RECIPIENT PROJECT
NUMBER
PROJECT TITLE TOTAL
OBLIGATIONS
ESTIMATED
TOTAL
COST
Montana 0017056 E OF ZURICH - HARLEM (CN & CE) National Highway 1, Blaine County, Reconstruction of the roadway from reference point 416.7 to 423.9 $24,897,606.53 $28,756,764.32
Montana 0110078 US 2 - CULBERTSON (CN & CE) National Highway 1, Roosevelt County, Reconstruction of the roadway from reference point 644.2 to 645.5 $22,249,184.86 $26,873,996.00
Montana 0143020 WHEATLAND COUNTY LINE-EAST (CN & CE) Primary Route 14, Multiple counties, Reconstruct the roadway and structure from reference point 77.0  to 88.1 $25,672,057.43 $29,651,256.00
Montana 0146023 TIMBER BRIDGES-FORSYTH AREA (IC, CN & CE) Primary Route 14, Rosebud County, Replace structures from reference point 227.2 to 258.6 $14,322,041.73 $28,925,185.95
Montana 0154138 WOLF CREEK-N & S (CN & CE) Multiple routes, Lewis & Clark County, Rehabilitate the existing roadway at various locations $43,451,994.32 $47,486,770.21
Montana 0513014 LAMBERT-WEST (CN & CE) State Primary 51, Richland County, Rehabilitation of the existing roadway from reference point 38.4 to 49.3 $21,644,986.55 $29,504,489.00
Montana 0575047 JCT SEC 462-EAST & WEST (CN & CE) National Highway 57, Garfield County, Reconstruct the roadway from reference point 230.1 to 239.7 $29,017,141.52 $33,524,832.00
Montana 0602101 BELT-N & S-PHASE 3 (CN & CE) Multiple routes, Cascade County, Reconstruct the roadway at various locations $23,455,814.61 $27,107,923.39
Montana 0614026 MALTA-SOUTH (CN & CE) National Highway 61, Phillips County, Rehabilitate/reconstruct the roadway from reference point 147.3 to 157.0 $26,541,980.40 $30,672,542.00
Montana 0831046 SALMON LAKE (CN & CE) State Primary 83, Missoula County, Reconstruction of the roadway from reference point 4.8 to 9.0 $48,839,608.40 $52,488,754.39
Montana 0901228 TAFT-WEST (CN & CE) Multiple routes, Mineral County, Reconstruction of the roadway at various locations $32,035,843.45 $49,632,252.00
Montana 0908177 I-90 YELLOWSTONE R-BILLINGS (CN & CE) Multiple routes, Yellowstone County, Reconstruct the roadway and replace structures at various locations $75,616,587.59 $87,160,308.56
Montana 0908188 MOSSMAIN INTCH-WEST BLGS INTCH (CN & CE) Multiple routes, Yellowstone County, Rehabilitate the roadway at various locations $23,272,387.13 $25,910,886.02
Montana 0945042 BAD ROUTE INTERCHANGE - SW (CN & CE) Multiple routes/counties, Reconstruction of the existing roadway at various reference points $5,000,000.00 $31,950,629.00
Montana 2012015 FAIRVIEW - WEST (CN & CE) Multiple routes, Richland County, Reconstruct the roadway on various routes $37,084,206.81 $42,832,301.76
Montana 2671007 RESERVE DR-W OF WHITEFISH STG (PE, RW, IC, CN & CE) Primary Route 267, Flathead County, Reconstruction of roadway from reference point 0.2 to 0.9 $34,556,384.54 $36,037,635.24
Montana STWD788 MT-200 BRIDGES LEWISTOWN AREA (CN & CE) Multiple routes, Fergus County, replace structures and associated roadwork at various locations $29,887,730.71 $45,609,754.00
Montana STWD790 TIMBER BRIDGES-GLASGOW AREA (IC, CN & CE) Multiple routes/counties, Replace structures at various locations $61,553,713.00 $70,981,296.50
Montana STWD899 RED LODGE AREA FLOOD REPAIRS (CN & CE) Multiple routes/counties, Reconstruct existing roadways at multiple locations $20,404,057.52 $36,846,201.26