RECIPIENT | PROJECT NUMBER |
PROJECT TITLE | TOTAL OBLIGATIONS |
ESTIMATED TOTAL COST |
---|---|---|---|---|
New York | 0016273 | NY 112 RECONS BETWEEN I-495(LIE) AND GRANNY ROAD | $32,490,601.00 | $39,208,126.00 |
New York | 0054183 | SMITHTOWN:RECONSTRUCTION OF ROUTE 347 FROM TERRY ROAD TO GIBBS POND ROAD. | $30,497,801.00 | $37,508,188.00 |
New York | 0054203 | SMITHTOWN:RECONSTRUCT ROUTE 347 FROM ROUTE 111 TO MOUNT PLEASANT ROAD. | $18,837,225.00 | $32,046,532.00 |
New York | 0054233 | RECONSTRUCT NY 347 FROM GIBBS POND ROAD TO HALLOCK ROAD | $64,925,220.00 | $79,952,032.72 |
New York | 0229483 | I495/CROOKED HILL RD INTRCHNG CONST | $24,311,883.00 | $37,054,138.00 |
New York | 0229563 | I495 PAVEMENT REHAB NASS LINE TO EXIT 55 | $24,642,324.00 | $39,585,726.00 |
New York | 0229573 | I495 Pavement Resurfacing Exit 55 to Exit 64 | $43,400,357.00 | $48,222,620.00 |
New York | 0534803 | SSP Pavement Resurfacing Exit 20 to Exit 32 | $22,255,154.00 | $27,818,944.00 |
New York | 0760653 | NASSAU COUNTY BRIDGE REHAB | $8,794,384.00 | $30,596,000.00 |
New York | 0760783 | HOSP RD/NY27 BRID WIDEN & INTERSECT IMPROV - CONST | $24,166,674.00 | $30,208,346.00 |
New York | 0761353 | WALT WHITMAN RD OVER I495 BRIDGE WIDENING | $24,258,614.29 | $30,323,268.29 |
New York | 0809253 | HEMPSTEAD:REPAIRS ON TWO DRAW BRIDGES, MEADOWBROOK STATE PARKWAY OVER SLOOP CHANNEL AND LOOP PARKWAY OVER LONG CREEK. | $20,473,758.00 | $27,605,074.00 |
New York | 1306813 | RT. 7 OVER THE HUDSON RIVER, BRIDGE REPAIR | $25,732,635.00 | $32,315,797.00 |
New York | 1525383 | I890 FROM THRUWAY EXIT26 TO I890 EXIT3 PAVEMENT REHAB | $18,081,766.00 | $25,487,115.00 |
New York | 1721513 | COLONIE:INTERSTATE 87 EXIT 4 ACCESS IMPROVEMENTS (PHASE 1) I-87 OVER ALBANY SHAKER RD-PAVEMENT RECONSTRUCTION & BRIDGE REPLACEMENT | $22,580,577.00 | $25,389,497.00 |
New York | 1721903 | I-87: EXIT 4, AIRPORT CONNECTOR, PART2 | $34,440,343.00 | $38,317,048.00 |
New York | 1810993 | DURABLE PAVEMENT MARKINGS AND INTERSTATE CRACK SEALING SFY 25-26 | $6,430,882.00 | $25,238,860.00 |
New York | 1SRP013 | AMTRAK RAIL/ LIVINGSTON AVE BRIDGE REPLACEMENT | $90,000,000.00 | $690,042,700.00 |
New York | 2134413 | UTICA:ROUTES 5, 8, & 12/NORTH SOUTH ARTERIAL & VIADUCT FROM BURRSTONE ROAD TO ORISKANY CIRCLE FOR RECONSTRUCTION. | $54,772,250.00 | $68,465,313.00 |
New York | 2326143 | UTICA:ROUTES 5A & 5S FROM CAR CRAFT COLLISION TO PLATT ST-SEPARATE SANITARY SEWER FROM STORM SEWER. | $19,993,060.00 | $25,053,826.00 |
New York | 3501903 | I-81 VIADUCT - I-481 CONVERSION TO I-81 NORTH OF KIRKVILLE RD | $132,823,362.29 | $296,386,502.00 |
New York | 3501913 | I-81 VIADUCT - I-481 CONVERSION TO I-81 SOUTH OF KIRKVILLE RD | $303,615,000.00 | $384,516,116.00 |
New York | 3501923 | I-81 VIADUCT - BL 81 NORTHERN SECTION PHASE 1 | $49,909,088.00 | $230,282,230.00 |
New York | 3501933 | I-81 VIADUCT - I-690 OVER CROUSE AND LODI | $193,689,878.89 | $344,742,117.35 |
New York | 3501943 | I-81 VIADUCT - BL 81 SOUTHERN SECTION PHASE 1 | $309,580,478.88 | |
New York | 3506413 | SYRACUSE:INTERSTATE 690 OVER TEALL AVENUE AND BEECH STREET-BRIDGE REPLACEMENT PROJECT. | $61,559,777.03 | $68,399,753.03 |
New York | 4104903 | RT 104 FROM RIDGEWAY AVE TO CULVER RD | $5,200,000.00 | $30,733,169.00 |
New York | 4390303 | I390/490 NORTHBOUND RAMPS REALIGNMENT | $53,970,592.00 | $61,664,924.00 |
New York | 4390933 | I-390 from Rt 20A (Exit 8 - Geneseo) To Exit 10 (Avon | $9,021,006.00 | $29,288,812.00 |
New York | 4490163 | 449016 - I-490 over the Erie Canal and over Kreag Rd (BINS 4443429 and 1048989) | $33,088,342.00 | $64,552,903.00 |
New York | 4590043 | I-590 OVER RT 31 BRIDGE REPLACEMENT AND I-590 over ALLEN'S CREEK RD BRIDGE DECK REPLACEMENT | $88,200.00 | $54,577,299.00 |
New York | 494X053 | RT 19 AND RT 98 OVER ERIE CANAL LIFT BRIDGE REHAB | $6,427,455.00 | $29,557,974.00 |
New York | 5006923 | I-86/CHAUTAUQUA LAKE; BRIDGE REHAB | $41,048,822.07 | $86,041,526.00 |
New York | 5111773 | Bridge Replacement & Widening US Route 20 over Cazenovia Creek, Towns of Elma & West Seneca, Erie County | $5,000,000.00 | $52,300,047.00 |
New York | 5512573 | Best Street Bridge Replacement over Kensington Expressway & New Substation, City of Buffalo, Erie County | $37,668,337.13 | $79,224,359.02 |
New York | 5760803 | BUFFALO:NY GATEWAY CONNECTIONS IMPROVEMENT TO THE US PEACE BRIDGE PLAZA. | $45,434,038.00 | $65,545,329.00 |
New York | 7111213 | BRIDGE REPLACEMENT, NY Route 12E over Chaumont River | $27,763,102.00 | $28,123,102.00 |
New York | 8006723 | WARWICK:ROUTE 17 EXIT 122 INTERCHANGE RECONSTRUCTION. | $39,617,125.00 | $81,971,616.00 |
New York | 8006843 | ROUTE 17 @ ROUTE 32 (EXIT 131) INTERCHANGE RECONSTRUCTION TOWNS OF MONROE AND WOODBURY ORANGE COUNTY. NY DEMO #583 | $113,157,814.00 | $142,642,639.00 |
New York | 8018463 | 801846 - ROUTE 28 / ESOPUS CREEK-BRIDGE REPLACEMENT - BIN 1091290, CIN C870151 | $20,837,454.00 | $26,054,894.00 |
New York | 8065103 | ROUTE 17 AT EXIT 122 STAGE II; ORANGE COUNTY | $101,489,645.00 | |
New York | 8101463 | WESTCHESTER COUNTY BRIDGES: HRP, SMRP, ROUTE 1 | $92,932,000.00 | $121,852,241.00 |
New York | 8127263 | TACONIC STATE PARKWAY @ PUDDING STREET INTERCHANGE, NEW GRADE SEPARATED INTERCHANGE, TOWN OF PUTNAM VALLEY PUTNAM COUNTY | $25,271,363.00 | $32,453,463.00 |
New York | 8239453 | ROUTE 9W: SEVEN BRIDGE REPLACEMENTS AND REHABILITATIONS IN THE TOWNS OF HIGHLANDS, CORNWALL, AND NEW WINDSOR, ORANGE COUNTY | $23,580,000.00 | $29,475,000.00 |
New York | 8392093 | US ROUTE 6, ANNSVILLE CIRCLE-CAMP SMITH: FLOOD MITIGATION; TOWN OF CORTLAND, WESTCHESTER COUNTY | $14,471,788.00 | $28,372,000.00 |
New York | 8729723 | I-287 BRIDGE DECK REPLACEMENTS OVER MIDLAND AVE AND METRO-NORTH RAILROAD, CITY OF RYE, WESTCHESTER CO. | $27,343,363.00 | $30,381,516.00 |
New York | 8756209 | FAIR STREET: RT 52 - JOHN SIMPSON ROAD, TOWN OF CARMEL, PUTNAM COUNTY | $19,379,823.00 | $27,932,279.00 |
New York | 8808623 | WURTS STREET / DOCK STREET & RONDOUT CREEK | $62,540,670.00 | $66,687,401.00 |
New York | 8813273 | BRIDGE REHABILITATION: SIX BRIDGES IN WESTCHESTER COUNTY. | $22,446,847.00 | $28,090,237.00 |
New York | 8813553 | ROUTE 9W WALL REPAIR, TOWN OF HIGHLANDS, ORANGE COUNTY | $14,097,633.00 | $29,023,616.00 |
New York | 8813683 | BRIDGE REHABILITATION/REPLACE: WESTCHESTER COUNTY | $27,875,681.00 | $45,504,078.00 |
New York | 8814073 | I-684 PMI PAVING: HUTCHINSON RIVER PARKWAY TO ROUTE 172 OVERPASS, TOWN OF BEDFORD, WESTCHESTER COUNTY | $26,373,982.62 | $29,319,932.62 |
New York | 8814893 | INTERSTATE 287 PAVING: WESTCHESTER AVENUE TO ROUTE 1, WESTCHESTER COUNTY | $32,377,766.00 | |
New York | 8815293 | RUSTIC RAIL REPLACEMENTS: WESTCHESTER COUNTY | $17,235,035.95 | $31,123,176.00 |
New York | 8LHT113 | Lower Hudson Transit Link (8823.50 & 8823.51) | $70,987,368.00 | $119,616,998.00 |
New York | 8TZ1003 | ROCKLAND AND WESTCHESTER COUNTIES:TAPPEN ZEE BRIDGE OVER THE HUDSON RIVER FOR BRIDGE REPLACEMENT (DESIGN/BUILD CONTRACT). | $3,216,685,500.00 | |
New York | 9013393 | RT 17 INTERCHANGE 105 RECONSTRUCTION AND RT 42 IMPROVEMENTS | $26,368,489.23 | $30,255,619.23 |
New York | 9038263 | RTE.434 GREENWAY: PENNSYLVANIA AVENUE TO MURRAY HILL ROAD | $22,095,631.00 | $27,619,539.00 |
New York | 9066743 | LIBERTY:ROUTE 17 @ PARKSVILLE BETWEEN MORRSTON EB ENT RAMP & FOX MOUNTAIN RD END 2 KM E OF COOLEY RD FOR RECONSTRUCT & NEW CONST. | $59,444,048.00 | $96,596,293.00 |
New York | 9067823 | RT 17 APALACHIN TO BROOME COUNTY LINE, CRACK & SEAT, TIOGA COUNTY | $35,169,591.00 | $51,612,844.00 |
New York | 9358223 | I-88 PAVEMENT & BRIDGE PROJECT, OTSEGO AND SCHOHARIE COUNTIES | $47,126,011.00 | $52,362,236.00 |
New York | 9358433 | I-88 EXIT 17 TO 18, CRACK & SEAT | $31,827,708.00 | $37,014,123.00 |
New York | 9500804 | BINGHAMTON:INTERSTATE 81/ROUTE 17 INTERCHANGE RECONSTRUCTION (PROSPECT MOUNTAIN PHASE 2) RECONST INTERCHANGE 4, INCL NEW BRIDGES, | $23,444,954.00 | $167,243,863.00 |
New York | 9501243 | 950124 - I81, EXIT 7 TO CORTLAND COUNTY LINE, MILLING AND RESURFACING | $23,293,423.00 | $25,881,585.00 |
New York | NYCD001 | NEW YORK CITY:VARIOUS HIGHWAYS IN THE VICINITY OF THE WORLD TRADE CENTER FOR AN ER PROJECT (9/11/2001 ATTACK). | $97,604,976.00 | $97,604,976.00 |
New York | X021523 | NEW YORK CITY (BROOKLYN):REPLACEMENT OF THE BELT PARKWAY BRIDGE OVER MILL BASIN IN BROOKLYN, NY TO BRING TO A STATE OF GOOD REPAIR | $164,239,866.33 | $283,299,833.33 |
New York | X021543 | NEW YORK CITY:REHABILITATION OF THE BELT PARKWAY BRIDGE OVER GERRITSON INLET. | $84,883,281.00 | $106,104,105.00 |
New York | X027083 | BRONX RIVER GREENWAY SEGMENT PHASE 2 | $29,875,863.00 | $37,344,830.00 |
New York | X051593 | Rehab of 7 Grand Central Parkway Bridges, Queens County - Design Build | $135,309,459.00 | $169,161,824.00 |
New York | X051603 | KGI INFRASTRUCTURE & OPERATIONAL IMPROVEMENT IN QUEENS CO. | $4,624,336.00 | $365,706,001.00 |
New York | X071483 | NEW YORK CITY:RECONSTRUCT THE HARLEM RIVER DRIVE VIADUCT BETWEEN E 125th & E 132nd ST INCLUDE CONST OF ENTRANCE RAMP FROM 3rd AVE ONTO SOUTHBOUND HRD. | $72,857,883.00 | $108,306,433.00 |
New York | X110263 | REPLACEMENT OF BRONX RIVER PARKWAY BRIDGES OVER MNRR, BRONX CO. (BINS 1075049 & 1075059) | $62,932,000.00 | $78,665,001.00 |
New York | X110283 | Replacement of Bronx River Parkway Bridge over Amtrak/CSX Railroad, Bronx County | $129,543,582.00 | $161,966,214.42 |
New York | X110293 | Bronx River Parkway: REPLACEMENT OF 2 BRIDGES OVER E TREMONT AVE AND MTA YARD, BRONX COUNTY | $204,527,908.30 | $565,609,082.00 |
New York | X228693 | MOBILITY IMPROVEMENT ON LIE EB B/T CLEARVIEW EXPWY & SPRINGFIELD BLVD, REPLACEMENT OF OCEANIA ST BRIDGE OVER LIE IN QUEENS COUNTY, NYC (BIN: 1055300) | $75,746,755.00 | $92,677,758.00 |
New York | X720313 | REPLACEMENT OF EAST 138TH STREET BRIDGE OVER MAJOR DEEGAN EXPRESSWAY | $40,433,862.00 | $52,860,002.00 |
New York | X720393 | Rehab of Major Deegan Expy Between W.161st St & Highbridge Interchange (BINS 1067451, 1066840) & Depot Pl Bridge Rehab over MDE (BIN 1067452) in Bronx | $114,884,833.00 | $131,315,051.00 |
New York | X720453 | REHABILITATION WEST TREMONT BRIDGE OVER MDE & MNR | $81,530,000.00 | |
New York | X726993 | NEW YORK CITY:REHAB 3 BRIDGES ALONG THE CROSS BRONX EXPRESSWAY HIGH-BRIDGE INTERCHANGE. | $45,350,697.00 | $84,509,372.00 |
New York | X727113 | Cross Bronx Expressway Active Traffic Management, Bronx Co. | $26,672,000.00 | $29,840,000.00 |
New York | X727163 | REPLACEMENT OF RAMP OCH, SHERIDAN BLVD. NORTH TO CBE WEST | $45,347,077.00 | $63,167,647.00 |
New York | X729773 | NEW YORK CITY:KOSCIUSZKO BRIDGE REPLACEMENT - Phase II. | $351,382,006.00 | $357,780,360.00 |
New York | X731273 | BRUCKNER EXPWY-HUTCHINSON PKWY MOBILITY IMPROVEMENT PROJECT, BRONX CO., NYC | $26,482,360.00 | $38,841,024.00 |
New York | X731453 | REHABILITATION OF BRUCKNER BLVD VIADUCT (278I). BRONX, NYC | $32,752,000.00 | $209,100,000.00 |
New York | X731513 | BRIDGE REHABILITATION OF BRUCKNER EXPRESSWAY (I-278) OVER ROSEDALE AVENUE, BRONX COUNTY | $46,396,800.00 | $52,411,000.00 |
New York | X731613 | GOWANUS EXPRESSWAY STEEL REPAIRS & RAMP D DECK REPLACEMENT, KINGS COUNTY | $28,725,858.00 | $32,472,621.00 |
New York | X731633 | HUNTS POINT TRUCK ACCESS IMPROVEMENT PROJECT PHASE 1, BRONX CO. NYC | $335,874,646.00 | $576,215,162.00 |
New York | X731653 | HUNTS POINT INTERSTATE ACCESS IMPROVEMENT PROJECT, CONTRACT 3, BRONX COUNTY | $49,199,999.92 | $458,164,896.92 |
New York | X731683 | REHABILITATION OF THE WOOLLEY AVE AND BRADLEY AVE BRIDGES OVER STATEN ISLAND EXPRESSWAY IN RICHMOND COUNTY, NY | $11,076,646.00 | $32,790,856.00 |
New York | X731703 | BRIDGE REHAB OF FORT HAMILTON PKWY OVER GOWANUS EXPWY, KINGS, CO. NYC | $52,547,587.00 | |
New York | X731733 | Gowanus Expressway Viaduct Painting and Steel Repairs, Kings County, NYC | $71,004,032.00 | $184,086,040.00 |
New York | X735803 | VAN WYCK EXPRESSWAY VIADUCT REHABILITATION, QUEENS COUNTY | $131,209,449.99 | $137,782,047.99 |
New York | X735843 | X73584 - (DB CONTRACT 3) VAN WYCK EXPRESSWAY CAPACITY IMPROVEMENTS | $524,485,431.28 | $815,463,266.00 |
New York | X757003 | NEW YORK CITY:WILLIS AVENUE OVER THE HARLEM RIVER FOR BRIDGE REPLACEMENT. | $217,541,858.00 | $538,557,994.00 |
New York | X757533 | BROADWAY BRIDGE REHABILITATION (2240137) | $88,720,000.00 | $110,900,000.00 |
New York | X758863 | MADISON AVE. BRIDGE REHAB (BIN 2240079) | $21,400,000.00 | $30,353,000.00 |
New York | X758923 | NEW YORK CITY (QUEENS):ROOSEVELT AVENUE OVER THE VAN WYCK EXPRESSWAY/INTERSTATE 678 FOR BRIDGE REHABILITATION. | $53,333,335.00 | $70,266,669.00 |
New York | X759193 | NYC, ER EVENT 01-02, SEPTEMBERR 11, 2001, RECONSTRUCTION OF WORTH ST, HUDSON ST. TO EAST BROADWAY | $12,000,000.00 | $95,000,000.00 |
New York | X759213 | ER EVENT NY2001-02, 9/11, NYC, MANHATTAN RECONSTRUCTION OF WARREN AND JOHN STREETS. | $8,029,697.98 | $27,429,697.98 |
New York | X759843 | NEW YORK CITY:ROUTE 9A WEST STREET PROMENADE - SITE PROJECT FOR RECONSTRUCTION. | $105,415,792.00 | $119,050,170.00 |
New York | X759846 | NEW YORK CITY:ROUTE 9A NORTH AND WEST PROMENADE PROJECT EXTRA TASKS FOR CONSTRUCTION INSPECTION AND CONSTRUCTION SUPPORT SERVICES. | $38,781,817.00 | $38,781,817.00 |
New York | X761243 | IMPLEMENT PHASE FOUR OF GRAND CONCOURSE SAFETY IMPROVEMENTS | $18,456,401.00 | $60,566,864.00 |
New York | X761263 | REHAB BROOKLYN BRIDGE, MANHATTAN APPROACHES (CONTRACT 7) | $58,987,703.13 | $159,040,843.00 |
New York | X761264 | REHABILITATE THE MANHATTAN APPROACHES TO THE BROOKLYN BRIDGE IN NY COUNTY | $39,200,000.00 | $41,263,158.00 |
New York | X762074 | TMC OPERATIONAL SUPPORT FOR FFY 19 | $36,250,000.00 | $62,556,415.00 |
New York | X764203 | PREVENTIVE MAINTENANCE INITIATIVE FOR THE EAST RIVER BRIDGES | $16,038,203.30 | $25,444,626.00 |
New York | X764263 | WILLIAMSBURG BRIDGE REHABILITATION CONTRACT # 9 (BIN2240039), NEW YORK COUNTY | $134,072,000.00 | $196,085,937.00 |
New York | X764273 | PREVENTIVE MAINTENANCE INITIATIVE FOR THE EAST RIVER BRIDGES | $22,813,144.00 | $28,516,430.00 |
New York | X770183 | NEW YORK CITY:GRAND CONCOURSE IMPROVEMENTS FROM EAST 166th STREET TO EAST 171st STREET. | $19,894,600.00 | $26,176,750.00 |
New York | X770783 | NYC:REPLACEMENT OF CITY ISLAND ROAD BRIDGE OVER EASTCHESTER BAY WITH A SINGLE SPAN CABLE-STAYED STRUCTURE. | $99,612,848.00 | $124,516,060.00 |
New York | X772433 | NEW YORK CITY:UNIONPORT BRIDGE REPLACEMENT | $148,897,916.00 | $219,825,398.00 |
New York | X772483 | NEW YORK CITY:REHABILITATION OF ATLANTIC AVENUE BRIDGE | $31,303,085.00 | $67,491,859.00 |
New York | X772513 | REHABILITATE RIVERSIDE DRIVE BRIDGE/W 158TH STREET (2246720) | $53,333,600.00 | $82,758,144.00 |
New York | X772563 | NEW YORK CITY:REHABILITATE THE WESTCHESTER AVENUE BRIDGE OVER THE HUTCHINSON RIVER PARKWAY. | $34,859,000.00 | $45,408,750.00 |
New York | X772843 | REHABILITATION MANHATTAN BRIDGE STRUCTURAL COMPONENTS (2240028) | $37,336,000.00 | $73,019,628.00 |
New York | X772863 | NEW YORK CITY:THE MACOMBS DAM BRIDGE OVER THE HARLEM RIVER FOR BRIDGE REHABILITATION. | $32,109,825.00 | $49,652,282.00 |
New York | X773093 | BROOKLYN WATERFRONT GREENWAY GOWANUS CONNECTOR | $30,948,284.00 | |
New York | X773113 | SAFETY IMPROVEMENTS ON 4TH AVENUE IN BROOKLYN (REPURPOSED EARMARK NY650 - PROGRAM CODE RPS9) | $15,774,175.00 | $50,677,414.00 |
New York | X773363 | RECONSTRUCTION OF TILLARY STREET (PHASE 2) (BROOKLYN), NEW YORK CITY. | $14,667,000.00 | $41,600,000.00 |
New York | X774073 | RECONSTRUCTION OF 5TH AVENUE BRIDGE OVER LIRR & SEA BEACH (Bridge NY), KINGS COUNTY | $45,284,117.00 | $50,802,516.00 |
New York | X777013 | EMERGENCY RELIEF NY2013-01, HURRICANE SANDY, NYCDOT (QUEENS COUNTY) PERMANENT FLOOD REPAIRS TO METROPOLITAN AVE BRIDGE BY CONTRACT | $22,600,000.00 | $28,250,000.00 |
New York | X777044 | ER EVENT NY 13-01, HURRICANE SANDY, NYCDOT PERMANENT REPAIRS TO MOVEABLE BRIDGES BY CONTRACT FORCES. | $41,673,232.00 | $52,091,540.00 |
New York | X777114 | ER EVENT NY 13-01, HURRICANE SANDY, NYCDOT PERMANENT REPAIRS TO BATTERY PARK AND WEST STREET UNDERPASSES BY CONTRACT FORCES. | $53,418,887.00 | $66,773,609.00 |
New York | X777503 | Flood Mitigation Improvements for Battery Park and West Street Underpasses in Manhattan- ER Event #NY 1301 | $36,373,971.00 | $45,467,464.00 |
New York | X806593 | LIE Active Traffic and Demand Management, I-495 between Queens-Midtown Tunnel and Main Street, Queens County | $22,065,600.00 | $27,582,000.00 |
New York | XM16563 | BRIDGE EXPANSION JOINTS REPLACEMENT AT VARIOUS FEDERAL AID ELIGIBLE LOCATIONS IN NYC | $23,289,640.00 | $29,112,051.00 |
New York | XM17033 | FDR Drive Cleaning and Painting - South Street, NY, NY | $4,122,656.00 | $38,123,007.00 |
New York | XM21603 | RETAINING WALL REHABILITATION & CORRECTIVE MAINTENANCE, ALL COUNTIES, NYC | $24,806,565.00 | $31,008,207.00 |
New York | XM22043 | BRIDGE PAINTING AT VARIOUS LOCATIONS IN BRONX, KINGS, QUEENS, AND RICHMOND COUNTIES, NYC | $18,764,261.00 | $43,729,045.00 |
New York | XM24033 | Bridge Painting at Various Federally Aid Eligible Locations in Bronx, Queens, Kings and Richmond Counties | $22,453,084.00 | $29,422,228.00 |