U.S. DEPARTMENT OF TRANSPORTATION FEDERAL HIGHWAY ADMINISTRATION FISCAL MANAGEMENT INFORMATION SYSTEM
Report: FMISF71A-2
Kentucky

SUMMARY PROJECT LEVEL DATA PURSUANT TO 23 U.S.C. 104(g)(3)(B) WITH AN ESTIMATED TOTAL COST OF $25,000,000 OR MORE
AS OF SEPTEMBER 30, 2021
RECIPIENT PROJECT
NUMBER
PROJECT TITLE TOTAL
OBLIGATIONS
ESTIMATED
TOTAL
COST
Kentucky 0011033 GRAVES COUNTY - RECONSTRUCT J.CARROLL PKWY INTERSECTION W/THE MAYFIELD BYPASS-PROVIDE SUPERIOR THROUGH MOVEMENT TO THE PARKWAY. I-69 CORRIDOR IMPR 26,560,985.00 26,560,985.00
Kentucky 0031019 Ohio/Daviess Co; I-65 Spur Corridor 30,994,040.00 30,994,040.00
Kentucky 0061061 Mountain Parkway widening/safety improvements from MP 73.4, 1.1 mi west of Licking River Bridge to MP 75.3 Burning Fork Bridge. 24,372,427.00 26,953,431.00
Kentucky 0061062 WIDEN MOUNTAIN PKWY TO 4 LANES FROM APPROX 0.4 MI E OF KY 3050 OVERPASS (MP71.0) TO 1.1 MI W OF BRIDGE OVER LICKING RIVER (MP73.4) 35,160,192.50 35,160,192.50
Kentucky 0061064 Magoffin- TIGER Mountain Parkway 30,245,953.00 36,345,953.00
Kentucky 0061072 WOLFE, MORGAN, MAGOFFIN - KY 9009-RECONSTRUCT TO WIDEN THE MOUNTAIN PARKWAY TO 4 LANES 96,306,579.90 96,306,579.90
Kentucky 0061076 Magoffin Co. | Mountain Parkway Corridor 69,307,938.40 69,307,938.40
Kentucky 0151004 KY 15 HAZARD BY-PASS, GRADE,DRAIN&INCIDENTAL SURFACE 0.00 27,234,636.00
Kentucky 0151078 Perry County - KY 15 RECONSTRUCTION 57,537,800.00 57,537,800.00
Kentucky 0151086 PERRY CO., KY 15 - IMPROVE SAFETY, UPGRADE GEOMETRICS, AND ADDRESS CAPACITY ISSUES 48,205,200.00 48,205,200.00
Kentucky 0241090 Reconstruct I-24/Purchase Parkway Interchange (I-69 Corridor Improvement). 42,648,486.00 42,648,486.00
Kentucky 0242075 Lyon-Caldwell-Trigg | I-24 Resurfacing & Rehab 31,648,650.00 31,648,650.00
Kentucky 0272109 Campbell - US 27 from 0.8 mile south of KY 154 to 0.300 mile south of KY 824 - Grade, drain & surface to provide a 4-lane facility 28,065,164.83 28,065,164.83
Kentucky 0302025 Owsley-Jackson | KY 30 Reconstruction 66,462,915.10 66,462,915.10
Kentucky 0302026 Lee-Owsley Co. | KY 11 Reconstruction 21,164,000.00 26,455,000.00
Kentucky 0311034 Jefferson- Dixie Highway TIGER project 24,690,000.00 37,921,970.50
Kentucky 0411026 Christian & Hopkins Cos. | Remove & Replace concrete pavement on Pennyrile Pkwy 55,264,110.00 55,264,110.00
Kentucky 0601159 Construct main river superstructure, approach spans & approache roadway to replace the Tennessee River bridge on US60 E of Paducah 80,180,965.84 80,180,965.84
Kentucky 0601196 Livingston Co. | US 60 over Cumberland River Bridge Replacement 56,342,464.00 70,340,580.00
Kentucky 0643058 Franklin Co. | I-64 Bridges 10,000,000.00 33,268,950.00
Kentucky 0649009 Jefferson Co. | I-64 Sherman Minton Bridge Maintence 41,261,866.00 85,285,441.00
Kentucky 0654048 Widen I-65 to 6 lanes from 0.6 mi north of Old Sonora Road to the Western Kentucky Parkway. 75,446,855.00 75,446,855.00
Kentucky 0655120 Bullitt Co- Construct new I-65 interchange 27,707,722.20 27,707,722.20
Kentucky 0659023 Louisville/Southern Indiana Ohio River Br "Downtown Crossing" general project mgmt/oversight including construction eng inspection 85,060,407.86 85,060,407.86
Kentucky 0659025 Jefferson - Construct the Downtown Ohio River Crossing & associated roadway approaches in Louisville & Jeffersonville, Indiana "Design-Build". 187,131,662.00 309,155,689.10
Kentucky 0752059 Laurel Co. | I-75 Widening 81,442,056.71 82,255,095.15
Kentucky 0752095 ROCKCASTLE CO., I-75 - WIDEN I-75 TO 6 LANES 45,425,091.09 45,920,900.00
Kentucky 0752098 ROCKCASTLE CO., I-75 - WIDEN I-75 TO 6 LANES 44,413,600.00 44,413,600.00
Kentucky 0752100 Laurel Co; widen I-75 to 6 lanes 58,903,800.00 58,903,800.00
Kentucky 0753092 Rockcastle County I-75 Widening 36,577,240.14 36,653,340.14
Kentucky 0756100 Scott Co. - CONSTRUCT NEW I-75 INTERCHANGE AND APPROACH ROADWAY FROM CHAMPION WAY TO CHERRY BLOSSOM WAY IN GEORGETOWN. 30,868,567.00 30,868,567.00
Kentucky 0757144 Boone Co. | I-71/75 INFRA Project 146,598,062.39 193,585,628.00
Kentucky 0758107 Kenton Co. | Brent Spence Bridge Maintenance 18,000,000.00 39,437,530.00
Kentucky 0801098 Trigg | Marshall - Construct a bridge and approaches on US 68/KY 80 over Kentucky Lake. 62,835,944.87 194,111,589.46
Kentucky 0801101 Trigg - Construct a bridge and approaches on US 68/KY 80 over Lake Barkley. 80,232,736.43 200,263,582.00
Kentucky 0801104 Trigg County - Aurora-Cadiz Road: Reconstruct (US 68) 31,328,123.00 31,328,123.00
Kentucky 0806044 Pike Co., US 460 - Construct twin bridges on relocated US 460 at Pond Creek. 19,057,522.95 29,624,550.00
Kentucky 0806047 Pike County | US 460 40,217,891.30 78,687,600.00
Kentucky 1271120 RUSSELL CO, US 127 - RELOCATE US 127 FROM THE NORTH BANK OF THE CUMBERLAND RIVER TO THE JAMESTOWN BYPASS. 35,549,477.80 35,549,477.80
Kentucky 2653043 Jefferson & Oldham Cos. | I-MOVE KY Design-Build 90,928,914.42 189,000,000.00
Kentucky 2681033 FAYETTE CO., KY 4 - WIDEN NEW CIRCLE ROAD 46,019,590.00 46,019,590.00
Kentucky 2759135 Boone Co. | I-275/Graves Rd XCHNG | Design-Build 74,760,935.00 75,300,935.00
Kentucky 2759136 Kenton Co; address pavement condition on pcc pavement on I-275 34,471,030.00 34,471,030.00
Kentucky 3020007 Henderson - I-69 Bridge over Ohio River 53,820,000.00 254,720,000.00
Kentucky 4611009 Pulaski Co | KY 461 | BUILD Grant 57,928,400.00 66,910,500.00
Kentucky 4714034 +-Pavement Reconstruction on I-471 from MP 0.0 (US27) to MP 5.72 (Ohio State Line) 53,570,178.60 53,570,178.60
Kentucky 5053031 Henderson Co.- US 60 Bridge over Green River 35,687,527.40 35,687,527.40
Kentucky 5129016 MERCER, GARRARD COS. KY 152 - REPLACE BRIDGE AND APPROACHES 36,157,719.51 36,157,719.51
Kentucky 5225005 Boone Co. - KY 536-reconstruct to a 5-lane urban section 29,121,600.00 29,216,400.00
Kentucky 6000167 Bridging KY Design-Build No.1 35,416,077.10 106,291,750.01
Kentucky 6411039 Calloway Co. BUILD | Improvements along US 641 28,940,000.00 57,696,965.00
Kentucky 8200014 Boone: Reconstruct & widen KY237 from Rogers Ln to KY18 - Grade, drain & surface 24,928,420.00 25,088,420.00