U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000


Skip to content
Facebook iconYouTube iconTwitter iconFlickr iconLinkedInInstagram

Federal Highway Administration Research and Technology
Coordinating, Developing, and Delivering Highway Transportation Innovations

Report
This report is an archived publication and may contain dated technical, contact, and link information

Federal Highway Administration > Publications > Research > Structures > Long-Term Performance of Epoxy-Coated Reinforcing Steel in Heavy Salt-Contaminated Concrete

Publication Number: FHWA-HRT-04-090
Date: JUNE 2004

Previous | Table of Contents | Next

Chapter 1. INTRODUCTION AND PROJECT HISTORY

The Federal Highway Administration (FHWA) research project, Corrosion Resistant Reinforcing for Concrete Components, began in 1993. The objective of the proposed study was to develop cost-effective new breeds of organic, inorganic, ceramic, and metallic coatings, as well as metallic alloys that could be utilized on or as reinforcement for embedment in portland cement concrete. It was required that new coatings and alloys should provide significantly more corrosion-resistant reinforcement than the fusion-bonded epoxy-coated reinforcement that has been used in the United States since 1975 and also the corrosion-free design life shall be 75 to 100 years when exposed to adverse environments.

The research was aimed at developing new reinforcement materials and systems that minimally damage the coating system during (1) coating application, (2) fabrication bending operations, and (3) shipment to and installation at the jobsite. It was required that alloys have superior characteristics, and that thin-clad conventional steel resist damage. The coating systems had to have superior physical and chemical properties that remain undamaged by long-term exposure to ultraviolet radiation, high temperatures, salt-laden atmosphere, and other environmental conditions during long-term storage before casting them in concrete.

On March 3, 1993, 3M informed the researchers that Scotchkote 213 (3M 213TM ) would no longer be manufactured, because of rulings from the U.S. Environmental Protection Agency (EPA). The 3M 213 epoxy-coated bars had been used almost exclusively in the bridges in the United States from about 1980 to 1990. Based on this change, it became crucial to secure bars coated with the 3M 213 for the in-concrete tests that were to begin in 1995.

An invitational letter for submitting candidate bars was sent to 46 companies on May 17 and 18, 1993. It was anticipated that numerous new candidate organic coatings would be submitted for testing, because the 3M 213 epoxy coating material was no longer available, and new steel surface pretreatments used before coating the bars were being considered. As a result, researchers used a 30-day prescreening test program to screen these numerous organic-coated candidate bar systems, with and without special steel surface pretreatments. At that time, the organic coaters agreed that pretreatment would improve coating adhesion strength and long-term performance.

The 1993–1998 research program involved testing more than 52 different organic, inorganic, ceramic, and metallic coatings on steel bars, as well as solid metallic bars. Specifically, they included epoxy-coated, other polymer-coated, ceramic-coated, galvanized-clad, epoxy-coated galvanized-clad, stainless steel-clad, nickel-clad, copper-clad, corrosion resistance alloy-clad, inorganic silicate-clad, solid corrosion-resistance alloy steel, solid aluminum-bronze, solid stainless steels, and solid titanium reinforcing bars.

Prescreening tests on organic-coated bars were conducted from 1993 to 1995. These screening tests are chronicled in two reports: The Performance of Bendable and Nonbendable Organic Coatings for Reinforcing Bars in Solution and Cathodic Disbondment Tests [1] and the related phase II screening test report.[2] Screening tests were also conducted from 1993 to 1995 on metallic-clad and solid metallic bars. This research studied 10 types of metal clad bars and 10 types of solid metal bars. The performance of various inorganic-, ceramic-, and metallic-clad bars and solid corrosion-resistant bars is discussed in the 1996 FHWA report, The Corrosion Performance of Inorganic-, Ceramic-, and Metallic-Clad Reinforcing Bars and Solid Metallic Reinforcing Bars in Accelerated Screening Tests.[3]

Based on screening tests as detailed in the three reports mentioned above, 12 bar types were selected for the 96-week in-concrete testing. The 141 reinforced concrete slab specimens using 12 different bar types were made and were exposed to the 96-week SE testing. These tests were completed in late 1997, and the final report was published in a 1998 FHWA report, Corrosion Evaluation of Epoxy-Coated, Metallic-Clad and Solid Metallic Reinforcing Bars in Concrete.[4]

The 96-week SE testing involved with the following wetting and drying cycles:

The 15 percent salt solution was chosen to represent the high salt concentrations occurring on inland bridge structures from deicing salts. The long ponding period was utilized to simulate a sustained period of submersion or long periods of high concrete moisture common in winter months or in marine structures. This 24-week cycle was repeated four times for a total test period of 96 weeks.

Configuration of the concrete slabs used in this FHWA study measured 30.5 x 30.5 x 17.8 centimeters (cm) (12 x 12 x 7 inches) and contained two layers of 29.2-cm (11.5-inch) long and 1.6-cm (5/8-inch) diameter reinforcement, as shown in figure 1. The top mat acted as a macroanode and contained either two straight or two bent reinforcing bars, while the bottom mat was a macrocathode that contained four straight reinforcing bars. The top mat bar was connected to two bottom mat bars through a 10Wresistor. A clear cover of 25.4 millimeters (mm) (1.0 inch) was used in all specimens. This cover conforms to either the American Association of State Highway and Transportation Officials- (AASHTO) specified bottom-of-slab cover, or possible minimum in-place clear cover, allowing for construction tolerances when 3.8- to 5.0-cm (1.5- to 2.0-inch) cover requirements are specified. While most previous published corrosion studies used only crack-free concrete slabs, some of the test slabs used in this project contained the cracks directly over a top mat rebar to simulate cracks observed on actual bridge decks. Table 1 presents the concrete mix design data for the test slab concrete.


The drawing shows three test slabs that measure 300 by 300 millimeters and 175 millimeters high. The cover is 25 millimeters. The first slab shows the cathode connected to the rebars on the top and bottom surface with cracks at the top surface. The second sample shows bent bars on the top surface with the left bar connecting to a cathode and rebars at the left bottom surface. The third drawing is a cutaway that shows two straight bars on the top surface and four on the bottom, all connected with a cathode. The top surface also has a dike to collect and hold water.

1 inch = 25.4 mm

Figure 1. Configuration of test slab

 

Table 1. Mix properties of concrete used

Concrete Property

Mean Value of 30 Batches

Standard Deviation

Cement, kg/m3 (lb/yd3)

370 (623)

3.3 (5.56)

Air, percent

5.6

0.51

Slump, mm (inch)

167 (6.58)

31.7 (1.25)

Unit wt., kg/m3 (lb/yd3)

2315 (144.5)

21.0 (1.31)

w/c

0.47

0.01

28-day compressive strength, MPa (psi)

39.3 (5,700)

2.7 (403)


Table 2 shows the chloride concentration data collected during the 96-week FHWA study, and figure 2 shows the estimated chloride concentration at the top mat depth (2.5 cm or 1.0 inch) with time. It is clear that rapid migration of chloride is achieved through the SE testing. At the sixth week of testing, chloride concentration at the 2.5 cm (1.0 inch) depth exceeded2.97 kg/m3 (5 pounds (lb)/yard (yd)3) (0.137 percent or 1,370 parts per million (ppm)), which was greater than 3 times the known chloride threshold (0.71 to 0.89 kg/m3 (1.2 to1.5 lb/yd3) or 300 to 350 ppm) for uncoated American Society for Testing and Materials (ASTM) A615 bar.

Table 2. Acid-soluble chloride concentrations (percent by weight of sample)

Test Period
(Weeks)

Nominal Sampling Depth (inch)

Estimated Chloride at
Top Mat

0.5

1.25

2.0

2.5

Percent by
Weight of
Sample

lb/yd3

6

0.347

0.032

< 0.007

< 0.007

0.137

5.3

12

0.551

0.048

0.011

< 0.007

0.216

8.4

24

0.562

0.231

0.031

< 0.007

0.314

12.2

48

0.63

0.484

0.152

0.012

0.533

20.8

72

0.86

0.489

0.204

0.04

0.613

23.9

96

0.873

0.721

0.485

0.314

0.772

30.1

1 inch = 25.4 mm
1 lb/yd3 = 0.59 kg/m3

 

This graph charts the chloride concentration to a 25.4-millimeter (1.0-inch) depth expressed in percent by weight of the sample; Y equals 0.0456X to the 0.6186 power and R squared equals 0.9964. The vertical axis ranges from 0 to 0.9. The horizontal axis is time ranging from 0 to 96 weeks. The graph depicts rapid migration of chloride that ranges from 0.137 percent at 6 weeks to 0.775 percent at 96 weeks.
Figure 2. Estimated chloride accumulation at 25.4 mm (1.0 inch) depth with time in the concrete test slab

Table 3 summarizes the performance data of seven different rebar materials tested under the 96-week FHWA test program. Figures 3 and 4 show average macrocell current and mat-to-mat AC resistance data of each type reinforcing bar in table 3. Furthermore, table 4 classifies average macrocell current and mat-to-mat AC resistance of the ECR slabs for each coating type. The 96-week FHWA study concluded that the best ECR performance was obtained when the bars were tested in a straight condition, with 0.004 percent damage in uncracked concrete using an ECR cathode in the bottom mat. Researchers also found that there was a clear relationship between the mat-to-mat resistance values of the ECRs and their corrosion performance. Better corrosion protection was provided by those coating systems that had high electrical resistance, that is, the corrosion was strongly dependent on the amount of damage in the coating.[4]

Table 3. Summary of corrosion performance of different reinforcing bar materials under 96-week SE testing[4]

Bar Type

Slab Configuration

Macrocell Current

Mat-to-Mat Resistance

Slab Condition
after 96 Weeks

Average
Macrocell
Current over
96 Weeks (uA)

Percentage of Black Bar

Average AC
Current over
96 Weeks (ohm)

Percentage of Black Bar

ASTM A615 Black

Uncracked

352.5

100

243

100

All slabs cracked

Precracked

405.3

100

263

100

Six Different Epoxy-Coated Bar Types

Uncracked

0.2 to 190.7

0.06 to 54.1

704 to 659,069

290 to 271,222

Some slabs cracked or exhibited rust staining

Precracked

1.4 to 191.8

0.35 to 47.3

591 to 103,722

225 to 39,438

Galvanized Bar

Uncracked

207.9

59.0

413

170.0

All slabs cracked

Precracked

294.1

72.5

318

120.9

Zinc Alloy-Clad Bar

Uncracked

126.7

35.9

385

158.4

One slab cracked

Precracked

273

67.3

325

123.6

Slabs cracked

Copper-Clad Bar

Uncracked

3.7

1.0

584

240.3

No damage observed

Precracked

14.2

3.5

491

186.7

304 Stainless Steel Bar

Uncracked

0.5

0.1

602

247.7

No damage observed

Precracked

11.3

2.8

566

215.2

Minor staining on concrete surface

316 Stainless Steel Bar

Uncracked

0.5

0.1

476

195.9

No damage observed

Precracked

0.5

0.1

429

163.1


The bar chart compares the average macrocell current for uncracked and precracked slabs for eight different bar types. The vertical axis is average current ranging from 0.01 to 1000. The horizontal scale is the uncracked and precracked bar types: ASTM A615 black, good performing epoxy-coated, poor performing epoxy-coated, galvanized, zinc alloy-clad, copper-clad, 304 stainless steel and 316 stainless steel. The uncracked good performing epoxy-coated and stainless steel bars had the lowest averages of 0.5 while the ASTM A615 precracked black bar had the highest average of 405. The poor performing epoxy-coated, galvanized and zinc alloy-clad bars also had relatively high averages.
Figure 3. Average macrocell current data of eight reinforcing bar materials for 96-week SE tests
The bar chart compares the average mat-to-mat AC resistance for uncracked and precracked slabs for eight different bar types. The vertical axis is average mat-to-mat AC resistance ranging from 1 to 1,000,000 ohms. The horizontal scale is the uncracked and precracked bar types: ASTM A615 black, good performing epoxy-coated, poor performing epoxy-coated, galvanized, zinc alloy-clad, copper-clad, 304 stainless steel and 316 stainless steel. The good performing epoxy-coated bars had the highest resistance between 100,000 and 900,000 ohms while the other bar types ranged between 243 and 722 ohms.
Figure 4. Average mat-to-mat ac resistance data of eight reinforcing bar materials for 96-week SE tests

 

Table 4.Summary of in-concrete test results per coating type[4]

Data

Slab Configuration

ECR Coating Type

Presence of Crack

Top Mat

Bottom Mat

Initial Defect Size (Percent)

A

B

C

D

E

F

Average Macrocell
Current (uA)

Uncracked

Straight ECR

Straight black

0.5

2.5

24.6

53.8

4.8

92.5

190.7

0.004

0.3

0.2

4.3

1.2

12.5

54.3

Straight ECR

0.5

0.3

0.4

1.2

1.4

1.4

2.3

0.004

0.2

0.3

0.3

1.3

0.4

5.1

Bent ECR

Straight black

0.5

38.8

30.8

80.3

30.2

0.8

171.6

0.004

0.5

0.4

7.9

1.9

0.4

122.0

Precracked

Straight ECR

Straight black

0.5

59.6

65.4

103.7

11.3

151.0

191.8

0.004

7.8

60.0

24.8

1.4

45.9

55.4

Average Mat-to-Mat
Resistance (ohm)

Uncracked

Straight ECR

Straight black

0.5

3,239

3,359

1,671

3,514

1,783

787

0.004

361,707

543,182

511,331

659,069

73,779

90,437

Straight ECR

0.5

5,941

9,255

7,147

6,914

4,431

3,682

0.004

488,452

561,286

528,333

941,250

259,250

479,375

Bent ECR

Straight black

0.5

1,349

1,943

1,393

2,738

3,805

705

0.004

13,561

97,752

171,951

68,950

167,100

57,768

Precracked

Straight ECR

Straight black

0.5

1,281

2,918

831

1,715

822

591

0.004

14,653

4,005

21,406

103,722

63,212

12,592

 

Previous | Table of Contents | Next

Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000
Turner-Fairbank Highway Research Center | 6300 Georgetown Pike | McLean, VA | 22101