Section 1305(b) of the Transportation Equity Act for the 21st Century
(TEA-21) modified Section 106 of Title 23 by adding subsection "(h)"
which requires a recipient of Federal-aid funds to submit to the Secretary
an annual finance plan for a project with an estimated total cost of $1
billion or more. The act requires that the plan be based on detailed
annual estimates of the cost to complete the remaining elements of the
project and on reasonable assumptions of future increases in the cost to
complete the project.
Mega projects costing over $1 billion are often implemented over a
number of years and may involve numerous individual elements. These
elements may or may not have independent utility. Thus a decision to start
implementing a mega project may require significant future financial
resources in order to achieve the transportation benefits of the initial
investment.
The initial finance plan will provide the decision maker with
information on the immediate and longer term financial implications
resulting from project initiation. The subsequent annual updates of the
finance plan provide information on actual cost and funds available in
comparison to initial estimates. The annual updates will provide the
decision maker with information on the financial implications of
completing the project.
A finance plan is a document that provides a reasonable assurance that
there will be sufficient financial resources available to implement and/or
complete the mega project as planned.
In essence, a finance plan provides a description of how a mega project
will be implemented over time by identifying project cost elements,
financial resources to be utilized, and assumptions about both cost and
revenue.
Finance plans are to be prepared for all Federal-aid (Title 23) projects
with an estimated total cost of $1 billion or more. This threshold should
be measured in year-of-expenditure dollars and be applied to projects
reasonably expected to cost at least $1 billion. A "project"
would generally be defined as that work described in the environmental
document and with independent utility between logical termini, and could
comprise several segments.
The plan should consist of at least five main sections: (1) the Cost
Estimate - in which the total cost and cost-to-complete are presented in
current dollars, (2) the Implementation Plan - in which the project
schedule is presented and the cost-to-complete is presented in annual
increments in inflated dollars, (3) Funding Sources - presented as annual
amounts available for project obligations and compared to annual
obligation needs, (4) Cash Flow - annualized presentation of cash income
and outgo to illustrate how periodic bills will be paid, and (5) Other
Factors.
(1) Cost Estimate
The Initial Cost Estimate
The initial finance plan should reflect the total project cost.
Project costs can be considered the equivalent of the project purchase
price. They should include all costs to obtain the design, right-of-way,
construction, project management, etc. Project costs do not include the
costs of acquiring revenue (taxation, interest payments, etc.).
All costs must be presented for a single base year so that all costs
are reported in comparable dollars. If significant portions of the
project are not to be funded with Federal-aid funding, they should be
separately identified.
Annual Cost Estimate Updates
Each annual update of the cost estimate should be prepared for a new
updated base year and be presented in total cost and cost-to-complete
estimates. These estimates should use the same project elements or
breakpoints to present the cost as used in the initial estimate.
Any significant change in the total project cost since the last
estimate should be clearly presented and major reasons for any
significant cost changes should be provided.
(2) Implementation Plan
The implementation plan should reflect the schedule for completing the
project and is to be based on the initial (or latest annual updated)
base year cost, adjusted to include inflation and costescalation
resulting from the latest design or plans.
The methodology (including assumptions for future inflation, cost
escalation, etc.) and reasonableness of the cost estimate should be
described.
In developing the implementation plan, the sponsor should consider a
wide array of sources of potential future cost changes. Cost changes
might result from unforeseen environmental and subsurface conditions,
inflation, litigation, technology or contractor problems/innovations,
overtime costs to adhere to a schedule, changes in governmental rules
impacting the project, value engineering savings, etc.
(3) Funding Sources
The plan should describe all funding sources for the project and
should clearly describe these funds as committed, or anticipated
amounts, with an evaluation of the likelihood of anticipated amounts
being realized. The key feature of this section would demonstrate that
funds will be available to permit annual project fund obligations as
presented in the Implementation Plan.
Federal funds should be described by funding category under existing
legislation and as potential amounts under future legislation.
Obligations of Federal-aid funds should be constrained by anticipated
annual limitations on Federal-aid fund obligations.
If special funding techniques such as advance construction are to be
utilized, the plan should include estimated annual conversion amounts.
Any costs which are likely to be funded from sources other than
Federal-aid should be presented. The amount and sources of funds for the
non-Federal share should be clearly discussed.
The plan should address the potential for unanticipated changes in
expected funds and the impact on the project. Such changes might include
delays or decreases in receipt of project funding, reductions in user
fees earmarked for the project, changes in governmental rules impacting
the project, etc.
(4) Cash Flow
The plan must include an annual schedule of cash needs versus
available cash to meet those needs. It must demonstrate that the project
payout schedule for payments to construction contractors and others can
be met.
In addition to addressing sources and uses of funds during the
construction period, the finance plan should include a long-term
pro-forma cash flow projection showing project operating, maintenance
and (if applicable) debt service costs and identify the related funding
sources to pay them.
(5) Other Factors
The State's needs for other projects in the rest of the State during
the period of analysis covered by the finance plan and the impact of the
subject project on the remainder of the State's program, should be
evaluated and presented.
All special project cost containment strategies being used or planned
for later use should be described. These might include
design-to-estimated cost for individual project elements (i.e. limit
design so as not to exceed a target construction cost), design build,
use of cost control teams, management cost control strategies, vendor
participation via warranties or guarantees, value engineering, incentive
and disincentive clauses, etc.
The plan should describe the major responsibilities, financial and
otherwise, of the various parties involved in the project and contain
evidence of agreements or commitments.
The plan should describe any special or unique agreements, laws,
rules, or regulations in addition to NEPA and Title 23, to which the
project is subject. These could include compliance with Federal or State
project-enabling legislation, financial agreements and covenants,
accounting system reports and audits, etc.
If pertinent, the plan should discuss the liability for subsequent
operation and maintenance costs as segments of the project come on line.
On some major projects the opening to traffic of a segment of the
project (for example, a tunnel or complex traffic management system)
could require significant operational resources while other elements of
the project are not complete and still require significant construction
expenditures.
Should the plan call for mechanisms other than existing funding
sources to meet the non-Federal revenue needs or to meet cash flow
demands, the likelihood of implementing the mechanisms must be
thoroughly analyzed. This would apply to mechanisms such as new taxes,
contributions from third parties, and short or long term borrowing. The
analysis must address whether authority exists or must be granted
through legislation or other means to pursue the mechanisms. In
evaluating finance plans the Federal interest will be in the likelihood
of realizing the non-Federal revenues and cash flow as opposed to the
choice of mechanism.