design value Actual Averages Within 10%?

3.8
6.2

3.60
5.41

Yes
No

PCC tests available On average 82% completed for core sections

 

Section level key design factors and monitoring data availability

Key pavement design factors Monitoring data availability, No. of tests
ID Slab Thick. mm Base type With Drain Lane Width m As Design ? IRI FWD Distress Meet Min. Req'd?
  Actual Design Manual Photo. Faulting
0213 234 203 AGG No 3.66 No 4 6 2 1 2 Yes
0214 208   AGG No 4.27 No 2 4 2 1 2 Yes
0215 302 279 AGG No 4.27 Yes 4 3 2 1 2 Yes
0216 300   AGG No 3.66 Yes 8 15 8 1 8 Yes
0217 216 203 LCB No 3.66 Yes 4 5 2 1 2 Yes
0218 198   LCB No 4.27 No 2 3 2 1 2 Yes
0219 277 279 LCB No 4.27 Yes 4 2 2 1 2 Yes
0220 279   LCB No 3.66 Yes 4 2 2 1 2 Yes
0221 226 203 PATB No 3.66 Yes 4 6 2 1 3 Yes
0222 257   PATB Yes 4.27 Yes 4 5 3 1 3 Yes
0223 287 279 PATB Yes 4.27 Yes 4 4 3 1 2 Yes
0224
NA - Section taken out of the SPS-2 study from the beginning.
Overall- Excellent, except for 0202. Good, except for deficient faulting data.
 
Supplemental Sections - 1 PCC section.
0259 267 mm JRC on 38 mm leveling course, 27.6 MPa ± 20% 14-day compressive strength. 4 2 2 1 2 Yes
   
Overall - Excellent.

Note: * Indicates seasonal monitoring section(s)
Bolded and Italic letters represent constructed values that are either not as designed or outside the design range. For slab thickness, the design range is set at (design value +/- 12.7 mm)

Key Observations and Deviations

The following key observations were noted in the project construction report:

Project Status Summary

Overall, this project site is in poor shape. The appendices to this report contain a significant amount of monitoring data. The following summarizes the status of this project:

Data from the Nevada SPS-2 site will require special analysis techniques to adjust for various design factors that were not constructed as planned. In particular, slab cracking will not be able to be evaluated in comparison with other sites; this may cause other problems that will complicate performance analysis.

North Carolina SPS-2

The North Carolina SPS-2 project site is located in the southbound lanes of U.S. 23, near Lexington, NC. U.S. 52 is a rural principal arterial with an AADT of 23,500 to 26,100 (1994) and 13 percent heavy trucks. The annual ESALs was estimated at 750,902. The SPS-2 project was included in the construction of 7.8 km of U.S. 52 in both the northbound and southbound lanes. U.S. 64 bisects this SPS-2 site. All test sections except section 370204 are located north of the U.S. 64 interchange. This section will be monitored with AVC equipment to determine if the traffic south of U.S. 64 is different from traffic to the north of U.S. 64.

The roadway typically consists of two 3.66-m-wide lanes, an outside shoulder width of 3.05 m, and an inside width of 1.22 m. The shoulders were constructed with econocrete instead of the SPS-2 required flexible bituminous design. The majority of SPS-2 test sections were constructed on tangent sections with slight grades. Sections that include a 203-mm PCC slab were constructed as add-on lanes adjacent to the mainline travel lane. This parallel roadway section was constructed through some deep cuts and high embankments.

Seasonal monitoring sensors, strain gauges, and linear variable differential transducers were installed on several test sections. Reconstruction began in 1992 with earthwork grading.

All required core sections were constructed. Two supplemental State test sections were also constructed. Table 47 summarizes key project information and data available for all the sections.

Table 47. North Carolina SPS-2 project summary.

Project level information and data availability        Construction date:   11/01/1993

Climate - WNF Data Availability Average Values As planned?

CLM: 17 years

AWS: 5 years

FI: 47°C days, Precip. 1,151 mm

FI: 67°C days, Precip. 1,199 mm

Yes
Traffic WIM: 5 years 750,902 ESALs/year (>200,000) Yes
Subgrade type Fine-grained soil for all. As designed? Varies

Flexural strength
14-day MPa

Design value Actual Averages Within 10%?

3.8
6.2

N/A
N/A

N/A
N/A

PCC tests available On average 82% completed for core sections                   Fair

 

Section level key design factors and monitoring data availability

Key pavement design factors Monitoring data availability, No. of tests
ID Slab Thick. mm Base type With Drain Lane Width m As Design ? IRI FWD Distress Meet Min. Req'd?
  Actual Design Manual Photo. Faulting
0201* 229 203 AGG No 3.66 No 10 25 9 1 10 Not quite
0202 259   AGG No 4.27 No 8 2 1 1 2 Not quite
0203 284 279 AGG No 4.27 Yes 8 2 1 1 2 Not quite
0204 284   AGG No 3.66 Yes 7 2 1 1 1 Not quite
0205 203 203 LCB No 3.66 Yes 8 3 1 1 2 Not quite
0206 213   LCB No 4.27 No 8 2 1 1 2 Not quite
0207 295 279 LCB No 4.27 Yes 8 2 1 1 2 Not quite
0208 284   LCB No 3.66 Yes 7 3 1 1 1 Not quite
0209 218 203 PATB No 3.66 Yes 8 5 5 1 6 Not quite
0210 213   PATB Yes 4.27 Yes 8 2 1 1 2 Not quite
0211 290 279 PATB Yes 4.27 Yes 8 2 1 1 2 Not quite
0212* 277 PATBYes3.66 Yes 83111Not quite
Overall- Fair, four sections outside design range. Overall - Good, except for late initial surveys.
Supplemental Sections - 2 PCC sections.
0259 254 mm JRC on 102 mm PATB on 25.4 mm AC on 203 mm lime-stabilized subgrade. 7 2 1 1 2 Yes
0260 279 mm JRC on 2.54 cm AC on 127 mm BTB on 203 mm cement-treated subgraded. 8 2 1 1 2 Yes
    
Overall - Excellent.

Note: * Indicates seasonal monitoring section(s)
Bolded and Italic letters represent constructed values that are either not as designed or outside the design range. For slab thickness, the design range is set at (design value +/- 12.7 mm)

Key Observations and Deviations

The following key observations were noted in the project construction report:

Project Status Summary

Overall, this project site is in fair shape. The appendices to this report contain a significant amount of monitoring data. The following summarizes the status of this project:

North Dakota SPS-2

The North Dakota SPS-2 project is located in the eastbound lanes of I-94 in eastern North Dakota, west of Fargo. I-94 is a rural interstate; in 1996 the AADT was 8,310, with 12 percent trucks. The initial annual ESALs in the design lane are estimated at 246,000.

The roadway typically consists of two 3.66-m-wide lanes, an outside shoulder width of 3.05 m, and an inside shoulder width of 1.22 m. The SPS-2 project was included in the reconstruction of a concrete pavement that included 229-mm concrete on 76-mm aggregate base on 152- to 229-mm aggregate subbase. The SPS-2 test sections were constructed on a portion of I-94 that is very flat and relatively straight. All sections except North Dakota supplemental sections 380260 and 360261 were constructed on tangent sections.

Several delays were encountered during subgrade preparation, due to the presence of extremely wet clayey soils. Construction of individual test sections was completed on October 1, 1994, and the pavements were opened to traffic on November 1, 1994.

All required core sections were constructed. Six supplemental State test sections were constructed. Table 48 summarizes key project information and data available for all the sections.

Table 48. North Dakota SPS-2 project summary.

Project level information and data availability        Construction date:   11/01/1994

Climate - DF Data Availability Average Values As planned?

CLM: 17 years

AWS: 5 years

FI: 1,313°C days, Precip. 545 mm

FI: 1,162°C days, Precip. 534 mm

Yes
Traffic WIM: 0 year N/A N/A
Subgrade type Fine-grained soil for all. As designed? Varies

Flexural strength
14-day MPa

Design value Actual Averages Within 10%?

3.8
6.2

N/A
N/A

N/A
N/A

PCC tests available On average 82% completed for core sections                   Fair

Section level key design factors and monitoring data availability

Key pavement design factors Monitoring data availability, No. of tests
ID Slab Thick. mm Base type With Drain Lane Width m As Design ? IRI FWD Distress Meet Min. Req'd?
  Actual Design Manual Photo. Faulting
0213 208 203 AGG No 4.27 No 2 2 2 1 3 Not quite
0214 201   AGG No 3.66 No 2 2 1 1 2 Not quite
0215 279 279 AGG No 3.66 Yes 2 2 1 1 1 Not quite
0216 284   AGG No 4.27 Yes 2 2 1 1 1 Not quite
0217 201 203 LCB No 4.27 Yes 2 1 2 1 3 Not quite
0218 201   LCB No 3.66 No 2 1 1 1 2 Not quite
0219 277 279 LCB No 3.66 Yes 2 1 1 1 2 Not quite
0220 277   LCB No 4.27 Yes 2 1 1 1 2 Not quite
0221 206 203 PATB No 4.27 Yes 2 1 2 1 3 Not quite
0222 208   PATB Yes 3.66 Yes 2 1 1 1 2 Not quite
0223 282 279 PATB Yes 3.66 Yes 2 1 1 1 2 Not quite
0224 274   PATB Yes 4.27 Yes 2 1 1 1 2 Not quite
Overall- Fair, four sections outside design range. Overall - Good, except for late initial surveys.
Supplemental Sections - 6 PCC sections.
0259 254 mm doweled JPC (ND mix) on 203 mm salve with skewered joints and 3.66 m lanes. 2 1 1 1 2 Yes
0260 279 mm doweled JPC (ND mix) on DGAB with skewed joints and 4.27 m lanes. 2 2 1 1 1 Yes
0261 279 mm doweled JPC (3.8 MPa MR) on DGAB with skewed joints and 3.66 m lanes. 2 2 1 1 1 Yes
0262 279 mm doweled JPC on LCB with skewed joints (various lengths) and 4.27 m lanes. 2 1 1 1 2 Yes
0263 279 mm doweled JPC on PATB with random skewed joints and 3.66 m lanes. 2 1 1 1 2 Yes
0264 279 mm doweled JPC on PATB with skewed joints and 4.27 m lanes. 2 1 1 1 2 Yes
   
Overall - Good.

Note: * Indicates seasonal monitoring section(s)
Bolded and Italic letters represent constructed values that are either not as designed or outside the design range. For slab thickness, the design range is set at (design value +/- 12.7 mm)

Key Observations and Deviations

The following key observations were noted in the project construction report:

Project Status Summary

Overall, this project site is in good shape. The appendices to this report contain a significant amount of monitoring data. The following summarizes the status of this project:

The North Dakota SPS-2 site does not appear to exhibit significant problems that will cause difficulty in performance analysis.

Ohio SPS-2

The Ohio SPS-2 project site is located in the northbound lanes of U.S. 23 in central Ohio, approximately 48 km north of Columbus. U.S. 23 is a rural principal arterial; in 1994 the AADT was 20,210, with 12 percent trucks. The initial annual ESALs are estimated at 600,000. The roadway typically consists of two 3.66-m-wide lanes, an outside asphalt shoulder width of 3.05 m, and an inside asphalt shoulder width of 1.22 m. The SPS-2 test sections were constructed on a portion of U.S. 23 that is relatively straight and flat.

Permanent WIM equipment consisting of weigh plates was mounted in each lane of U.S. 23. Additional instrumentation was installed in the SPS-2 project area to collect environmental data, including temperatures of individual pavement layers and moisture freeze/thaw conditions of the subbase and subgrade layers. The load-response monitoring instrumentation that was installed included strain, deflection, and pressure gauges.

Construction started in the fall of 1994 with the subgrade preparation. Individual test sections were completed by October 1995, and the project was open to traffic on October 1, 1996. All required core sections were constructed. Seven supplemental State test sections were also constructed. Table 49 summarizes key project information and data available for all the sections.


Table 49. Ohio SPS-2 project summary.

Project level information and data availability        Construction date:   09/01/1996

Climate - WF Data Availability Average Values As planned?

CLM: 17 years

AWS: 6 years

FI: 375°C days, Precip. 972 mm

FI: 121°C days, Precip. 730 mm

Yes
Traffic WIM: 0 year N/A N/A
Subgrade type Fine-grained soil for all. As designed? Varies

Flexural strength
14-day MPa

Design value Actual Averages Within 10%?

3.8
6.2

4.72
4.23

No
No

PCC tests available On average 96% completed for core sections

Section level key design factors and monitoring data availability

Key pavement design factors Monitoring data availability, No. of tests
ID Slab Thick. mm Base type With Drain Lane Width m As Design ? IRI FWD Distress Meet Min. Req'd?
  Actual Design Manual Photo. Faulting
0201 201 203 AGG No 4.27 No 4 5 1 1 2 Yes
0202 211   AGG No 3.66 No 4 4 1 1 2 Yes
0203 277 279 AGG No 3.66 Yes 4 3 1 1 2 Yes
0204* 282   AGG No 4.27 Yes 8 15 1 1 3 Yes
0205 203 203 LCB No 4.27 Yes 4 4 1 1 2 Yes
0206 201   LCB No 3.66 No 4 3 1 1 2 Yes
0207 282 279 LCB No 3.66 Yes 4 3 1 1 2 Yes
0208 279   LCB No 4.27 Yes 4 3 1 1 2 Yes
0209 206 203 PATB No 4.27 Yes 4 5 1 1 2 Yes
0210 203   PATB Yes 3.66 Yes 4 5 1 1 2 Yes
0211 290 279 PATB Yes 3.66 Yes 4 4 1 1 2 Yes
0212 269   PATB Yes 4.27 Yes 4 4 1 1 2 Yes
Overall- Fair, four sections outside design range. Overall - Excellent.
Supplemental Sections - 7 PCC sections.
0259 279 mm JPC (3.8 MPa MR) on 152 mm DGAB 3 4 1 0 2 Yes
0260 279 mm JPC (3.8 MPa MR) on 102 mm PATB on 1022 mm DGAB 4 4 1 1 2 Yes
0261 279 mm JPC (3.8 MPa MR) on 102 mm CTPB on 1022 mm DGAB 4 3 1 1 2 Yes
0262 279 mm JPC on 102 mm CTPB on 102 mm DGAB 3 3 1 1 2 Yes
0263 279 mm JPC on 152 mm DGAB 3 3 1 0 2 Yes
0264 279 mm JPC on 152 mm DGAB 4 2 1 0 2 Yes
0265 279 mm JPC (3.8 MPa MR) on 102 mm PATB on 102 mm DGAB 4 4 1 1 2 Yes
    Overall - Excellent

Note: * Indicates seasonal monitoring section(s)
Bolded and Italic letters represent constructed values that are either not as designed or outside the design range. For slab thickness, the design range is set at (design value +/- 12.7 mm)

Key Observations and Deviations

The following key observations were noted in the project construction report:

Project Status Summary

Overall, this project site is in very good shape. The appendices to this report contain a significant amount of monitoring data. The following summarizes the status of this project:

The Ohio SPS-2 site does not appear to exhibit significant problems that will cause difficulty in performance analysis.

Washington SPS-2

The Washington SPS-2 project site is located in the northbound lanes of S.R. 395 in eastern Washington, 4.8 km south of Ritzville. S.R. 395 is an urban principal arterial; in 1993 the AADT was 18,000. The initial annual ESALs are estimated at 461,759. The SPS-2 project includes construction of two new northbound lanes and the upgrade of S.R. 395 to a four-lane divided highway. The new lanes were constructed uphill from the existing lanes. Two sections were located in a cut (section 530203 and 530259), while all other sections were located on fills. The roadway design for this project consists of two 3.66-m-wide lanes, an outside shoulder width of 3.05 m, and an inside shoulder width of 1.22 m.

The initial SPS-2 sections were constructed on a horizontal curve to the left from the beginning of the SPS-2 project to Station 2050+00. Section 530201 is partially located within a horizontal curve and partially located within a superelevation runout area. Sections 530205, 530206, 530207, and 530208 are on tangent, while the remaining sections were constructed on a curve to the left. The maximum superelevation rate for this curve is 3 percent. Vertical grades range from 0.14 percent to 3 percent.

Construction of the SPS-2 site started in June 1993 with the removal of the existing pavement. Construction of individual test sections was completed by November 1, 1995.

All required core sections were constructed, as was one supplemental State test section. Table 50 summarizes key project information and data available for all the sections.

Table 50. Washington SPS-2 project summary.

Project level information and data availability        Construction date:   11/01/1995

Climate - DF Data Availability Average Values As planned?

CLM: 17 years

AWS: 5 years

FI: 265°C days, Precip. 308 mm

FI: 138°C days, Precip. 355 mm

Yes
Traffic WIM: 2 years N/A Yes
Subgrade type Fine-grained soil for all. As designed? Varies

Flexural strength
14-day MPa

Design value Actual Averages Within 10%?

3.8
6.2

3.34
5.7 23

No
Yeso

PCC tests available On average 96% completed for core sections

Section level key design factors and monitoring data availability

Key pavement design factors Monitoring data availability, No. of tests
ID Slab Thick. mm Base type With Drain Lane Width m As Design ? IRI FWD Distress Meet Min. Req'd?
  Actual Design Manual Photo. Faulting
0201 221 203 AGG No 3.66 No 4 5 3 0 3 Yes
0202 211   AGG No 4.27 Yes 4 5 3 0 3 Yes
0203 282 279 AGG No 4.27 Yes 4 5 3 0 3 Yes
0204* 284   AGG No 3.66 Yes 4 5 3 0 3 Yes
0205 216 203 LCB No 3.66 Yes 4 4 3 0 3 Yes
0206 218   LCB No 4.27 No 4 4 3 0 3 Yes
0207 282 279 LCB No 4.27 Yes 4 4 3 0 3 Yes
0208 284   LCB No 3.66 Yes 4 4 3 0 3 Yes
0209 229 203 PATB No 3.66 No 4 5 3 0 3 Yes
0210 211   PATB Yes 4.27 Yes 4 5 3 0 3 Yes
0211 300 279 PATB Yes 4.27 No 4 5 3 0 3 Yes
0212 287   PATB Yes 3.66 Yes 4 5 3 0 3 Yes
Overall- Fair, four sections outside design range. Overall - Excellent.
Supplemental Sections - 1PCC section.
0259 Undoweled 254 mm JPC (4.5 MPa MR) on 76 mm ATB on 51 mm crushed surfacing base courses; 4.27 m lane. 4 4 3 0 3 Yes
    Overall - Excellent

Note: * Indicates seasonal monitoring section(s)
Bolded and Italic letters represent constructed values that are either not as designed or outside the design range. For slab thickness, the design range is set at (design value +/- 12.7 mm)

Key Observations and Deviations

The following key observations were noted in the project construction report:

Project Status Summary

Overall, this project site is in good shape. The appendices to this report contain a significant amount of monitoring data. The following summarizes the status of this project:

The Washington SPS-2 site does not appear to exhibit significant problems that will cause difficulty in performance analysis.

Wisconsin SPS-2

The Wisconsin SPS-2 project site is located on the westbound and eastbound lanes of Wisconsin State Highway 29 (STH-29), a rural arterial road, in Marathon County, WI. This site is roughly 5.6 km east of Hatley, WI. In 1995, the ADT was 6,650 vehicles with a truck distribution of 29.5 percent. The initial annual ESALs were estimated at 500,000. The site is located on a 0.3 percent downgrade with four curves in between. The maximum curve does not exceed 2 degrees with a superelevation equal to 0.055 l/l. The lanes are 3.66 m and 4.27 m wide, with an outside shoulder of 3.05 m and an inside shoulder of 1.83 m.

A WIM system was installed on August 29, 1997. The WIM equipment used was a DAW-1000 bending plate unit manufactured by PAT Equipment.

The subgrade preparation for this project began in early June 1997, and paving operations were completed by mid-October 1997.

All required core sections were constructed. Eight supplemental State test sections were also constructed. Table 51 summarizes key project information and data available for all the sections.


Table 51. Wisconsin SPS-2 project summary.

Project level information and data availability        Construction date:   10/01/1997

Climate - DF Data Availability Average Values As planned?

CLM: 0 year

AWS: 0 year

N/A

N/A

N/A
Traffic WIM: 0 year N/A N/A
Subgrade type Fine-grained soil for all. As designed? Varies

Flexural strength
14-day MPa

Design value Actual Averages Within 10%?

3.8
6.2

4.37
6.09

No
Yes

PCC tests available On average 71% completed for core sections

Section level key design factors and monitoring data availability

Key pavement design factors Monitoring data availability, No. of tests
ID Slab Thick. mm Base type With Drain Lane Width m As Design ? IRI FWD Distress Meet Min. Req'd?
  Actual Design Manual Photo. Faulting
0213 NA 203 AGG No 4.27 NA 3 1 1 0 1 Yes
0214   AGG No 3.66 3 1 1 0 2 Yes
0215 279 AGG No 3.66 3 1 1 0 1 Yes
0216   AGG No 4.27 3 1 1 0 1 Yes
0217 203 LCB No 4.27 3 1 1 0 1 Yes
0218   LCB No 3.66 3 1 1 0 1 Yes
0219 279 LCB No 3.66 3 1 1 0 1 Yes
0220   LCB No 4.27 3 1 1 0 1 Yes
0221 203 PATB No 4.27 3 1 1 0 1 Yes
0222   PATB Yes 3.66 3 1 1 0 1 Yes
0223 279 PATB Yes 3.66 3 1 1 0 1 Yes
0224   PATB Yes 4.27 3 1 1 0 1 Yes
Overall- Not enough data. Overall - Excellent.
Supplemental Sections - 8 PCC sections.
0259 279 mm JPC (3.8 MPa MR) on 152 mm DGAB 3 1 1 0 1 Yes
0260 279 mm JPC (3.8 MPa MR) on 152 mm DGAB, with alternative dowel bar placement 3 1 1 0 1 Yes
0261 203 mm JPC (3.8 MPa MR) on 102 mm OGDB on 102 mm DGAB 3 1 1 0 1 Yes
0262 203 mm JPC (6.3 MPa MR) on 152 mm DGAB, with tied concrete shoudler 3 1 1 0 1 Yes
0263 203-279 mm JPC (3.8 MPa MR) on 152 mm DGAB, variable pavement thickness 3 1 1 0 1 Yes
0264 279 mm JPC (3.8 MPa MR) on 152 mm DGAB, with composite dowels 3 1 1 0 1 Yes
0265 279 mm JPC (3.8 MPa MR) on 152 mm DGAB, with stainless steel dowels. 3 1 1 0 1 Yes
0266   3 0 0 0 0 Yes
   
Overall - Excellent

Note: * Indicates seasonal monitoring section(s)
Bolded and Italic letters represent constructed values that are either not as designed or outside the design range. For slab thickness, the design range is set at (design value +/- 12.7 mm)

Key Observations and Deviations

The following key observations were noted in the project construction report:

Project Status Summary

Overall, this project site is in good shape, given the available data. The appendices to this report contain a significant amount of monitoring data as well as significant materials testing data. However, site condition data, pavement structure data, and other key pavement design feature data are deficient at this time. Not enough data exist in the database to assess the designed versus constructed status of the project.

The following summarizes the status of this project:

 

Previous | Table of Contents | Next