Location | Oatman Highway (Historic Route 66) Crossing at Sacramento Wash in Topock, AZ |
|
---|---|---|
Award Sub-Recipient | Mohave County | |
Innovation | Prefabricated Bridge Elements and Systems (PBES) | |
Award Fiscal Year | 2015 | |
Project Aspect | Design and Construction | |
Description | The Arizona Department of Transportation (ADOT) and Mohave County will construct a bridge over the Sacramento Wash in Topock, Arizona providing a 110-ft clear span that will pass the 2-year, 30-minute storm event using Prefabricated Bridge Elements and Systems (PBES) for the abutments and superstructure. The proposed bridge and roadway improvements will be constructed on the existing alignment and therefore a temporary roadway closure will be required to complete the work. Given the length of detour required during a road closure, accelerated construction alternatives will be implemented resulting in a full roadway closure timeframe estimated at four days. Fabrication of the PBE will be completed such that they are ready prior to the roadway closure. |
|
Grant Award | $1,000,000 | |
Partner | Arizona Department of Transportation | |
Project Web Page | http://www.azdot.gov/projects/northwest-district-projects/mohave-county-sacramento-wash-bridge-in-topock/overview | |
Project Contact | Rashidul Haque, PE Project Manager Project Management Group Arizona Department of Transportation 206 S. 17th Avenue Phoenix, Arizona 85007 (602) 712-7352 RHaque@azdot.gov Tim Walsh, PE Engineering Manager Mohave County Public Works 3715 Sunshine Drive, P.O. Box 7000 Kingman, Arizona 86402-7000 (928) 757-0910 Tim.Walsh@mohavecounty.us |