<< Previous | Contents | Next >> |
Accelerated Construction Technology Transfer Toolkit
Archived: Sample Materials and Forms
Utilities final presentation
MDOT ACTT Workshop
I-94 Accelerated Construction Technology
Detroit, Michigan
April 17-19, 2007
MDOT ACTT Workshop
Utilities/Railroad Coordination
Final Presentation
Utilities/Railroad Coordination
Team Members
- Marion Leaphart, Utilities Manager, SC DOT
- Veena Jasuja, MDOT, Detroit TSC
- Nick Lefke, MDOT, Lansing, Design
- Bill Stonebrook, MDOT, Lansing, Design
- Steve Rapp, MDOT, Lansing, Design
Facilitator:
- Anu Taneja, MDOT, Lansing, Contract Services
Notes:
- Lynn Venturino, MDOT, Lansing, Design Support
Utilities
Designate a full time MDOT utilities coordinator
- Oversee all aspects of utility coordination, communication, and cooperation during design and construction
- Act as "go to" person for MDOT, utilities, and vendors
Utilize Subsurface Utility Engineering (SUE)
- Have SUE provider available during design and construction
- Update current SUE data
- Utilize SUE deliverables effectively with stakeholders
- Expedites conflict resolution
Identify and resolve municipal utility issues
- Early and often involvement of municipal utilities
- Early identification of potential "show stoppers"
- Identify all relocation and proposed new work
- Coordination with stakeholders
Identify and resolve private/public utility issues
- Early and often involvement of private/public utilities
- Early identification of potential "show stoppers"
- Identify all relocation and proposed new work
- Identify reimbursable relocations
- Advanced utility relocations
- Coordination with stakeholders
Participate in preliminary engineering costs for private/public utilities
- Provides incentive to private/public utilities to cooperate in a timely manner
- Increases cooperation during design phase
Railroads
Form Steering Committee of officials from MDOT and Railroads (RR)
- Authority to make high level decisions
- Expedite RR decision making (i.e. trackage rights, union work rules, etc.)
Form a Design Engineering Committee
- Early and often involvement of railroads
- Early identification of design constraints
- Early identification of potential "show stoppers"
Provide adequate time for RR coordination in the MDOT process
- Two year minimum coordination time
- Coordination time begins from submittal of preliminary plans from MDOT to RR
Contract with qualified vendor to perform RR coordination
- Vendor must be knowledgeable in RR operations
- Effective in obtaining RR approvals
- Involve MDOT RR experts in vendor selection process
Coordinate at-grade crossings with service roads
Diagnostic Team Review (DTR) meeting should take place well in advance of construction, if required.
Maintenance of RR traffic
- Early and often involvement of RR
- Construct temporary runaround "shoo-fly" tracks
- Part width bridge construction
- Roll-in/lift-in superstructure
- Build new permanent bridges parallel to existing RR
- Trackage rights agreements between RR during construction
Possible elimination of two RR structures over I-75
- RR approval required
<< Previous | Contents | Next >> |