U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000


Skip to content U.S. Department of Transportation/Federal Highway AdministrationU.S. Department of Transportation/Federal Highway Administration

Construction

 

Indiana Department of Transportation SEP 14 Report Alternate Pavement Type

Appendix C SR 25 (IR-30840)

Seven (7) Contractors participated in the bidding (7 PCCP options and 5 HMA options were bid) and all bids were below the engineer's estimate. Five (5) Contractors participated in both pavement type pay options.

INDOT provided the following pavement design thickness for mainline of this project:

  1. 10 inches of PCCP or
  2. 13.5 inches of HMA

Bid Analysis Summary

PCCP Pay item Options
Bidders Initial Bid PW Cost for PCCP Bid Analysis
A $26,695,938.17 + $2,108,515.00 = $28,804,453.17
B $26,950,326.93 + $2,108,515.00 = $29,058,841.93
C $26,994,088.85 + $2,108,515.00 = $29,102,603.85
D $28,217,279.05 + $2,108,515.00 = $30,325,794.05
E $28,372,604.40 + $2,108,515.00 = $30,481,119.40
F $30,007,418.05 + $2,108,515.00 = $32,115,933.05
G $30,827,332.05 + $2,108,515.00 = $32,935,847.05
HMA Pay item Options
Bidders Initial Bid PW Cost for HMA Bid Analysis
B $27,605,987.05 + $3,449,253.00 = $31,055,240.05
A $27,671,360.16 + $3,449,253.00 = $31,120,613.16
C $27,876,127.63 + $3,449,253.00 = $31,325,380.63
F $28,191,983.79 + $3,449,253.00 = $31,641,236.79
D $29,117,275.82 + $3,449,253.00 = $32,566,528.82

The low bid amount, out of all 7 bids, was for PCCP pay items option (Bidder A) and after adding PW cost of HMA and PCCP to the respective pavement type options, PCCP option was also the low bid (Bidder A). PCCP pay items option of Bidder A was awarded for this contract.

INDOT compared the estimated cost with actual low bid costs of both pavement types. The following table shows the cost comparison with low bid of those pavement items that were relative to the mainline pavements and relative to this alternate bid for pavement type. All other items in the bids were common to both types of pavement. Shoulders and "S" Lines are to be HMA.

Cost Comparison of Unique Items
Bid Item Bid Quantities Estimated Cost of Item Per Unit Low Bid Cost of Item Per Unit Range of Bid Costs of Item Per Unit Average Bid Cost of Item Per Unit HMA or PCCP Option
QC/QA PCCP, 10 IN. 199,445 yd2 $28.58 $23.66 $22.99 - $26.00* $24.40 PCCP
Subbase for PCCP 51,490 yd3 $30.59 $26.00 $26.00 - $52.00* $34.45 PCCP
D-1 Contraction Joint 97,990 ft $8.64 $8.48 $7.64 - $15.00* $9.39 PCCP
QC/QA-HMA, 4, 70, Surface 18,179 TON $70.50 $67.97 $66.50 - $71.95 $67.88 HMA
QC/QA-HMA, 4, 70, Intermediate 30,340 TON $49.40 $52.12 $48.43 - $52.12 $50.71 HMA
QC/QA-HMA, 4, 64, Base 48,570 TON $48.10 $49.57 $48.39 - $49.57 $48.69 HMA
QC/QA-HMA, 5, 76, Intermediate, OG 31,370 TON $54.20 $45.99 $45.00 - $47.44 $45.68 HMA

* Bidder F was significantly and consistently higher on all the PCCP option items.

The above table shows that pavement item bids on PCCP are consistently lower than the estimates used in evaluation, overall the HMA items were lower than the estimates with only a few HMA items higher. This indicates that a true cost savings was realized by INDOT in this process.

The table below compares some common HMA items found in both PCCP and HMA options to check for unbalanced bids. These bids appear to be consistent and no anomalies were found.

Cost Comparison of Some Common Items Used in Both PCCP and HMA
Bid Item Bid Quantities Low Bid Cost of Item Per Unit Range of Bid Costs of Item Per Unit Average Bid Cost of Item Per Unit HMA or PCCP Bid
QC/QA-HMA, 2, 64, Surface 2,119 TON $64.00 $64.00 - $67.20 $65.37 PCCP
QC/QA-HMA, 2, 64, Surface 1,855 TON $65.92 $64.50 - $65.92 $65.00 HMA
QC/QA-HMA, 2, 64, Intermediate 3,375 TON $52.00 $52.00 - $56.21 $54.46 PCCP
QC/QA-HMA, 2, 64, Intermediate 12,410 TON $55.19 $52.39 - $55.19 $53.92 HMA
QC/QA-HMA, 2, 64, Base 7,617 TON $52.00 $52.00 - $54.48 $52.51 PCCP
QC/QA-HMA, 2, 64, Base 7,617 TON $53.15 $52.00 - $53.16 $52.46 HMA

Conclusion

INDOT saved the tax payers approximately $866,508.88 immediately, at the bid opening, (HMA Low Bid - PCCP Low Bid). Using the Bid Analysis amounts (after PW costs applied); INDOT saved the tax payers approximately $2,207,246.88 over the 50 year service life of the pavement. These savings include the reduction of INDOT's consultant cost of $43,540.00 for producing two sets of typical plan sheets and quantities. The inhouse costs for INDOT were determined negligible.

The PW cost for future maintenance did not impact the bid and which contractor received the contract. INDOT believes using this process of alternate bids for pavement type selection on this project was very successful.

PW of Future Maintenance of the Pavement SR 25 (IR-30840)

PW of HMA Option = $3,449,253.00

PW of PCCP Option = $2,108,515.00

HMA PW for Future Rehabilitation Work
Age in Years Rehab. Cost $ Present Worth Cost $
3 Joint Seal 182,952.00 $162,643.66
6 Joint Seal 182,952.00 $144,589.62
9 Joint Seal 182,952.00 $128,539.65
12 Joint Seal 182,952.00 $114,271.28
15 Joint Seal 182,952.00 $101,586.75
18 Joint Seal 182,952.00 $90,310.25
20 Mill and Functional Overlay 3,995,007.00 $1,823,269.04
23 Joint Seal 182,952.00 $74,228.44
26 Joint Seal 182,952.00 $65,988.82
29 Joint Seal 182,952.00 $58,663.82
32 Joint Seal 182,952.00 $52,151.92
35 Mill and Resurface 1,947,871.00 $493,620.65
38 Joint Seal 182,952.00 $41,216.42
41 Joint Seal 182,952.00 $36,641.25
44 Joint Seal 182,952.00 $32,573.94
47 Joint Seal 182,952.00 $28,958.11
Total HMA PW Cost $3,449,253.62
PCCP PW for Future Rehabilitation Work
Age in Years Rehab. Cost $ Present Worth Cost $
8 Reseal the Joint 176,176.00 $128,730.08
16 Reseal the Joint 176,176.00 $94,061.81
24 Reseal the Joint 176,176.00 $68,730.04
30 Mill and Functional Overlay 4,022,890.00 $1,240,332.09
33 Joint Seal 182,952.00 $50,146.08
36 Joint Seal 182,952.00 $44,579.68
39 Joint Seal 182,952.00 $39,631.17
42 Mill and Resurface 1,989,558.00 $383,138.99
45 Joint Seal 182,952.00 $31,321.09
48 Joint Seal 182,952.00 $27,844.34
Total PCCP PW Cost $2,108,515.36

PW = F [1/(1+i)n]

Where: F = Future Construction Cost
i = Discount rate (4%)
n = Number of years from year zero

Total Cost
Total Cost Alternative 1: 10 inches PCCP Alternative 2: 13.5 inches HMA
Agency Cost ($1000) User Cost ($1000) Agency Cost ($1000) User Cost ($1000)
Undiscounted Sum $7,455.74 $0.00 $8,504.21 $0.00
Present Value $2,108.52 $0.00 $3,449.25 $0.00
EUAC $98.15 $0.00 $160.56 $0.00
Lowest Present Value Agency Cost Alternative 1: 10 inches PCCP
Lowest Present Value User Cost Alternative 1: 10 inches PCCP
Expenditure Stream
Year Alternative 1: 10 inches PCCP Alternative 2: 13.5 inches HMA
Agency Cost ($1000) User Cost ($1000) Agency Cost ($1000) User Cost ($1000)
0
1
2
3 $182.95
4
5
6 $182.95
7
8 $176.18
9 $182.95
10
11
12 $182.95
13
14
15 $182.95
16 $176.18
17
18 $182.95
19
20 $3,995.01
21
22
23 $182.95
24 $176.18
25
26 $182.95
27
28
29 $182.95
30 $4,022.89
31
32 $182.95
33 $182.95
34
35 $1,947.87
36 $182.95
37
38 $182.95
39 $182.95
40
41 $182.95
42 $1,989.56
43
44 $182.95
45 $182.95
46
47 $182.95
48 $182.95
49
50
Updated: 07/25/2017
Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000