RECIPIENT | PROJECT NUMBER |
COUNTY | POPULATION RANGE |
OWNERSHIP | PROGRAM | TYPE OF IMPROVEMENT |
TOTAL OBLIGATIONS |
ESTIMATED TOTAL COST |
---|---|---|---|---|---|---|---|---|
North Dakota | 1094208 | Morton | >= 5,000 AND < 50,000 | State | HIGHWAY INFRA PRGM -APPOR | Bridge Replacement - Added Capacity | $14,246,499.51 | $15,829,443.90 |
North Dakota | 1094208 | Morton | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - Added Capacity | $10,542,226.60 | |
North Dakota | 1094208 | Morton | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,637,167.06 | |
North Dakota | 1094208 | Morton | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $805,715.28 | $895,239.20 |
North Dakota | 1094212 | Burleigh | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $26,389,730.29 | $29,535,207.34 |
North Dakota | 1094212 | Burleigh | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $2,638,973.04 | $2,953,520.74 |
North Dakota | 1094212 | Burleigh | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $857,433.95 | $952,704.39 |
North Dakota | 1094212 | Burleigh | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $1,730,010.83 | $1,922,234.26 |
North Dakota | 1094212 | Burleigh | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $2,106,855.95 | $2,603,306.50 |
North Dakota | 1094212 | Burleigh | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | $11,480.00 | |
North Dakota | 1094212 | Burleigh | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - Added Capacity | $13,813,273.98 | $15,348,082.20 |
North Dakota | 1094212 | Burleigh | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $1,381,327.40 | $1,534,808.22 |
North Dakota | 1094212 | Burleigh | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $210,685.60 | $261,478.66 |
North Dakota | 1094212 | Burleigh | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $1,800.00 | $2,000.00 |
North Dakota | 1094212 | Burleigh | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $360,000.00 | $400,000.00 |
North Dakota | 1094212 | Burleigh | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $697,572.00 | $775,080.00 |
North Dakota | 1094214 | Burleigh | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM - COVID APP | 4R - No Added Capacity | $1,953,150.24 | $1,953,150.24 |
North Dakota | 1094214 | Burleigh | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $969,989.31 | $1,077,765.90 |
North Dakota | 1094214 | Burleigh | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $1,600,000.00 | |
North Dakota | 1094214 | Burleigh | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $16,853,322.09 | $28,300,903.20 |
North Dakota | 1094214 | Burleigh | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Rehabilitation - Added Capacity | $314,815.00 | |
North Dakota | 1094214 | Burleigh | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $3,164,663.43 | |
North Dakota | 1094223 | Morton | >= 5,000 AND < 50,000 | State | CONGESTION AIR QUALITY | Right of Way | $1,052,090.00 | $1,300,000.00 |
North Dakota | 1094223 | Morton | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $20,310,410.74 | $25,096,269.30 |
North Dakota | 1094223 | Morton | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | $3,515,607.11 | $10,386,948.00 |
North Dakota | 1094223 | Morton | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | $623,004.81 | $1,441,445.50 |
North Dakota | 1094223 | Morton | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $1,787,793.14 | $3,548,321.73 |
North Dakota | 1094223 | Morton | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $62,300.48 | $144,144.55 |
North Dakota | 1A94078 | Burleigh | >= 50,000 AND < 200,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Bridge Replacement - Added Capacity | $16,490,933.00 | $18,323,258.88 |
North Dakota | 1A94078 | Morton | >= 5,000 AND < 50,000 | N/A | HIGH PRIORITY PROJECT SEC 1702 | Bridge Replacement - Added Capacity | $7,544,468.00 | $8,712,182.62 |
North Dakota | 5094143 | Golden Valley | < 5,000 | State | HIGHWAY INFRA PRGM -APPOR | Bridge Rehabilitation - Added Capacity | $1,908,301.28 | $2,120,334.75 |
North Dakota | 5094143 | Golden Valley | < 5,000 | State | HIGHWAY INFRA PRGM -APPOR | Construction Engineering | $190,830.13 | $212,033.48 |
North Dakota | 5094143 | Golden Valley | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $23,833,112.27 | $26,481,235.86 |
North Dakota | 5094143 | Golden Valley | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $3,243,967.73 | $3,604,408.59 |
North Dakota | 5094143 | Golden Valley | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $540,000.00 | $600,000.00 |
North Dakota | 5094143 | Golden Valley | < 5,000 | State | NATIONAL HWY FREIGHT PGM | 4R - No Added Capacity | $8,606,565.00 | $9,562,850.00 |
North Dakota | 5094143 | Golden Valley | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $2,197,274.21 | $2,441,415.79 |
North Dakota | 5094143 | Golden Valley | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $219,727.42 | $244,141.58 |
North Dakota | 5094150 | Golden Valley | < 5,000 | State | HIGHWAY INFRA PRGM -APPOR | Bridge Rehabilitation - Added Capacity | $1,014,301.19 | $1,127,001.32 |
North Dakota | 5094150 | Golden Valley | < 5,000 | State | HIGHWAY INFRA PRGM -APPOR | Bridge Replacement - Added Capacity | $1,362,090.16 | $1,513,433.51 |
North Dakota | 5094150 | Golden Valley | < 5,000 | State | HIGHWAY INFRA PRGM -APPOR | Construction Engineering | $237,639.14 | $264,043.49 |
North Dakota | 5094150 | Golden Valley | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $16,769,422.90 | $18,632,692.11 |
North Dakota | 5094150 | Golden Valley | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $2,989,827.15 | $3,322,030.17 |
North Dakota | 5094150 | Golden Valley | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $1,700,000.00 | |
North Dakota | 5094150 | Golden Valley | < 5,000 | State | NATIONAL HWY FREIGHT PGM | 4R - No Added Capacity | $8,778,696.00 | $9,754,106.67 |
North Dakota | 5094150 | Golden Valley | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $4,350,152.66 | $4,833,502.96 |
North Dakota | 5094152 | Billings | < 5,000 | State | CONGESTION AIR QUALITY | 4R - Added Capacity | $3,079,970.98 | $3,805,722.21 |
North Dakota | 5094152 | Billings | < 5,000 | State | HIGHWAY INFRA PRGM -APPOR | Bridge Rehabilitation - Added Capacity | $312,284.56 | $385,869.96 |
North Dakota | 5094152 | Billings | < 5,000 | State | REDISTRIBUTION OF CERTAIN AUTH | 4R - Added Capacity | $1,208,669.77 | $1,493,475.56 |
North Dakota | 5094152 | Billings | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $6,138,844.75 | $7,585,375.94 |
North Dakota | 5094152 | Billings | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | $160,000.00 | |
North Dakota | 5094152 | Billings | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Rehabilitation - Added Capacity | $8,764,705.27 | $10,829,983.04 |
North Dakota | 5094152 | Billings | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $1,950,447.53 | $2,426,042.67 |
North Dakota | 5094152 | Billings | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $4,851,401.39 | $5,994,564.92 |
North Dakota | 5094152 | Billings | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $97,116.00 | $120,000.00 |
North Dakota | 7085116 | McKenzie | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $3,800,000.00 | |
North Dakota | 7085116 | McKenzie | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $74,225,470.56 | |
North Dakota | 7085116 | McKenzie | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - Added Capacity | $1,482,850.90 | |
North Dakota | 7085116 | McKenzie | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $7,722,950.33 | |
North Dakota | 7085116 | McKenzie | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Facilities for Pedestrians and Bicycles | $1,521,181.75 | |
North Dakota | 7085116 | McKenzie | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $1,400,000.00 | |
North Dakota | 7085116 | McKenzie | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $3,404,924.19 | $4,207,246.00 |
North Dakota | 8029173 | Statewide | N/A | State | HIGHWAY INFRA PRGM -APPOR | Bridge Rehabilitation - Added Capacity | $439,962.93 | $488,847.70 |
North Dakota | 8029173 | Traill | >= 5,000 AND < 50,000 | State | HIGHWAY INFRA PRGM -APPOR | Bridge Replacement - Added Capacity | $1,600,399.35 | $1,778,221.50 |
North Dakota | 8029173 | Traill | >= 5,000 AND < 50,000 | State | HIGHWAY INFRA PRGM -APPOR | Construction Engineering | $160,039.94 | $177,822.15 |
North Dakota | 8029173 | Statewide | N/A | State | HIGHWAY INFRA PRGM -APPOR | Construction Engineering | $43,996.29 | $48,884.77 |
North Dakota | 8029173 | Traill | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $9,246,462.39 | $10,273,847.10 |
North Dakota | 8029173 | Cass | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $3,815,357.63 | $4,239,286.26 |
North Dakota | 8029173 | Traill | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,521,958.67 | $1,691,065.19 |
North Dakota | 8029173 | Cass | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $628,004.13 | $697,782.37 |
North Dakota | 8029173 | Traill | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $219,240.64 | $243,600.71 |
North Dakota | 8029173 | Cass | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $90,465.03 | $100,516.70 |
North Dakota | 8029173 | Cass | >= 50,000 AND < 200,000 | State | NATIONAL HWY FREIGHT PGM | 4R - Added Capacity | $2,464,683.71 | $2,738,537.45 |
North Dakota | 8029173 | Traill | >= 5,000 AND < 50,000 | State | NATIONAL HWY FREIGHT PGM | 4R - Added Capacity | $5,973,124.29 | $6,636,804.77 |
North Dakota | 8094098 | Cass | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Bridge Rehabilitation - Added Capacity | $350,903.78 | $389,893.08 |
North Dakota | 8094098 | Cass | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Construction Engineering | $35,090.38 | $38,989.30 |
North Dakota | 8094098 | Cass | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $83.97 | $93.30 |
North Dakota | 8094098 | Cass | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $818,316.00 | $909,240.00 |
North Dakota | 8094098 | Cass | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $20,770,320.39 | $23,078,133.77 |
North Dakota | 8094098 | Cass | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,077,032.04 | $2,307,813.38 |
North Dakota | 8094098 | Cass | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $19,716.03 | $21,906.70 |
North Dakota | 9052056 | Ward | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Bridge Rehabilitation - Added Capacity | $430,353.37 | $887,692.60 |
North Dakota | 9052056 | Ward | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Construction Engineering | $43,035.34 | $88,769.26 |
North Dakota | 9052056 | Wells | < 5,000 | State | HSIP LIMITING FLEXIBLE | Construction Engineering | $1,005,082.88 | |
North Dakota | 9052056 | Sheridan | < 5,000 | State | HSIP LIMITING FLEXIBLE | Construction Engineering | $233,298.85 | |
North Dakota | 9052056 | McHenry | >= 5,000 AND < 50,000 | State | HSIP LIMITING FLEXIBLE | Construction Engineering | $590,819.27 | |
North Dakota | 9052056 | Pierce | < 5,000 | State | HSIP LIMITING FLEXIBLE | Construction Engineering | $87,798.58 | |
North Dakota | 9052056 | Pierce | < 5,000 | State | HSIP LIMITING FLEXIBLE | Safety | $366,395.80 | $793,097.63 |
North Dakota | 9052056 | McHenry | >= 5,000 AND < 50,000 | State | HSIP LIMITING FLEXIBLE | Safety | $5,427,130.60 | $8,298,517.14 |
North Dakota | 9052056 | Sheridan | < 5,000 | State | HSIP LIMITING FLEXIBLE | Safety | $973,588.85 | $2,107,423.19 |
North Dakota | 9052056 | Wells | < 5,000 | State | HSIP LIMITING FLEXIBLE | Safety | $4,194,351.98 | $9,079,063.09 |
North Dakota | 9052056 | Ward | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Safety | $750,598.14 | $750,598.14 |
North Dakota | 9052056 | Renville | < 5,000 | State | NAT SIG FREIGHT AND HWY PROJ | 4R - Added Capacity | $705,664.80 | $1,106,715.47 |
North Dakota | 9052056 | Foster | < 5,000 | State | NAT SIG FREIGHT AND HWY PROJ | 4R - Added Capacity | $1,544,584.54 | $1,930,730.68 |
North Dakota | 9052056 | Ward | >= 50,000 AND < 200,000 | State | NAT SIG FREIGHT AND HWY PROJ | 4R - Added Capacity | $5,431,949.19 | $8,519,090.35 |
North Dakota | 9052056 | Wells | < 5,000 | State | NAT SIG FREIGHT AND HWY PROJ | 4R - Added Capacity | $8,103,039.10 | $10,128,798.87 |
North Dakota | 9052056 | Statewide | N/A | N/A | NAT SIG FREIGHT AND HWY PROJ | Bridge Rehabilitation - Added Capacity | $2,310,489.00 | |
North Dakota | 9052056 | Statewide | N/A | N/A | NAT SIG FREIGHT AND HWY PROJ | Construction Engineering | $231,048.90 | |
North Dakota | 9052056 | Wells | < 5,000 | State | NAT SIG FREIGHT AND HWY PROJ | Construction Engineering | $810,303.91 | $1,012,879.89 |
North Dakota | 9052056 | Ward | >= 50,000 AND < 200,000 | State | NAT SIG FREIGHT AND HWY PROJ | Construction Engineering | $851,883.81 | |
North Dakota | 9052056 | Foster | < 5,000 | State | NAT SIG FREIGHT AND HWY PROJ | Construction Engineering | $154,458.46 | $193,073.07 |
North Dakota | 9052056 | Renville | < 5,000 | State | NAT SIG FREIGHT AND HWY PROJ | Construction Engineering | $110,696.77 | |
North Dakota | 9052056 | McHenry | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $4,103,217.63 | $11,610,999.87 |
North Dakota | 9052056 | Ward | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $1,039,948.11 | $2,942,772.84 |
North Dakota | 9052056 | Ward | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $179,054.62 | $369,337.09 |
North Dakota | 9052056 | McHenry | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $706,477.65 | $1,457,255.88 |
North Dakota | 9052056 | McHenry | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Safety | $462,300.00 | $571,234.40 |
North Dakota | 9052056 | Sheridan | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Safety | $182,550.00 | $225,565.30 |
North Dakota | 9052056 | Pierce | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Safety | $68,700.00 | $84,888.17 |
North Dakota | 9052056 | Wells | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Safety | $786,450.00 | $971,765.73 |
North Dakota | 9999500 | Eddy | < 5,000 | State | NATL INTRASTRUCTURE INVESTMENT | 4R - Restoration & Rehabilitation | $1,186,328.12 | $2,731,586.73 |
North Dakota | 9999500 | Kidder | < 5,000 | State | NATL INTRASTRUCTURE INVESTMENT | 4R - Restoration & Rehabilitation | $1,638,633.12 | $3,773,044.26 |
North Dakota | 9999500 | Wells | < 5,000 | State | NATL INTRASTRUCTURE INVESTMENT | 4R - Restoration & Rehabilitation | $2,149,747.46 | $4,949,913.57 |
North Dakota | 9999500 | McHenry | >= 5,000 AND < 50,000 | State | NATL INTRASTRUCTURE INVESTMENT | 4R - Restoration & Rehabilitation | $3,363,765.30 | $7,745,257.43 |
North Dakota | 9999500 | Mountrail | >= 5,000 AND < 50,000 | State | NATL INTRASTRUCTURE INVESTMENT | 4R - Restoration & Rehabilitation | $710,283.16 | $1,635,466.64 |
North Dakota | 9999500 | LaMoure | < 5,000 | State | NATL INTRASTRUCTURE INVESTMENT | 4R - Restoration & Rehabilitation | $2,225,879.40 | $5,125,211.60 |
North Dakota | 9999500 | Sheridan | < 5,000 | State | NATL INTRASTRUCTURE INVESTMENT | 4R - Restoration & Rehabilitation | $3,358,826.88 | $7,733,886.44 |
North Dakota | 9999500 | Stutsman | >= 5,000 AND < 50,000 | State | NATL INTRASTRUCTURE INVESTMENT | 4R - Restoration & Rehabilitation | $3,860,498.84 | $8,889,014.13 |
North Dakota | 9999500 | Ward | >= 50,000 AND < 200,000 | State | NATL INTRASTRUCTURE INVESTMENT | 4R - Restoration & Rehabilitation | $1,299,966.20 | $2,993,244.76 |
North Dakota | 9999500 | Ward | >= 50,000 AND < 200,000 | State | NATL INTRASTRUCTURE INVESTMENT | Construction Engineering | $129,996.62 | $299,324.48 |
North Dakota | 9999500 | Stutsman | >= 5,000 AND < 50,000 | State | NATL INTRASTRUCTURE INVESTMENT | Construction Engineering | $564,582.01 | $1,299,981.61 |
North Dakota | 9999500 | Sheridan | < 5,000 | State | NATL INTRASTRUCTURE INVESTMENT | Construction Engineering | $335,882.69 | $773,388.64 |
North Dakota | 9999500 | LaMoure | < 5,000 | State | NATL INTRASTRUCTURE INVESTMENT | Construction Engineering | $222,587.94 | $512,521.16 |
North Dakota | 9999500 | Mountrail | >= 5,000 AND < 50,000 | State | NATL INTRASTRUCTURE INVESTMENT | Construction Engineering | $71,028.31 | $163,546.66 |
North Dakota | 9999500 | McHenry | >= 5,000 AND < 50,000 | State | NATL INTRASTRUCTURE INVESTMENT | Construction Engineering | $336,376.53 | $774,525.74 |
North Dakota | 9999500 | Wells | < 5,000 | State | NATL INTRASTRUCTURE INVESTMENT | Construction Engineering | $214,974.75 | $494,991.36 |
North Dakota | 9999500 | Kidder | < 5,000 | State | NATL INTRASTRUCTURE INVESTMENT | Construction Engineering | $212,009.86 | $488,164.54 |
North Dakota | 9999500 | Eddy | < 5,000 | State | NATL INTRASTRUCTURE INVESTMENT | Construction Engineering | $118,632.81 | $273,158.67 |
North Dakota | 9999500 | Stutsman | >= 5,000 AND < 50,000 | State | PROTECT PROGRAM APPORTIONED | Resilience Improvement - Highway Project | $3,288,641.55 | $3,288,641.55 |
North Dakota | 9999500 | Kidder | < 5,000 | State | PROTECT PROGRAM APPORTIONED | Resilience Improvement - Highway Project | $886,880.99 | $886,880.99 |
North Dakota | 9999500 | Kidder | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | $199,548.22 | $221,720.25 |
North Dakota | 9999500 | Stutsman | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | $739,944.35 | $822,160.39 |
North Dakota | 9999509 | Statewide | N/A | State | HIGHWAY INFRA PRGM -APPOR | Bridge Replacement - Added Capacity | $7,075,335.60 | $8,742,537.50 |
North Dakota | 9999509 | Statewide | N/A | State | HIGHWAY INFRA PRGM -APPOR | Construction Engineering | $707,533.56 | $874,253.75 |
North Dakota | 9999509 | Sioux | < 5,000 | State | HSIP LIMITING FLEXIBLE | Construction Engineering | $216,036.70 | $216,036.70 |
North Dakota | 9999509 | Sioux | < 5,000 | State | HSIP LIMITING FLEXIBLE | Safety | $2,160,367.04 | $2,160,367.04 |
North Dakota | 9999509 | McKenzie | >= 5,000 AND < 50,000 | State | NATL INTRASTRUCTURE INVESTMENT | 4R - No Added Capacity | $13,616,379.93 | $27,232,759.86 |
North Dakota | 9999509 | McKenzie | >= 5,000 AND < 50,000 | State | NATL INTRASTRUCTURE INVESTMENT | Construction Engineering | $136,124.08 | $272,248.15 |
North Dakota | 9999509 | Mountrail | >= 5,000 AND < 50,000 | State | NATL INTRASTRUCTURE INVESTMENT | Construction Engineering | $398,750.48 | $797,500.95 |
North Dakota | 9999509 | Mountrail | >= 5,000 AND < 50,000 | State | NATL INTRASTRUCTURE INVESTMENT | Safety | $3,987,504.76 | $7,975,009.50 |
North Dakota | 9999509 | McKenzie | >= 5,000 AND < 50,000 | State | NATL INTRASTRUCTURE INVESTMENT | Safety | $1,361,240.75 | $2,722,481.50 |
North Dakota | 9999509 | McKenzie | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $1,152,202.55 | $1,423,702.64 |
North Dakota | 9999509 | McKenzie | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,319,167.51 | $2,865,646.25 |
North Dakota | 9999509 | McKenzie | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $8,093.00 | $10,000.00 |
North Dakota | 9999509 | McKenzie | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $57,642.39 | $71,225.00 |
North Dakota | SB97001 | Statewide | N/A | N/A | ST INFR BANK PILOT - ADV CAP | Other | $23,968,184.00 | |
North Dakota | SB97001 | Statewide | N/A | N/A | STATE INFRASTRUCTURE BANK - GF | Other | $2,540,000.00 | $3,138,516.00 |