Based on the research and interviews conducted for this study, public agencies are incorporating a variety of mechanisms to enhance opportunities for early involvement of the private sector in the project development process. While these mechanisms are fostering development of better projects through increased information sharing, greater technical and financial innovation, and improved risk management, it is unclear if these mechanisms have expanded private investment in P3s. The lack of clarity may be partly due to the extent to which different mechanisms have been tested. The frequency with which these mechanisms have been used varies widely, with some practices - such as industry forums - being employed almost universally, while other practices, such as use of Pre-Development Agreements (PDAs), having only a limited track record in the United States.
Table 6-1 summarizes the potential effects of the different mechanisms examined in this study. Broader knowledge and adoption of some of these mechanisms would provide potential benefits. The majority of the mechanisms have the potential to foster positive effects by adding value, reducing schedule and cost, and managing risk. Such effects are denoted in the table in blue and through the use of plus (+) signs. With some mechanisms, there is potential that the benefits of early private sector involvement could be countered by reduced competition or other negative effects. Such effects are donated in the table in red and through the use of minus (-) signs. The magnitude of these potential effects is indicated by the intensity of the blue and red shading in individual cells.
As indicated in Table 6-1, one of the key tradeoffs that public agencies may encounter in employing some early involvement mechanisms with P3 projects is the potential for reduced competition. The increased information sharing between private and public sectors associated with early involvement mechanisms may reduce competition, particularly when the procurement process "locks in" a private entity at an early stage. This may diminish the creative tension that results from competition. Conversely, early "lock-in" may result in positive synergies by reducing the private sector's perception of risk, which could increase its willingness to invest.
Early involvement requires an additional investment of time and resources early in the project development process, but it has the potential to produce a better defined and more financially feasible project. This dynamic may also produce efficiencies later in the process, expediting project implementation.
Involvement Mechanisms | Add Value & Foster Innovation | Maintain or Reduce Cost & Schedule | Maintain or Increase Competition | Reduce Public Sector Risk | Reduce Priate Sector Risk |
---|---|---|---|---|---|
Planning to Procurement | |||||
Program Development and Project Screening | High (+) | Medium (+) | Low/No | Low/No | Low/No |
Industry Forums | Medium (+) | Low/No | Low/No | Low/No | Low/No |
Market Sounding | High (+) | Low (+) | Low/No | Low/No | Low/No |
RFIs | High (+) | Medium (+) | Low/No | Low/No | Medium (+) |
Unsolicited Proposals | Medium (+) | Medium (+) | High (-) | Low (-) | Low (+) |
PDAs/MDAs | Medium (+) | Medium (+) | High (-) | Medium (-) | Medium (+) |
Risk Workshops | Medium (+) | Low (+) | Medium (+) | Medium (+) | Medium (+) |
Collaborative Evaluation of Alternatives | Medium (+) | Low (+) | Low (-) | Medium (+) | Medium (+) |
Progressive Design-Build | Medium (+) | Medium (+) | Medium (-) | Medium (+) | Low (-) |
Procurement | |||||
Industry Meetings | Medium (+) | Low/No | Low/No | Low/No | Low/No |
Multi-Stage Procurement | High (+) | High (-) | Medium (+) | Medium (-) | High (-) |
Multiple P3 Delivery Procurements | Medium (+) | High (-) | Medium (+) | High (-) | High (-) |
ATCs | High (+) | High (+) | Medium (+) | Medium (+) | Medium (+) |
Interweaving | Medium (+) | Medium (+) | Medium (-) | Medium (+) | Medium (+) |
Sole Source Procurements | Low/No | High (+) | High (-) | High (-) | Medium (+) |
Post-Procurement | |||||
Lender Engagement | Medium (+) | Low/No | Low/No | Low/No | Low/No |
Competitive Stipends | Medium (+) | Low/No | Medium (+) | Medium (+) | Medium (+) |
Legend | Positive | Negative |
---|---|---|
High | High (+) | High (-) |
Medium | Medium (+) | Medium (-) |
Low | Low/No | Low (-) |
Based on the findings reported in this Discussion Paper, public project sponsors considering early involvement of the private sector in the development of P3 projects may consider the following successful practices: