U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000


Skip to content
Facebook iconYouTube iconTwitter iconFlickr iconLinkedInInstagram

Washington Division

Home / About / Field Offices / Washington Division

Semi-Annual Reports to WSDOT

Semi-Annual Project Delivery Report
With data from Federal Fiscal Year 2008 Quarters 3 & 4 (April 2008-Sept 2008)
Issue IV, February 5, 2009

Introduction

The Federal Highway Administration (FHWA) Washington Division has developed the following Project Delivery Report which highlights some of the broad array of activities / initiatives / approvals we perform to assist the Washington State Department of Transportation (WSDOT) and local agencies in delivering projects.

Presented below and herein are charts / graphs of project delivery measures. Additional charts / graphs will be added in future reports as new data is gathered for supplemental measures. On the last page we highlight other project delivery challenges.

We will continue to add to / revise the performance measures for future reporting and welcome any suggestions. Our goal is to continue to set the standard for excellence in FHWA in project delivery.

Approal of ER Damage Inspection Reports by Quarter

This chart shows the timeliness of approval for emergency relief (ER) damage inspection reports. Our goal is to ap-prove 90% of these reports within 10 days of receipt. We did not meet our goal in the 3rd/4th quarters of FY 2008. This is attributed to the Washington Division revising its long-standing policy to not pay for "debris removal." After evaluating the Division's policy against new ER guidance from HQ we modified our policy to cover costs associated with debris removal within the roadway prism. Many debris removal ER damage inspection reports were held for several weeks while the Division's policy was being reevaluated resulting in the longer than usual time for approval.

Approval of Documented Categorical Exclusions by Quarter

This chart shows the timeliness of approval of documented categorical exclusions (DCEs) by quarters for FYs 2007 and 2008 (FY 2009 will be reported in the next issue). As the chart depicts, we are approving the majority of DCEs within the first 10 days of receipt.

Other Approvals/Actions

Environmental Document Approvals

Design Approvals

Design Deviations

Access Actions

Approval of R/W Cert 2s & 3s by quarters

This chart shows the timeliness of approval for right-of-way (R/W) certifications 3 (approval of certifications 1 and 2 have been delegated to WSDOT). In order to authorize the advertisement of a project for construction, the State must certify the R/W has been cleared, per 23 CFR 635.309. A certification 3 means there are some parcels where rights have not been obtained and there may be some displacees remaining. Certification 3s are to be used infrequently. Our goal is to take action on / approve 90% of certification 3s within 10 days of receipt.

Timeliness of Authorizations / Modifications

With-in 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
0 to 5 Days 208 780 858 724 1327 1463 1456 943 1451 1645
6 to 10 Days 24 241 307 121 90 101 103 68 175 128
11 to 15 Days 12 77 109 39 10 22 24 13 37 12
16 to 20 Days 9 29 34 21 5 3 8 1 18 5
20 + Days 31 152 68 98 52 15 17 8 16 13
Totals 284 1279 1376 1003 1484 1604 1608 1033 1697 1803

This table reflects the number of authorizations / modifications approved within certain timeframes since 1999. For federal fiscal year (FY) 2008 our approval has increased to 91% (1645/1803) up from FY 2007's 86% (1451/1697) within the first five (5) days. The 91% exceeded our goal of 90%! This is attributed to being fully staffed, as well as the emphasis placed on timely approvals. (Note: the FY begins on October 1 and ends on September 30 of the following year. )

 

Endangered Species Act (ESA) Formal Consultation Data

These charts show the formal timeframes from 2001 to present for endangered species act (ESA) consultations for the US Fish & Wildlife Service ((USF&WS)) and the National Oceanic & Atmospheric Administration–Fisheries Service (NMFS) beginning with consultations in April 2001.

These charts show the formal timeframes from 2001 to present for endangered species act (ESA) consultations for the US Fish & Wildlife Service (USF&WS) and the National Oceanic & Atmospheric Administration–Fisheries Service (NMFS) beginning with consultations in April 2001. Each diamond point represents the number of days needed for completion of a formal consultation for a specific project. Formal consultation is entered into when a project is determined "likely to adversely affect" a listed endangered species (some of the most encountered on projects are chinook, coho, sockeye, and chum salmon; bull trout; bald eagles, and marbled murrelets). Formal consultations are required to be completed with 135 days (90 days for consultation and 45 days to prepare a biological opinion (BO)).

For more information contact:

Dan Mathis
Division Administrator
FHWA Washington Division
360-753-9480
Daniel.Mathis@dot.gov
Kevin Ward
Assistant Division Administrator
FHWA Washington Division
360-753-9480
Kevin.Ward@dot.gov
Page last modified on April 1, 2013
Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000