RECIPIENT PROJECT
NUMBER
PROJECT TITLE TOTAL
OBLIGATIONS
ESTIMATED
TOTAL
COST
Wyoming 0901091 NORTH SHERIDAN INTERCHANGE-I-90, GRADING, DRAINING, MILLING, PLANT MIX, REMOVAL AND REPLACEMENT OF STRUCTURES $46,192,214.36 $49,873,859.50
Wyoming 2000058 PE WY 22, JACKSON - WILSON TETON COUNTY $45,870,749.00 $52,404,253.00
Wyoming 2000062 JACKSON - WILSON / WY 22 $26,540,301.00 $26,813,291.00
Wyoming HPP0418 US 212 / BEARTOOTH HIGHWAY $25,903,000.00 $26,936,679.00
Wyoming I254160 CASPER MARGINAL $38,506,120.37 $43,689,900.19
Wyoming I254161 GLENROCK - CASPER / CASPER MARGINAL / I-25 $36,720,229.29 $39,234,885.65
Wyoming I254168 CASPER-KAYCEE / MIDWEST SECTION / I-25 $24,296,712.57 $27,578,933.06
Wyoming I254169 GLENROCK - CASPER / I-25 CASPER MARGINAL /BRIDGE REPLACEMENT $28,707,076.00 $33,803,645.00
Wyoming I802209 LYMAN-GREEN RIVER / LITTLE AMERICA / I-80 $24,095,475.29 $25,970,609.22
Wyoming I803152 ROCK SPRINGS - RAWLINS / PATRICK DRAW - WEST BOUND LANE $35,170,648.64 $38,209,908.00
Wyoming I803153 ROCK SPRINGS - RAWLINS / PATRICK DRAW / EASTBOUND LANE $27,044,879.80 $29,154,099.63
Wyoming I804271 I-80 WINTER FREIGHT IMPROVEMENT PROJECT $27,838,230.00 $34,819,551.00
Wyoming I901117 RANCHESTER TO SHERIDAN - REHABILITATION / REALIGNMENT PROJECT $34,706,807.40 $39,959,264.00
Wyoming N104066 HOBACK JUNCTION - JACKSON ROAD / SNAKE RIVER SECTION **RECONSTRUCTION / TURNOUT** $82,534,772.77 $90,088,125.03
Wyoming ND32401 ER / WYO22 / BIG FILL SLIDE / DDIR#1 $44,111,119.13 $48,641,097.96
Wyoming WL32304 KEMMERER / US 189 / WILDLIFE CROSSINGS $25,684,832.00 $38,023,100.00