U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000
Virginia Division
The FHWA Risk Management Plan identifies the major risk areas in implementing the American Recovery and Reinvestment Act of 2009 (Recovery Act). For the consideration of the Division Offices, example checklists have been developed for use in “visible monitoring” efforts. The Quality Assurance Checklist provides inspection guidelines in regard to materials testing/acceptance and project inspection.
Date | |
Federal Project Number: | |
State Project Number: | |
Project Name/Route Number, Section and Mileposts |
|
County | |
Project Description | |
Percent Work Complete | |
Percent Time Elapsed | |
Original Contract Completion Date | |
Current Contract Completion Date | |
Award Amount | |
Current Contract Estimate |
Regulations and Guidance
23
CFR 630 Subpart J - Work Zone Safety and Mobility
23
CFR 635.105 – Supervising Agency
23
CFR 637 - Construction Inspection and Approval
29
CFR 1926 – Safety and Health Regulations for Construction
Construction Program Management and Inspection Guide
https://www.fhwa.dot.gov/construction/cpmi04tc.cfm
Questions and Answers on 23 CFR 637
https://www.fhwa.dot.gov/pavement/materials/qanda637.cfm
Federal-Aid Policy Guide, NS 23 CFR 637B, transmittal #36, published July 19,
2006.
https://www.fhwa.dot.gov/legsregs/directives/fapg/0637bsup.htm
Technical Advisory T 6120.3 Use of Contractor Test Results in the Acceptance
Decision, Recommended Quality Measures, and the Identification of Contractor/Department
Risks, published on August 9, 2004.
https://www.fhwa.dot.gov/legsregs/directives/techadvs/t61203.htm
Quality Assurance Stewardship Review - Summary Report for Fiscal Years 2003 through
2006
https://www.fhwa.dot.gov/pavement/materials/stewardreview2007.cfm
Reference | Item | Yes | No | N/A |
---|---|---|---|---|
635.105 | Full time State Engineer in responsible charge of the construction work | |||
635.105 | Staffing is adequate | |||
Field staff has all equipment required to perform necessary inspections and materials tests | ||||
637.209 | Material testers are certified | |||
Comments: |
Reference | Item | Yes | No | N/A |
---|---|---|---|---|
General | ||||
637.207 | Quality control plan has been prepared for the project | |||
637.207 | Contractor is undertaking processes included in approved QC plan | |||
637.209 | Personnel performing inspection work are qualified per the approved qualification program, or otherwise suitably experienced to perform successfully | |||
637.207 | State is conducting sampling and testing to verify contractor data as defined in the state quality assurance program. | |||
637.209 | Testing to accept materials are conducted in a certified laboratory as required in the state's quality assurance program. | |||
Environmental | ||||
Erosion and sediment control devices are installed properly and are well maintained | ||||
Contract specific environmental requirements are in compliance | ||||
Inspections are conducted in accordance with contract requirements | ||||
Environmental permits are available onsite | ||||
Earthwork | ||||
Fill placement complies with contract requirements | ||||
Compaction test results are satisfactory | ||||
Sampling and testing (frequency/location) are conducted in accordance with contract requirements | ||||
Structures | ||||
Pile Driving records are on file (including welder certifications and procedures) | ||||
Placement, tying, and cover of reinforcing steel comply with contract requirements | ||||
Bolt certifications are on file along with test results | ||||
Curing process complies with specifications | ||||
Sampling and testing (frequency/location) are conducted in accordance with contract requirements | ||||
Asphalt | ||||
Base is in good condition | ||||
Mix is delivered at proper temperature | ||||
Tacking complies with specifications | ||||
Mix is spread properly (thickness, crown, joints, uniform texture, continuous operation of paver) | ||||
Proper density is being obtained | ||||
Ride quality is in conformance with specifications | ||||
Sampling and testing (frequency/location) are conducted in accordance with contract requirements | ||||
PCC | ||||
Mix spread to correct thickness | ||||
Curing and tining applied in timely manner | ||||
Dowel baskets properly installed | ||||
Ride quality is in conformance with specifications | ||||
Sampling and testing (frequency/location) are conducted in accordance with contract requirements | ||||
Work Zone | ||||
Traffic control devices installed in accordance with Traffic Control Plan | ||||
Traffic control devices are clean and well maintained | ||||
Travel way is well delineated | ||||
Work zone inspections are completed in accordance with contract requirements | ||||
Comments: |
Reference | Item | Yes | No | N/A |
---|---|---|---|---|
635.123 | Project field records adequately maintained to quantities submitted for payment | |||
Inspector Daily Reports and Project Diary adequately support work progress, time charges etc. | ||||
Contract change documentation is adequately maintained | ||||
Acceptance sampling and testing reports are on file | ||||
Materials sampling and testing conducted as required | ||||
Failed tests are documented with cross-references to re-tests | ||||
Materials Certifications are on file | ||||
Buy America requirements included on invoices and certifications for all iron and steel products | ||||
Approved mix designs are on file | ||||
Trial batch results are properly identified and acceptable | ||||
Comments: |
Table of Contents | (continued) |