C-54 C. Contractor Selection
- Project Development Assembles Team with Region Coordination
- Develop RFP with Selection Criteria and Weights
- Project Team Determines Bid Items and Quantities
- Advertise RFP
- Pre-Proposal Contractor Meetings
- Team Members Individually Score Proposals
- Section Meeting Ranking by Consensus
- Optional Interview
- Team Award Recommendation
- Deputy Director Approval
- Award Design Contract
- Project Development Team Reviews Weighting Criteria
- Project Development Team Reviews Status of CMGC Program
- Interview All Contractors Selection by Team Consensus
- Re-advertise RFP or Process as Design-Bid-Build
[start]
1 go to 2
2 branches to either 3, 12, or 13
If 2 branched to 3
3 go to 4
4 go to 5
5 go to 6
6 go to 7
7 go to 8
8 branches to either 9 or 14
If 2 branched to 12
12 go to 4
If 8 branched to 9
9 go to 10
If 8 branched to 14
14 go to 9
10 branches to either 11 or 15
[end]