RECIPIENT | PROJECT NUMBER |
COUNTY | POPULATION RANGE |
OWNERSHIP | PROGRAM | TYPE OF IMPROVEMENT |
TOTAL OBLIGATIONS |
ESTIMATED TOTAL COST |
---|---|---|---|---|---|---|---|---|
Kansas | 0702047 | Gove | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $33,208,681.19 | $36,941,034.66 |
Kansas | 0702047 | Gove | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge New Construction | $443,788.10 | $493,097.89 |
Kansas | 0702047 | Gove | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Rehabilitation - No Added Capacity | $209,167.75 | $232,408.61 |
Kansas | 0702047 | Gove | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | $442,244.60 | $491,382.89 |
Kansas | 0702047 | Gove | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,651,125.74 | $2,951,940.08 |
Kansas | 0702047 | Gove | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $3,304,391.25 | $3,692,223.43 |
Kansas | 0702047 | Gove | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $2,177.70 | $2,770.35 |
Kansas | 0702047 | Gove | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Training | $4,320.00 | $12,000.00 |
Kansas | 0702047 | Gove | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $180,000.00 | $200,000.00 |
Kansas | 0705217 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $141,747,625.00 | |
Kansas | 0705217 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $40,973,640.00 | |
Kansas | 0705217 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - Added Capacity | $2,089,860.00 | |
Kansas | 0705217 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $42,247,075.00 | |
Kansas | 0705217 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $17,029,365.00 | |
Kansas | 0705217 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $10,000,000.00 | |
Kansas | 0705217 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $15,000,000.00 | |
Kansas | 0705217 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $25,000,000.00 | |
Kansas | 0706125 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $1,862,647.48 | $2,069,863.51 |
Kansas | 0706125 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - No Added Capacity | $2,795,116.36 | $3,106,068.05 |
Kansas | 0706125 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $23,918,987.07 | $26,584,013.89 |
Kansas | 0706125 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $3,332,849.51 | $3,705,178.98 |
Kansas | 0706125 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $340,736.56 | |
Kansas | 0706125 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $4,320.00 | $12,000.00 |
Kansas | 0706125 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $450,000.00 | $500,000.00 |
Kansas | 0706125 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HWY FREIGHT PGM | Bridge Replacement - Added Capacity | $29,805,513.53 | $33,117,237.26 |
Kansas | 0706125 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HWY FREIGHT PGM | Construction Engineering | $1,170,000.00 | $1,300,000.00 |
Kansas | 0706125 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HWY FREIGHT PGM | Preliminary Engineering | $4,321,193.35 | $4,840,097.27 |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | 4R - No Added Capacity | $2,047,255.99 | $2,277,146.80 |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Bridge Rehabilitation - No Added Capacity | $6,452.88 | $7,172.07 |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Bridge Replacement - No Added Capacity | $2,177,046.75 | $2,419,695.19 |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Construction Engineering | $6,807.81 | $7,919.53 |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Safety | $342,566.54 | $394,400.76 |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Training | $1,100.92 | |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $20,267,752.59 | $22,543,662.38 |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - No Added Capacity | $63,883.31 | $71,003.25 |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - No Added Capacity | $21,137,281.68 | $23,539,491.50 |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $2,475,179.55 | $2,879,380.48 |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $3,844,337.89 | $4,315,824.84 |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $6,893,294.59 | |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Safety | $310,082.73 | $420,918.27 |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $10,899.08 | |
Kansas | 2351200 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $1,230,046.34 | $1,366,718.16 |
Kansas | A100502 | Cherokee | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $32,153,831.07 | $40,209,000.84 |
Kansas | A100502 | Cherokee | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $12,291,061.77 | $15,368,315.21 |
Kansas | A100502 | Cherokee | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $4,554,819.58 | $5,697,215.81 |
Kansas | A100502 | Cherokee | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $3,760,000.00 | $4,729,381.17 |
Kansas | A100502 | Cherokee | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $4,083,063.78 | |
Kansas | A100502 | Cherokee | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $12,000.00 | |
Kansas | A100502 | Cherokee | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $608,000.00 | $764,010.27 |
Kansas | A100702 | Reno | >= 50,000 AND < 200,000 | State | CONGESTION AIR QUALITY | New Construction Roadway | $10,000,000.00 | $12,504,557.88 |
Kansas | A100702 | Reno | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $7,985,935.42 | $9,986,216.08 |
Kansas | A100702 | Reno | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $2,530,323.84 | $3,185,817.23 |
Kansas | A100702 | Reno | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | New Construction Roadway | $16,773,874.69 | $20,974,988.68 |
Kansas | A100702 | Reno | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $2,307,106.06 | $2,921,959.78 |
Kansas | A100702 | Reno | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $5,795,395.56 | |
Kansas | A100702 | Reno | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $12,000.00 | |
Kansas | A100702 | Reno | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $2,813,600.00 | $3,517,000.00 |
Kansas | A100703 | Rice | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $9,407,473.88 | $11,764,089.55 |
Kansas | A100703 | Rice | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $2,714,264.32 | $3,406,674.72 |
Kansas | A100703 | Rice | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | New Construction Roadway | $23,301,308.70 | $29,137,888.68 |
Kansas | A100703 | Rice | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $2,964,727.84 | $3,726,248.43 |
Kansas | A100703 | Rice | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $3,637,539.53 | |
Kansas | A100703 | Rice | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $12,000.00 | |
Kansas | A100703 | Rice | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $2,124,000.00 | $2,655,145.49 |
Kansas | A100802 | Haskell | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $393,500.00 | |
Kansas | A100802 | Haskell | < 5,000 | State | NATIONAL HIGHWAY SYSTEM | Preliminary Engineering | $1,150,000.00 | |
Kansas | A100802 | Haskell | < 5,000 | State | NATIONAL HWY FREIGHT PGM | 4R - No Added Capacity | $20,906,528.00 | $26,133,160.00 |
Kansas | A100802 | Haskell | < 5,000 | State | NATIONAL HWY FREIGHT PGM | Construction Engineering | $1,567,992.00 | $1,959,990.00 |
Kansas | A126606 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $517,696.11 | $575,523.66 |
Kansas | A126606 | Shawnee | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $144,040.09 | $160,106.47 |
Kansas | A126606 | Shawnee | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $2,015,982.00 | $2,239,980.00 |
Kansas | A126606 | Shawnee | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $19,732,303.89 | $21,936,436.24 |
Kansas | A126606 | Shawnee | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $90,000.00 | $100,000.00 |
Kansas | A155302 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $1,141.45 | $1,427.91 |
Kansas | A155302 | Bourbon | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $13,696,261.75 | $17,133,550.09 |
Kansas | A155302 | Bourbon | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $2,406,272.44 | $3,010,208.36 |
Kansas | A155302 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $200.54 | $250.87 |
Kansas | A155302 | Bourbon | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - Added Capacity | $414,786.52 | $518,891.14 |
Kansas | A155302 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $101.69 | $127.65 |
Kansas | A155302 | Bourbon | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,220,230.17 | $1,531,717.51 |
Kansas | A155302 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $268.38 | $336.97 |
Kansas | A155302 | Bourbon | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $3,220,306.84 | $4,043,332.60 |
Kansas | A155302 | Bourbon | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $1,531,918.09 | |
Kansas | A155302 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $127.67 | |
Kansas | A155302 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $0.21 | $0.65 |
Kansas | A155302 | Bourbon | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $2,495.79 | $7,799.35 |
Kansas | A155302 | Bourbon | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $393,163.01 | $491,588.87 |
Kansas | A155302 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $32.77 | $40.97 |
Kansas | A155402 | Crawford | >= 5,000 AND < 50,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Preliminary Engineering | $1,704,720.00 | $1,714,315.04 |
Kansas | A155402 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $17,512,853.33 | $21,906,972.26 |
Kansas | A155402 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - Added Capacity | $101,753.81 | $127,286.67 |
Kansas | A155402 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,765,903.05 | $2,219,591.57 |
Kansas | A155402 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $2,258,345.26 | $2,835,642.71 |
Kansas | A155402 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $997,513.52 | |
Kansas | A155402 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $7,200.00 | |
Kansas | A155402 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $1,333,670.02 | $1,668,378.10 |
Kansas | A155403 | Crawford | >= 5,000 AND < 50,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Preliminary Engineering | $1,500,000.00 | $1,563,626.33 |
Kansas | A155403 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $16,649,568.34 | $20,827,106.03 |
Kansas | A155403 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $877,917.15 | $1,098,202.84 |
Kansas | A155403 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - No Added Capacity | $52,281.27 | $65,399.59 |
Kansas | A155403 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $2,319,847.40 | $2,901,840.54 |
Kansas | A155403 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $153,397.39 | $159,904.13 |
Kansas | A155403 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $958,661.71 | |
Kansas | A155403 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $7,000.00 | |
Kansas | A155403 | Crawford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $902,268.74 | $1,131,707.13 |
Kansas | A158601 | Cherokee | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $27,940,549.87 | $35,080,702.78 |
Kansas | A158601 | Cherokee | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge New Construction | $243,512.21 | $304,529.47 |
Kansas | A158601 | Cherokee | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,105,387.72 | $2,653,289.93 |
Kansas | A158601 | Cherokee | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $1,362,087.05 | $1,741,467.22 |
Kansas | A158601 | Cherokee | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $3,194,276.20 | |
Kansas | A158601 | Cherokee | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Training | $2,496.00 | $7,800.00 |
Kansas | A158601 | Cherokee | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $2,824,188.10 | $3,536,891.02 |
Kansas | A236801 | Morris | >= 5,000 AND < 50,000 | State | CONGESTION AIR QUALITY | 4R - Restoration & Rehabilitation | $17,491,476.57 | $21,878,344.97 |
Kansas | A236801 | Morris | >= 5,000 AND < 50,000 | State | CONGESTION AIR QUALITY | Bridge Rehabilitation - Added Capacity | $773,882.90 | $967,973.00 |
Kansas | A236801 | Morris | >= 5,000 AND < 50,000 | State | CONGESTION AIR QUALITY | Bridge Replacement - Added Capacity | $1,725,972.14 | $2,158,846.54 |
Kansas | A236801 | Morris | >= 5,000 AND < 50,000 | State | CONGESTION AIR QUALITY | Construction Engineering | $1,467,482.31 | $1,875,306.73 |
Kansas | A236801 | Morris | >= 5,000 AND < 50,000 | State | CONGESTION AIR QUALITY | Preliminary Engineering | $1,992,028.20 | |
Kansas | A236801 | Morris | >= 5,000 AND < 50,000 | State | CONGESTION AIR QUALITY | Right of Way | $2,084,012.04 | |
Kansas | A236801 | Morris | >= 5,000 AND < 50,000 | State | CONGESTION AIR QUALITY | Training | $5,800.00 | |
Kansas | A236801 | Morris | >= 5,000 AND < 50,000 | State | CONGESTION AIR QUALITY | Utilities | $2,784,060.53 | |
Kansas | A236901 | Geary | >= 5,000 AND < 50,000 | State | HIGHWAY INFRA PRGM -APPOR | 4R - Restoration & Rehabilitation | $1,015,295.50 | $1,269,119.38 |
Kansas | A236901 | Morris | >= 5,000 AND < 50,000 | State | HIGHWAY INFRA PRGM -APPOR | 4R - Restoration & Rehabilitation | $804.50 | $1,005.62 |
Kansas | A236901 | Morris | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | $15,627.08 | $19,545.51 |
Kansas | A236901 | Geary | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | $19,721,800.59 | $24,666,967.08 |
Kansas | A236901 | Geary | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Rehabilitation - Added Capacity | $483,348.01 | $604,535.41 |
Kansas | A236901 | Geary | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - Added Capacity | $1,272,316.81 | $1,591,317.62 |
Kansas | A236901 | Geary | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $1,830,912.18 | $2,315,990.16 |
Kansas | A236901 | Morris | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $1,450.77 | $1,835.13 |
Kansas | A236901 | Morris | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $1,521.57 | |
Kansas | A236901 | Geary | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $1,920,258.10 | |
Kansas | A236901 | Geary | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $2,506,137.55 | |
Kansas | A236901 | Morris | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $1,985.80 | |
Kansas | A236901 | Morris | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Training | $2.22 | |
Kansas | A236901 | Geary | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Training | $2,797.78 | |
Kansas | A236901 | Geary | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $1,251,844.66 | |
Kansas | A236901 | Morris | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $991.93 | |
Kansas | A237003 | Russell | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $11,214,253.54 | $35,604,315.84 |
Kansas | A237003 | Russell | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Rehabilitation - Added Capacity | $243,884.45 | |
Kansas | A237003 | Russell | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - Added Capacity | $856,420.71 | |
Kansas | A237003 | Russell | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,884,745.37 | |
Kansas | A237003 | Russell | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $599,446.18 | |
Kansas | A237003 | Russell | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $603,291.54 | |
Kansas | A237003 | Russell | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Training | $12,000.00 | |
Kansas | A237003 | Russell | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $1,165,748.40 | |
Kansas | A237303 | Miami | >= 5,000 AND < 50,000 | State | REPURPOSED EARMARK SUBJ TO LIM | 4R - No Added Capacity | $387,248.64 | $484,175.00 |
Kansas | A237303 | Miami | >= 5,000 AND < 50,000 | State | REPURPOSED EARMARK SUBJ TO LIM | Bridge Rehabilitation - Added Capacity | $19,050.36 | $23,818.65 |
Kansas | A237303 | Miami | >= 5,000 AND < 50,000 | State | REPURPOSED EARMARKS EXEMPT | 4R - No Added Capacity | $121,347.62 | $121,376.25 |
Kansas | A237303 | Miami | >= 5,000 AND < 50,000 | State | REPURPOSED EARMARKS EXEMPT | Bridge Rehabilitation - Added Capacity | $5,969.59 | $5,971.02 |
Kansas | A237303 | Miami | >= 5,000 AND < 50,000 | State | REPURPOSED SPECIAL | 4R - No Added Capacity | $2,877,009.16 | $3,597,110.45 |
Kansas | A237303 | Miami | >= 5,000 AND < 50,000 | State | REPURPOSED SPECIAL | Bridge Rehabilitation - Added Capacity | $141,532.43 | $176,957.30 |
Kansas | A237303 | Miami | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $9,558,047.26 | $11,950,377.80 |
Kansas | A237303 | Miami | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Rehabilitation - Added Capacity | $470,199.86 | $587,890.38 |
Kansas | A237303 | Miami | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $1,332,535.97 | $1,666,387.85 |
Kansas | A237303 | Miami | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $915,183.50 | |
Kansas | A237303 | Miami | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $5,544,684.45 | |
Kansas | A237303 | Miami | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $2,342,865.52 | $2,928,581.90 |
Kansas | A238001 | Anderson | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $16,101,757.60 | $20,148,741.01 |
Kansas | A238001 | Anderson | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - No Added Capacity | $896,348.51 | $1,121,291.63 |
Kansas | A238001 | Anderson | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,341,691.14 | $1,687,050.50 |
Kansas | A238001 | Anderson | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $1,294,505.75 | $1,645,369.33 |
Kansas | A238001 | Anderson | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $1,264,435.75 | |
Kansas | A238001 | Anderson | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $1,283,114.34 | $1,603,956.39 |
Kansas | A238301 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $26,748,925.23 | $33,436,156.54 |
Kansas | A238301 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $1,480,487.06 | $1,850,608.83 |
Kansas | A238301 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $1,526,870.34 | $1,908,587.92 |
Kansas | A238301 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $2,348,841.36 | $2,948,510.80 |
Kansas | A238301 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $2,358,672.55 | $2,969,706.87 |
Kansas | A238301 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $1,662,388.30 | |
Kansas | A238301 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $7,600.00 | |
Kansas | A238301 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $627,199.10 | $785,826.27 |
Kansas | A238401 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $10,682.37 | $13,369.91 |
Kansas | A238401 | Ford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $36,570,034.25 | $45,770,569.06 |
Kansas | A238401 | Ford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $1,544,586.40 | $1,931,348.81 |
Kansas | A238401 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $451.18 | $564.16 |
Kansas | A238401 | Ford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - Added Capacity | $2,077,062.19 | $2,597,156.54 |
Kansas | A238401 | Ford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $219,825.18 | $274,869.48 |
Kansas | A238401 | Ford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $3,206,117.83 | $4,034,827.99 |
Kansas | A238401 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $936.53 | $1,178.60 |
Kansas | A238401 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $994.06 | $1,249.58 |
Kansas | A238401 | Ford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $3,403,071.90 | $4,277,811.04 |
Kansas | A238401 | Ford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $8,809,844.85 | |
Kansas | A238401 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $2,573.42 | |
Kansas | A238401 | Ford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $9,600.00 | |
Kansas | A238401 | Ford | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $2,875,588.87 | $3,639,173.32 |
Kansas | A238401 | Gray | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $839.98 | $1,063.03 |
Kansas | A238501 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $18,937,615.46 | $23,688,019.32 |
Kansas | A238501 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,493,333.70 | $1,885,149.48 |
Kansas | A238501 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $1,440,000.00 | $1,810,564.79 |
Kansas | A238501 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $1,592,494.20 | |
Kansas | A238501 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $6,000.00 | |
Kansas | A238501 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $4,357,573.39 | $5,447,019.24 |
Kansas | A238503 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $16,899,743.17 | $21,136,706.16 |
Kansas | A238503 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $5,185,306.02 | $6,485,386.12 |
Kansas | A238503 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - Added Capacity | $301,923.23 | $377,623.24 |
Kansas | A238503 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,768,826.78 | $2,217,763.46 |
Kansas | A238503 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $989,138.10 | $1,274,625.32 |
Kansas | A238503 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $414,960.52 | |
Kansas | A238503 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $12,000.00 | |
Kansas | A238503 | Seward | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $4,082,444.39 | $5,295,977.19 |
Kansas | A307901 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $5,101,121.93 | $6,389,876.01 |
Kansas | A307901 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $13,085,110.21 | $16,367,914.17 |
Kansas | A307901 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,453,739.76 | $1,819,223.84 |
Kansas | A307901 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $1,373,782.05 | $1,737,485.13 |
Kansas | A307901 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $2,752.14 | |
Kansas | A307901 | Wyandotte | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $48,000.00 | $60,000.00 |
Kansas | A323203 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $13,910,926.08 | $15,905,210.60 |
Kansas | A323203 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $5,319,057.58 | $5,917,186.67 |
Kansas | A323203 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | New Construction Roadway | $13,571,800.24 | $15,577,377.65 |
Kansas | A323203 | Sedgwick | >= 200,000 | N/A | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $3,973,386.56 | $4,496,823.08 |
Kansas | A323203 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $1,562,121.08 | |
Kansas | A323203 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $10,285.71 | |
Kansas | A323203 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $7,553,475.39 | $8,392,750.43 |
Kansas | A323203 | Sedgwick | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge New Construction | $2,318,487.68 | $2,650,868.44 |
Kansas | A323203 | Sedgwick | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | New Construction Roadway | $2,261,966.70 | $2,596,229.59 |
Kansas | A323203 | Sedgwick | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Training | $1,714.29 | |
Kansas | A323222 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $7,033,228.59 | $27,363,971.33 |
Kansas | A323222 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $3,947,957.74 | $15,359,037.74 |
Kansas | A323222 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - Added Capacity | $98,856.07 | $384,587.45 |
Kansas | A323222 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $3,878,509.89 | $15,088,859.77 |
Kansas | A323222 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,714,048.93 | $12,865,107.53 |
Kansas | A323222 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Safety | $5,646.06 | $27,039.72 |
Kansas | A323222 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Special Bridge | $421,752.72 | $1,640,775.87 |
Kansas | A323222 | Sedgwick | >= 200,000 | State | NATL INTRASTRUCTURE INVESTMENT | 4R - No Added Capacity | $9,599,523.61 | $37,348,578.33 |
Kansas | A323222 | Sedgwick | >= 200,000 | State | NATL INTRASTRUCTURE INVESTMENT | Bridge New Construction | $5,388,494.49 | $20,963,266.44 |
Kansas | A323222 | Sedgwick | >= 200,000 | State | NATL INTRASTRUCTURE INVESTMENT | Bridge Rehabilitation - Added Capacity | $134,926.80 | $524,916.22 |
Kansas | A323222 | Sedgwick | >= 200,000 | State | NATL INTRASTRUCTURE INVESTMENT | Bridge Replacement - Added Capacity | $5,293,706.41 | $20,594,505.64 |
Kansas | A323222 | Sedgwick | >= 200,000 | State | NATL INTRASTRUCTURE INVESTMENT | Safety | $7,706.20 | $36,906.05 |
Kansas | A323222 | Sedgwick | >= 200,000 | State | NATL INTRASTRUCTURE INVESTMENT | Special Bridge | $575,642.49 | $2,239,464.61 |
Kansas | A323601 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $40,160,130.85 | |
Kansas | A323601 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $6,067,770.39 | |
Kansas | A323601 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Resurfacing | $930,191.69 | |
Kansas | A323601 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $3,766,792.53 | |
Kansas | A323601 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $2,626,959.83 | |
Kansas | A323601 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $322,739.74 | |
Kansas | A323601 | Shawnee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $163,807.15 | |
Kansas | A325501 | Allen | >= 5,000 AND < 50,000 | State | HIGHWAY INFRA PRGM -APPOR | 4R - No Added Capacity | $546,308.50 | $683,512.15 |
Kansas | A325501 | Neosho | >= 5,000 AND < 50,000 | State | HIGHWAY INFRA PRGM -APPOR | 4R - No Added Capacity | $3,807,543.53 | $4,763,796.03 |
Kansas | A325501 | Neosho | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $18,139,669.69 | $22,687,624.90 |
Kansas | A325501 | Allen | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $2,602,690.04 | $3,255,233.22 |
Kansas | A325501 | Allen | >= 5,000 AND < 50,000 | N/A | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - No Added Capacity | $458,384.70 | $573,262.12 |
Kansas | A325501 | Neosho | >= 5,000 AND < 50,000 | N/A | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - No Added Capacity | $516,901.90 | $646,444.54 |
Kansas | A325501 | Allen | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $168,468.27 | $210,800.86 |
Kansas | A325501 | Neosho | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,174,153.93 | $1,469,194.49 |
Kansas | A325501 | Allen | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $228,139.49 | |
Kansas | A325501 | Neosho | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $1,590,037.55 | |
Kansas | A325501 | Allen | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $1,179.48 | |
Kansas | A325501 | Neosho | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | $8,220.52 | |
Kansas | A325501 | Neosho | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $347,549.42 | $439,602.42 |
Kansas | A325501 | Allen | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $49,866.58 | $63,074.39 |
Kansas | A363403 | Douglas | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $179,064,300.00 | |
Kansas | A363403 | Douglas | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | $22,620,610.00 | |
Kansas | A363403 | Douglas | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - Added Capacity | $2,320,560.00 | |
Kansas | A363403 | Douglas | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $1,170,930.00 | |
Kansas | A363403 | Douglas | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $13,429,825.00 | |
Kansas | A363403 | Douglas | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $10,800,000.00 | |
Kansas | A363403 | Douglas | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $16,000,000.00 | |
Kansas | A570003 | Johnson | >= 200,000 | State | HIGHWAY INFRA PRGM - COVID APP | 4R - Added Capacity | $5,316,676.00 | $6,645,845.00 |
Kansas | A570003 | Johnson | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $87,060,506.59 | $525,915,484.00 |
Kansas | A570003 | Johnson | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $5,600,000.00 | $35,000,000.00 |
Kansas | A570003 | Johnson | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $7,200,000.00 | $45,000,000.00 |
Kansas | A580201 | Hodgeman | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | $29,420,080.98 | |
Kansas | A580201 | Hodgeman | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,942,008.10 | |
Kansas | A580201 | Hodgeman | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $1,107,500.00 | |
Kansas | A580201 | Hodgeman | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $350,930.00 | |
Kansas | A605601 | Kingman | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $34,008,405.10 | |
Kansas | A605601 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $51,927.10 | |
Kansas | A605601 | Kingman | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - Added Capacity | $1,950,495.60 | |
Kansas | A605601 | Kingman | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $2,515,485.91 | |
Kansas | A605601 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $3,840.87 | |
Kansas | A605601 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $1,023.70 | |
Kansas | A605601 | Kingman | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $670,443.82 | |
Kansas | A605601 | Kingman | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $149,014.03 | |
Kansas | A605601 | Sedgwick | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $227.53 | |
Kansas | A606201 | Geary | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $29,076,463.15 | |
Kansas | A606201 | Geary | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $2,036,105.49 | |
Kansas | A606201 | Geary | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $777,439.50 |