| RECIPIENT | PROJECT NUMBER |
PROJECT TITLE | TOTAL OBLIGATIONS |
ESTIMATED TOTAL COST |
|---|---|---|---|---|
| Pennsylvania | P3MB002 | Major Bridge P3 Package 1 | $91,185,000.00 | $107,720,024.00 |
| Pennsylvania | T012579 | I-90: MP 3.5 to 7 Reconstruct - #1 | $76,536,110.00 | $76,536,110.00 |
| Pennsylvania | T014471 | I-80: MM0 to MM5 Reconstruct | $124,363,583.00 | $124,363,583.00 |
| Pennsylvania | T022393 | I-80 Preservation MM 96 to MM 119 | $57,195,730.00 | $57,195,730.00 |
| Pennsylvania | T032472 | SR 220: PA 287 to West Fourth Street | $39,810,393.00 | $39,810,393.00 |
| Pennsylvania | T033171 | I-80 from Northumberland County Line to SR 54 | $58,843,980.00 | $58,843,980.00 |
| Pennsylvania | T035176 | CSVT Southern Section Earthwork | $91,500,000.00 | $91,500,000.00 |
| Pennsylvania | T042584 | I-84 ov LackRR/Roaring & 435 | $126,565,000.00 | $126,565,000.00 |
| Pennsylvania | T042630 | I-81 Mill/Fill Dickson City to Susq County Line | $55,984,792.00 | $55,984,792.00 |
| Pennsylvania | T043697 | I-81 Dorrance Bridges | $29,788,275.00 | $29,788,275.00 |
| Pennsylvania | T043703 | SR 115 over I-81 | $53,201,971.00 | $66,998,500.00 |
| Pennsylvania | T044239 | I-84 E&W I-4R Wayne - E26 | $114,222,000.00 | $114,222,000.00 |
| Pennsylvania | T044249 | I-84 E&W I-4R MP 40 - E46 | $95,258,000.00 | $95,258,000.00 |
| Pennsylvania | T044253 | I-84 E&W I-4R E26 to E34 | $120,459,168.00 | $120,459,168.00 |
| Pennsylvania | T051461 | Interstate 78 (12M) | $191,645,877.00 | $191,645,877.00 |
| Pennsylvania | T051489 | I-78-Rt 61 Bridge Replace | $150,775,021.00 | $150,775,021.00 |
| Pennsylvania | T053405 | I-78 - Lehigh St to 309 South Interchange | $41,889,215.00 | $41,889,215.00 |
| Pennsylvania | T054306 | I-80/Exit 308 Realignment | $114,700,516.00 | $114,700,516.00 |
| Pennsylvania | T061158 | I-95, Pennsylvania Turnpike Interchange D10 | $99,995,111.00 | $99,995,111.00 |
| Pennsylvania | T061166 | I-95, Section D20 | $86,800,000.00 | $86,800,000.00 |
| Pennsylvania | T063183 | Wanamaker Ave o/ Darby Ck | $39,389,528.00 | $39,389,528.00 |
| Pennsylvania | T063196 | Gov Printz Blvd o/Conrail | $20,843,000.00 | $29,119,998.00 |
| Pennsylvania | T063199 | US 322 over CSX & Bethel Rd | $10,767,000.00 | $67,364,450.00 |
| Pennsylvania | T064209 | RTMC General Contract | $40,765,476.79 | $40,765,476.79 |
| Pennsylvania | T064227 | US202:Johnson-Swede #4 | $54,239,000.00 | $54,239,000.00 |
| Pennsylvania | T064263 | Ridge/Germantwn Intrs Re-Alignmnt | $27,350,788.00 | $27,350,788.00 |
| Pennsylvania | T065169 | I-95N:Columbia-AnnSt N(C) | $250,483,797.63 | $250,483,797.63 |
| Pennsylvania | T065185 | I-95 Betsy Ross Bridge and Aramingo Avenue Interchange | $157,710,762.78 | $157,710,762.78 |
| Pennsylvania | T065188 | S.R. 0676, Vine Street Expressway Sections PAB and PAA | $72,436,199.00 | $72,436,199.00 |
| Pennsylvania | T065203 | I-95 Betsy Ross Ramps and Adams Ave. Connector City of Philadelphia | $56,230,046.25 | $56,230,046.25 |
| Pennsylvania | T065216 | I-95S: Columbia-Ann St N | $359,329,815.00 | $359,329,815.00 |
| Pennsylvania | T065232 | I-95: Kennedy-Levick | $86,702,546.00 | $86,702,546.00 |
| Pennsylvania | T065235 | I-95: Betsy Ross Rmps A&B | $103,000,000.00 | $103,000,000.00 |
| Pennsylvania | T065253 | I-95: Allegheny & Castor Ave Intr Connection | $32,000,000.00 | $32,000,000.00 |
| Pennsylvania | T065259 | I-95 Corridor ITS | $32,293,082.00 | $32,293,082.00 |
| Pennsylvania | T065268 | I-95: Cottman On-Ramp | $58,924,440.00 | $58,924,440.00 |
| Pennsylvania | T065273 | I-95: Margaret-Carver | $335,599,762.00 | $335,599,762.00 |
| Pennsylvania | T065278 | Penn's Landing Project Development | $370,341,471.00 | $418,472,878.00 |
| Pennsylvania | T065279 | I-76: Rte 1- I 676 Paving/Guiderail | $40,517,740.00 | $40,517,740.00 |
| Pennsylvania | T065307 | I-95: Betsy Ross Mainln NB | $143,951,625.00 | $386,265,000.00 |
| Pennsylvania | T082203 | Am Leg Mem Hwy Resurface | $29,548,188.00 | $29,548,188.00 |
| Pennsylvania | T084200 | Mount Rose Avenue and I-83 Interchange (Exit 18) | $69,318,041.00 | $69,318,041.00 |
| Pennsylvania | T084431 | I-83 Exit 4 | $33,634,716.78 | $33,634,716.78 |
| Pennsylvania | T085179 | I-83 East Shore Section 1 | $117,798,293.52 | $117,798,293.52 |
| Pennsylvania | T085211 | US 322 & Chambers Hill Rd | $41,481,151.00 | $41,481,151.00 |
| Pennsylvania | T085229 | I-83 East Shore Section 3 | $150,924,379.00 | $150,924,379.00 |
| Pennsylvania | T085249 | I-83 East Shore Section 3B | $158,579,040.00 | $158,579,040.00 |
| Pennsylvania | T087258 | Centerville Rd Interchang | $25,891,200.00 | $25,891,200.00 |
| Pennsylvania | T087283 | US 222 /US 30 Interchange Improvements | $80,180,106.00 | $80,180,106.00 |
| Pennsylvania | T089132 | US 22/322 Resurfacing | $26,733,924.00 | $26,733,924.00 |
| Pennsylvania | T091051 | Breezewood-Fulton Co Line | $25,782,372.00 | $25,782,372.00 |
| Pennsylvania | T092122 | I-99 Newry Pulloff to Plank Rd Intchg | $28,355,950.00 | $28,355,950.00 |
| Pennsylvania | T094029 | I-70 EB Amaranth to Bdfrd | $32,498,386.80 | $32,498,386.80 |
| Pennsylvania | T101310 | Margaret Rd Intersection | $28,649,805.00 | $28,649,805.00 |
| Pennsylvania | T101330 | Graff Bridge Preservation | $34,635,419.00 | $50,293,832.00 |
| Pennsylvania | T111019 | I-79 at PA 910 Interchange | $35,696,501.00 | $36,558,000.00 |
| Pennsylvania | T111025 | McKeesport Duquesne Bridge | $27,850,000.00 | $59,706,000.00 |
| Pennsylvania | T111026 | I-376, Edgewood to Churchill | $99,780,410.00 | |
| Pennsylvania | T111143 | Neville Island Bridge | $48,676,092.00 | $48,676,092.00 |
| Pennsylvania | T111155 | PA 28/Highland Park Br Interchange | $60,250,605.00 | $60,250,605.00 |
| Pennsylvania | T111165 | I-79, Neville Island to I-279 | $33,733,641.00 | $33,733,641.00 |
| Pennsylvania | T111172 | Boulevard of Allies Ramps | $40,757,102.00 | $40,757,102.00 |
| Pennsylvania | T111181 | Forbes Avenue ov Fern Hollow | $25,000,000.00 | $25,000,000.00 |
| Pennsylvania | T111189 | I-79, Moon Run - Neville Island | $49,464,647.00 | $49,464,647.00 |
| Pennsylvania | T111197 | New Kensington Bridge | $28,301,000.00 | $28,301,000.00 |
| Pennsylvania | T111216 | SR 4003 - East Street to Babcock Blvd | $31,469,000.00 | $31,469,000.00 |
| Pennsylvania | T111222 | I-376, Churchill to Monroeville | $84,465,961.00 | $84,465,961.00 |
| Pennsylvania | T111224 | Charles Anderson Bridge | $55,459,632.00 | $55,459,632.00 |
| Pennsylvania | T111225 | I-376, Commercial Street Bridge | $107,097,522.00 | $107,097,522.00 |
| Pennsylvania | T112000 | Frankfort Road Bridge | $30,014,167.00 | $33,636,167.00 |
| Pennsylvania | T112280 | Koppel Bridge carrying PA 351 over the Beaver River | $32,123,075.93 | $32,123,075.93 |
| Pennsylvania | T112311 | Freedom Rd Upgrade - Ph C | $31,739,113.00 | $31,739,113.00 |
| Pennsylvania | T124262 | Western section (MPMS 73514) - Interstate 70 from SR 136 (Beau Street) to I-79 South Junction Eastern section (MPMS 75950) - Interstate 70 from I-79 | $131,448,119.00 | $131,448,119.00 |
| Pennsylvania | T125305 | I-70 Arnold City Interch | $101,533,252.00 | $101,708,252.00 |
| Pennsylvania | T125320 | LVTIP: PA 819 to Norvelt (PA 981-Q20) | $60,836,955.00 | $60,836,955.00 |
| Pennsylvania | T125337 | New Stanton Intrchng | $54,890,958.04 | $54,890,958.04 |
| Pennsylvania | T125349 | Yukon & Madison Interchanges | $98,045,884.76 | $98,045,884.76 |
| Pennsylvania | T125374 | I-70 @ PA 51 Interchange | $145,000,000.20 | $145,000,000.20 |
| Pennsylvania | T125391 | Salina Bridge | $35,420,000.00 | $35,420,000.00 |
| Pennsylvania | T125400 | LVTIP: Pleasant Unity to Airport | $57,526,882.00 | $57,526,882.00 |
| Pennsylvania | U021001 | PA 26/I-80 Interchange | $35,110,410.00 | $58,517,351.00 |
| Pennsylvania | U035183 | CSVT Structures South Sec | $69,000,000.00 | $122,400,000.00 |
| Pennsylvania | U056001 | St.Clair to Frackville Reconstruction | $21,012,220.00 | $26,265,275.00 |
| Pennsylvania | U102102 | Freedom Rd (Beaver Co. to Haine School Rd) and Three Degree Road Intersection | $25,000,000.00 | $29,763,542.00 |
| Pennsylvania | X012626 | Central Bayfront Parkway Multimodal | $49,360,267.00 | $70,829,273.00 |
| Pennsylvania | X021461 | EXIT 161 Bellefonte Interchange | $101,250,000.00 | $125,000,000.00 |
| Pennsylvania | X021462 | EXIT 161 Bellefonte Interchange | $105,082,270.00 | $131,352,838.00 |
| Pennsylvania | X033178 | SR 54 Corridor Safety Improvement | $20,192,295.00 | $27,223,515.00 |
| Pennsylvania | X035175 | CSVT Southern Section Earthwork | $35,000,000.00 | $35,000,000.00 |
| Pennsylvania | X042622 | SR 6 (Robert P. Casey Highway) to SR 6006 | $28,360,350.00 | $35,450,439.00 |
| Pennsylvania | X042655 | SR 435 over Lackawanna County Railroad Authority | $20,401,398.00 | $30,924,648.00 |
| Pennsylvania | X043547 | South Valley Parkway | $23,173,159.06 | $29,015,578.41 |
| Pennsylvania | X043644 | Extension of SR 424 to SR 924 | $21,044,000.00 | $26,305,000.31 |
| Pennsylvania | X044217 | Interstate 84 from Milford to New York State Line Pike County | $61,448,785.62 | $68,276,959.57 |
| Pennsylvania | X045341 | I-81 Mill/Fill Lackawanna Line to New Milford | $34,403,121.00 | $38,225,691.00 |
| Pennsylvania | X053385 | Cementon Bridge | $20,661,343.00 | $25,826,680.00 |
| Pennsylvania | X053419 | 309 & Tilghman I/C Recon | $74,153,824.00 | $88,608,938.00 |
| Pennsylvania | X055319 | PA 33 Bushkill Creek Bridges | $22,706,216.00 | $28,382,769.00 |
| Pennsylvania | X056292 | St.Clair to Frackville Reconstruction | $40,895,755.00 | $51,698,997.00 |
| Pennsylvania | X056293 | St.Clair to Frackville Reconstruction | $30,853,180.00 | $38,566,475.00 |
| Pennsylvania | X061258 | Route 1 Improvement-South | $81,732,211.00 | $102,165,267.00 |
| Pennsylvania | X061264 | PA309:Sellersville Bypass(Parent) | $51,914,086.00 | $64,892,610.00 |
| Pennsylvania | X061268 | Route 1 Improvement-North | $100,996,256.00 | $126,245,324.00 |
| Pennsylvania | X062226 | State Route 422 Reconstruction | $66,103,829.31 | $82,629,788.31 |
| Pennsylvania | X063233 | US 322: from US Route 1 in Concord Township to east of Mattson Road/Featherbed Lane near Clayton Park and the Bethel Township line. Bridges include | $56,262,939.24 | $70,328,676.24 |
| Pennsylvania | X063243 | I95 Delaware Line-Phila NB(Parent) | $48,580,597.00 | $53,978,442.00 |
| Pennsylvania | X063244 | I-95 Delaware Line-Phila SB | $27,593,729.00 | $30,659,699.00 |
| Pennsylvania | X063258 | I-476: I-76 Interchange to I-95 | $63,103,090.00 | $70,053,447.40 |
| Pennsylvania | X063259 | US 322: Chelsea Parkway - Market St Int | $44,741,035.00 | $108,929,933.00 |
| Pennsylvania | X064314 | US 422 Betzwood Bridge(C) | $87,163,751.09 | $109,513,071.56 |
| Pennsylvania | X064324 | Markley St Improvement Project South | $23,421,659.00 | $29,277,325.00 |
| Pennsylvania | X064346 | US202:Swede-Morris #2 | $44,833,186.00 | $56,041,484.00 |
| Pennsylvania | X064362 | US202:Morris-Swedesfd #3 | $40,315,319.00 | $50,394,151.00 |
| Pennsylvania | X064383 | 309 Cnntr: Allntwn Rd-Souderton Pk | $38,755,289.00 | $48,444,113.00 |
| Pennsylvania | X064390 | US 422: Norfolk Southern - Evergreen Rd | $57,127,210.00 | $92,107,975.00 |
| Pennsylvania | X065293 | Improvements to Cottman Avenue, Torresdale Avenue, Princeton Avenue, State Road and New State Road | $34,136,730.13 | $37,926,700.13 |
| Pennsylvania | X065306 | Arch, Market, Little Market, Chestnut and 30th Streets over Amtrak (Six structures);; City of Philadelphia | $54,822,045.85 | $68,527,556.85 |
| Pennsylvania | X065318 | I-95: Columbia - Ann(C) | $87,369,639.00 | $109,211,678.00 |
| Pennsylvania | X065319 | SR 95 From: Levick Street To: Bleigh Avenue In: The city of Philadelphia | $239,322,643.35 | $265,914,051.35 |
| Pennsylvania | X065373 | Chestnut St over Lower 30th Street, I-76 (Schuylkill Expressway), Schuylkill River, Schuylkill River Trail, CSX and 24th Street;; and Schuylkill Avenu | $96,127,665.00 | $119,864,184.00 |
| Pennsylvania | X065400 | I-95: Allegheny AdvCntrc | $24,403,053.00 | $27,114,506.00 |
| Pennsylvania | X065403 | Rsvlt Blvd o/Wayne Junc | $96,609,619.00 | $116,584,656.00 |
| Pennsylvania | X065414 | I-95 Bridge Repairs | $50,397,674.00 | $55,997,417.00 |
| Pennsylvania | X065450 | Citywide 3R 110 | $30,299,737.00 | $39,937,135.50 |
| Pennsylvania | X065457 | Market St over Schuylkill River, SEPTA & CSX | $42,750,904.00 | $157,355,381.00 |
| Pennsylvania | X065459 | Citywide 3R 111 | $5,460,000.00 | $52,411,252.25 |
| Pennsylvania | X065461 | Girard Point Bridge Rehab - Phases 1 & 2 | $326,758,881.00 | |
| Pennsylvania | X082217 | I-81 Resurfacing Exit 59 to Wade Bridge | $23,303,676.00 | $25,892,972.00 |
| Pennsylvania | X085250 | PA 283 Reconstruction 3 | $74,523,973.86 | $93,154,970.86 |
| Pennsylvania | X099162 | NEVI Corridor Connections | $20,000,000.00 | $25,000,000.00 |
| Pennsylvania | X102390 | Three Degree Rd Intersection | $22,579,368.00 | $28,224,211.00 |
| Pennsylvania | X102414 | Karns Crossing Bridge | $38,463,252.00 | $71,331,332.00 |
| Pennsylvania | X111437 | 9th Street Bridge Rehab | $21,298,807.00 | $26,623,511.00 |
| Pennsylvania | X111612 | 6th Street Bridge Rehab | $31,938,627.00 | $39,923,286.00 |
| Pennsylvania | X111865 | Campbell's Run Road | $14,130,709.90 | $38,293,751.00 |
| Pennsylvania | X121246 | Layton Bridge | $4,000,000.00 | $49,600,161.00 |
| Pennsylvania | X121248 | McClure/Kingview Road Interchange | $48,514,273.00 | $65,019,064.00 |