U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000


Skip to content
Facebook iconYouTube iconTwitter iconFlickr iconLinkedInInstagram

Federal Highway Administration Research and Technology
Coordinating, Developing, and Delivering Highway Transportation Innovations

Report
This report is an archived publication and may contain dated technical, contact, and link information
Publication Number: FHWA-HRT-04-094
Date: November 2004

Evaluation of LS-DYNA Soil Material Model 147

PDF Version (2.87 MB)

PDF files can be viewed with the Acrobat® Reader®

CHAPTER 5. DEVELOPER'S RECOMMENDED PARAMETERS

The developer modeled direct shear test 4 (DS-4) using LS-DYNA and prepared a graph of the physical test data compared to the shear stress-deflection curve from LS‑DYNA. This figure and the corresponding input parameters from the developer are shown in figure 15 and table 11, respectively. The LS-DYNA format for these parameters is shown in table 12.

View Alternative Text

Figure 15. DS-4 simulation results from the developer.

Note: Figure 15 is labeled "shear force"; however, it is really shear stress. It is assumed that the shear stress was made by dividing the shear force (the x-direction cross section force defined in the model) by the original cross-sectional area of the sample (0.2 square meters (m2)).

Table 11. Revised developer's and baseline material parameters.

Material Parameter

Input Deck

RO

Nplot

Spgrav

Rhowat

Vn

Gammar

Baseline

2.350E-6

3

2.79

1.0E-6

1.1

0.0

Developer's e-mail

2.350E-6

3

2.79

1.0E-6

1.1

0.0

Input Deck

Itermax

K

G

Phimax

Ahyp

Coh

Baseline

10

0.465

0.186

1.1

1.0E-7

6.2e-6

Developer's e-mail

10

0.00325

0.0013

1.1

1.0E-7

6.2e-6

Input Deck

Eccen

An

Et

Mcont

Pwd1

PwKsk

Baseline

0.7

0.0

0

0.034

0.0

0.0

Developer's e-mail

0.7

0.0

0

0.034

0.0

0.0

Input Deck

Pwd2

Phires

Dint

Vdfm

Damlev

Epsmax

Baseline

0.0

0.0E-0

2.5E-3

5.0E-0

1.00

1.00

Developer's e-mail

0.0

1.0E-3

1.0E-5

6.0E-8

0.99

0.80

Table 12. Input deck as per developer's e-mail
$                
*MAT_FHWA_SOIL
$
mid
ro
NPLOT
SPGRAV
RHOWAT
VN
GAMMAR
ITERMAX
 
1
2.350E-6
3
2.79
1.0e-6
1.1
0.0
10
$
K
G
PHIMAX
AHYP
COH
ECCEN
AN
ET
 
  0.00325
0.00130
1.1
1.0E-7
6.2E-6
0.7
0.0
0.0
$
MCONT
PWD1
PWKSK
PWD2
PHIRES
DINT
VDFM
DAMLEV
 
0.034
0.00
0.0
0.0
0.001
0.00001
6.0E-08
0.99
$
EPSMAX
 
0.80
$

These parameters were put into the direct shear model at the user's facility and were simulated. The model became unstable at 38 ms and terminated, as shown in figure 16. The shear stress versus displacement for this run is shown in figure 17. The shear stress calculated on the user's SGI computer was significantly lower than the shear stress calculated by the developer's PC computer.

It was then noted that the developer's graph, as shown in figure 15, terminated at approximately 46 mm. Because the loading was at 1 mm/ms and the specified termination time was 50 ms, the direct shear model should have displaced 50 mm. This suggests that the developer's graph is representative of instability occurring in the soil material model as well.

View Alternative Text

Figure 16. Instability of developer's soil model.

View Alternative Text

Figure 17. Direct shear results with the developer's soil parameters.

CAUSE OF INSTABILITY

As is shown in figure 16, shooting nodes can be seen in the model. It was desired to see which material parameters induced this failure mode. The parameters used are shown in tables 13 and 14. Additionally, the four parameters that were believed to be the source of the instability were altered individually to determine the source of the instability. These parameters and their corresponding LS-DYNA runs are listed in table 15.

It appears that the damage routines caused the instability. When Damlev was changed from 1.00 to 0.99, the model became unstable. Since both Damlev and Epsmax must be exceeded in order to delete elements, the instability lies somewhere in the damage algorithms and probably not in the variable input routines. Therefore, it must be the instability with other material parameters, the damage algorithms, and/or the element formulation.

Subuently, the developer proposed a probable cause for the instability as follows. In LS-DYNA, an element fails when one of the gauss points reaches the failure criteria. For fully integrated elements (8 gauss points), this causes an early failure. This early failure does not let the internal forces go to zero before the failed elements are eliminated from the calculation. In turn, this leads to very large unbalanced forces at the nodes, causing unstable behavior (shooting nodes). In addition, this analysis is difficult for LS-DYNA to complete with fully integrated elements because of the well-known problems with shear locking of fully integrated elements.

Unfortunately, under-integrated elements are not an option because of excessive hourglassingas discussed in chapter 6.

Table 13. Material parameters used to determine instability.
$ - K = 2.162E-6 kg/mm3 Field experience
$ - SPGRAV = 2.65  Prior studies
$ - RHOWAT = 1.0E-6 kg/mm3 Theoretical
$ - VN = 1.1 Developer's original value
$ - GAMMAR = 0.0 Developer's original value
$ - ITERMAX = 10 Developer's original value
$ - K        = 0.00325 GPa Developer's e-mail value
$ - G = = 0.00130 GPa Developer's e-mail value
$ - PHIMAX =   = 1.1                Direct shear physical testing
$ - AHYP = 1.6E-7 GPa Calculated from COH and PHIMAX
$ - COH = 6.2E-6 GPa Parameter study
$ - ECCEN = = 0.7 Theoretical/reasonability
$ - AN = 0.0 Developer's original value
$ - ET = 0.0 Developer's original value
$ - MCONT = 0.034 Irrelevant with PWD = 0
$ - PWD1 = 0.0 No pore-water effects
$ - PWKSK = 0.0   No pore-water effects


Table 14. Parameters varied to identify instability source.

Input Deck

Material Parameter

Baseline Value

New Recommendations From Developer

Phires

0.0

0.001

Dint

0.0025

0.00001

Vdfm

5.0

6.0E-8

Damlev

1.0

0.99

Epsmax

0.80

0.80

Table 15. LS-DYNA models for instability determination.

Input Deck

Material Parameter

Phires

Dint

Vdfm

Damlev

Epsmax

Complete Run?

T35

New

Baseline

Baseline

Baseline

Baseline

Yes

T36

New

New

Baseline

Baseline

Baseline

Yes

T37

New

New

New

Baseline

Baseline

Yes

T38

New

New

New

New

Baseline

No

T34

New

New

New

New

New

No

Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000
Turner-Fairbank Highway Research Center | 6300 Georgetown Pike | McLean, VA | 22101