C-56 E. Blind Bid Opening
Contractor submits bid
Consultant submits engineering estimate
Third party submits independent cost estimate
- Prepare M&P spreadsheet for blind bid opening
- a. Designer Creates Engineer Estimate
b. Contractor Creates price proposal
c. Third Party Independent Cost Estimate - Bids & Estimate Submitted to Password Protected Blind Bid Spreadsheet
- Compare EE, ICE and contractor to each other
- Discuss areas that are not within 10% of each other
- Repeast blind bid opening up to 3 times. Then submit bids to EBS for the normal bid opening process
- Have all blind bids been opened?
- Submit bids to EBS for the normal bid opening
[start]
1 go to 2a, 2b and 2c
2a, 2b, 2c go to 3
3 go to 4
4 go to 5
5 go to 6
6 go to 7
If 7 no - go to 1
If 7 yes - go to 8