![]() |
![]() ![]() |
![]() U.S. Department of Transportation
Federal Highway |
|
Refer to: HIF |
Mr. Andrew S. Natsios
Chairman
Massachusetts Turnpike Authority
185 Kneeland Street
Boston, MA 02110
Dear Mr. Natsios:
After reviewing the Central Artery/Tunnel (CA/T) Project Finance Plan Update submitted on March 15, 2000, we are unable to accept it as submitted.
The most critical issue to resolve is the identification of new funding resources. The State Legislature must act to make funding resources available to cover the cost of the CA/T Project, including the cost increase and adequate contingencies, with such actions signed into law by the Governor before a plan can be accepted. Documentation that these actions have been completed must be provided to the Federal Highway Administration (FHWA) by May 19, 2000, or we will freeze the use of obligation authority (OA) for the CA/T Project. Prior to May 19, 2000, any use of OA will be on an exception basis for work that cannot be deferred without cost increases.
The following comments are offered for your consideration and action. These items should be addressed in the form of a completely revised Finance Plan Update. Submission is required by June 16, 2000, and the transmittal letter should indicate the response or action taken regarding these comments:
Funding and Funding ResourcesWe offer the following comments on specific elements of the Finance Plan Update or Task Force Report items:The FHWA is limiting new Advance Construction (AC) authorizations on the CA/T Project to the amount specified in previous accepted Finance Plan Updates. This amount, $222 million, is defined by Exhibit 5-4 on page 32 in the March 15 Update. Advance Construction authorizations for the CA/T Project cannot exceed the existing AC balance plus $222 million.
Similarly, the FHWA will limit the use of OA on the CA/T Project to amounts indicated in the Finance Plan Update on page 30, as Federal obligations of $7.049 billion plus the Grant Anticipation Notes (GAN) of $1.5 billion. This action limits Federal funds for the CA/T Project to $8.549 billion as defined in Exhibit 5-1: Summary of $11.7 billion Obliga- tions by Funding Source. Our Massachusetts Division Office will control this limitation through the Financial Management Information System. The new Finance Plan Update must show the projected use of OA annually in the years beyond 2003, including planned conversions to repay the $1.5 billion GAN's, any other AC conversions since the AC balance at the end of 2005 is projected to be over $300 million in excess of the amount needed for the GAN's, or any other planned use of OA.
Subject to an agreement between the State and the FHWA that describes an AC conversion process, the State would be allowed to use additional OA above the $8.549 million level to convert up to the full amount of AC limit being authorized for the CA/T Project. The process for doing this would require a formal public notice process enabling the public and Regional Transportation Planning bodies to comment. In addition, the amount of increase would have to be approved by the Governor and incorporated in future statewide transportation improvement program approvals.
Balanced Statewide Program
The Finance Plan Update submitted on March 15 discussed the statewide program in very broad terms. The lack of specific actions and a time table to develop a consensus on this issue is a significant concern. On March 13, 2000, the FHWA wrote to Secretary Kevin Sullivan to request that the State take the lead with its partners and constituents to build consensus on how to define the commitment to a Statewide Road and Bridge Program. The State must consult with the planning agencies and other transportation constituents on a statewide basis to develop a statewide program funding level, a definition of how to measure attainment of the program funding level, and what activities will be included in the statewide program funding commitment (e.g., planning, design, or construction).
I want to stress that Secretary of Transportation Rodney E. Slater and Federal Highway Administrator Kenneth R. Wykle have made clear that the Finance Plan Update must account for a balanced statewide transportation program. The establishment of a statewide program funding commitment and identification of appropriate funding resources for the Statewide Road and Bridge Program must be completed before the Finance Plan Update can be accepted.
Insurance Program
The February 29 deadline for this information has passed and the information submitted is not adequate. The information presented about exposure and funding needs for the period after construction (the so-called tail period) needs to be clarified. The State must define the insurance program, how the risk/exposures are to be covered, what trust reserves are required and/or how coverages will be funded. No insurance program reserves can be included in the funding plan as credit until the State has submitted an insurance program that is acceptable to the FHWA.
The FHWA's Cost Estimate
Our Massachusetts Division Office has completed an independent assessment of the cost to complete the CA/T Project. The FHWA's estimate indicates that project costs will most likely exceed the State's announced $1.4 billion increase by $300 to $480 million. This estimate and the estimate by the State's consultant would indicate that funding resources in excess of $13.1 billion should be anticipated. The Finance Plan Update should include an estimated project cost and identify the resources that could be made available to cover any additional costs.
Agreement to Define Future Process and Information Submissions to Improve Cost and Funding Oversight
The fact that the State began a process in late 1998 to track potential exposures and elected not to present this information on the Project Monthly Management (PMM) reports or otherwise advise the FHWA is particularly disturbing. Good management at both the State and Federal levels mandates full sharing of information regarding the project. To assure clarity and understanding of roles and requirements to implement this letter and the Federal Task Force's Report, it will be necessary to execute an agreement between the FHWA, the Massachusetts Turnpike Authority (MTA), and the Massachusetts Highway Department. The FHWA will provide a draft of this agreement for review and coordination between the parties.
Sincerely yours,
|
Last updated May 8, 2000