C-53 B. Organize and Plan Project Select Consultant
- Select Project Team
- Identify Project Tasks
- Assign Tasks
- Develop Consulting Scope and Cost
- Consultant Contract Method
- Choose Consultant
- Negotiate Consultant Contract
- Develop Staffing Plan, Financial Plan, Schedule, Cost Module
- Schedule UDOT Resources
- Develop RFQ
- Advertise and Select Consultant
[Start]
1 go to 2
2 go to 3
3 go to 4
3 branches to either 4 or 9
If 3 branched to 4
4 go to 5
5 branches to 6 or 10
If 5 branched to 6
6 go to 7
7 go to 8
If 3 branched to 9
9 go to 8
If 5 branched to10
10 go to 11
11 go to 7
7 go to 8