RECIPIENT | PROJECT NUMBER |
PROJECT TITLE | TOTAL OBLIGATIONS |
ESTIMATED TOTAL COST |
---|---|---|---|---|
Kentucky | 0011033 | GRAVES COUNTY - RECONSTRUCT J.CARROLL PKWY INTERSECTION W/THE MAYFIELD BYPASS-PROVIDE SUPERIOR THROUGH MOVEMENT TO THE PARKWAY. I-69 CORRIDOR IMPR | 26,560,985.00 | 26,560,985.00 |
Kentucky | 0031019 | Ohio/Daviess Co; I-65 Spur Corridor | 30,994,040.00 | 30,994,040.00 |
Kentucky | 0061061 | Mountain Parkway widening/safety improvements from MP 73.4, 1.1 mi west of Licking River Bridge to MP 75.3 Burning Fork Bridge. | 24,372,427.00 | 26,953,431.00 |
Kentucky | 0061062 | WIDEN MOUNTAIN PKWY TO 4 LANES FROM APPROX 0.4 MI E OF KY 3050 OVERPASS (MP71.0) TO 1.1 MI W OF BRIDGE OVER LICKING RIVER (MP73.4) | 35,160,192.50 | 35,160,192.50 |
Kentucky | 0061064 | Magoffin- TIGER Mountain Parkway | 30,245,953.00 | 36,345,953.00 |
Kentucky | 0061072 | WOLFE, MORGAN, MAGOFFIN - KY 9009-RECONSTRUCT TO WIDEN THE MOUNTAIN PARKWAY TO 4 LANES | 96,306,579.90 | 96,306,579.90 |
Kentucky | 0061076 | Magoffin Co. | Mountain Parkway Corridor | 69,307,938.40 | 69,307,938.40 |
Kentucky | 0151004 | KY 15 HAZARD BY-PASS, GRADE,DRAIN&INCIDENTAL SURFACE | 0.00 | 27,234,636.00 |
Kentucky | 0151078 | Perry County - KY 15 RECONSTRUCTION | 57,537,800.00 | 57,537,800.00 |
Kentucky | 0151086 | PERRY CO., KY 15 - IMPROVE SAFETY, UPGRADE GEOMETRICS, AND ADDRESS CAPACITY ISSUES | 48,205,200.00 | 48,205,200.00 |
Kentucky | 0241090 | Reconstruct I-24/Purchase Parkway Interchange (I-69 Corridor Improvement). | 42,648,486.00 | 42,648,486.00 |
Kentucky | 0242075 | Lyon-Caldwell-Trigg | I-24 Resurfacing & Rehab | 31,648,650.00 | 31,648,650.00 |
Kentucky | 0272109 | Campbell - US 27 from 0.8 mile south of KY 154 to 0.300 mile south of KY 824 - Grade, drain & surface to provide a 4-lane facility | 28,065,164.83 | 28,065,164.83 |
Kentucky | 0302025 | Owsley-Jackson | KY 30 Reconstruction | 66,462,915.10 | 66,462,915.10 |
Kentucky | 0302026 | Lee-Owsley Co. | KY 11 Reconstruction | 21,164,000.00 | 26,455,000.00 |
Kentucky | 0311034 | Jefferson- Dixie Highway TIGER project | 24,690,000.00 | 37,921,970.50 |
Kentucky | 0411026 | Christian & Hopkins Cos. | Remove & Replace concrete pavement on Pennyrile Pkwy | 55,264,110.00 | 55,264,110.00 |
Kentucky | 0601159 | Construct main river superstructure, approach spans & approache roadway to replace the Tennessee River bridge on US60 E of Paducah | 80,180,965.84 | 80,180,965.84 |
Kentucky | 0601196 | Livingston Co. | US 60 over Cumberland River Bridge Replacement | 56,342,464.00 | 70,340,580.00 |
Kentucky | 0643058 | Franklin Co. | I-64 Bridges | 10,000,000.00 | 33,268,950.00 |
Kentucky | 0649009 | Jefferson Co. | I-64 Sherman Minton Bridge Maintence | 41,261,866.00 | 85,285,441.00 |
Kentucky | 0654048 | Widen I-65 to 6 lanes from 0.6 mi north of Old Sonora Road to the Western Kentucky Parkway. | 75,446,855.00 | 75,446,855.00 |
Kentucky | 0655120 | Bullitt Co- Construct new I-65 interchange | 27,707,722.20 | 27,707,722.20 |
Kentucky | 0659023 | Louisville/Southern Indiana Ohio River Br "Downtown Crossing" general project mgmt/oversight including construction eng inspection | 85,060,407.86 | 85,060,407.86 |
Kentucky | 0659025 | Jefferson - Construct the Downtown Ohio River Crossing & associated roadway approaches in Louisville & Jeffersonville, Indiana "Design-Build". | 187,131,662.00 | 309,155,689.10 |
Kentucky | 0752059 | Laurel Co. | I-75 Widening | 81,442,056.71 | 82,255,095.15 |
Kentucky | 0752095 | ROCKCASTLE CO., I-75 - WIDEN I-75 TO 6 LANES | 45,425,091.09 | 45,920,900.00 |
Kentucky | 0752098 | ROCKCASTLE CO., I-75 - WIDEN I-75 TO 6 LANES | 44,413,600.00 | 44,413,600.00 |
Kentucky | 0752100 | Laurel Co; widen I-75 to 6 lanes | 58,903,800.00 | 58,903,800.00 |
Kentucky | 0753092 | Rockcastle County I-75 Widening | 36,577,240.14 | 36,653,340.14 |
Kentucky | 0756100 | Scott Co. - CONSTRUCT NEW I-75 INTERCHANGE AND APPROACH ROADWAY FROM CHAMPION WAY TO CHERRY BLOSSOM WAY IN GEORGETOWN. | 30,868,567.00 | 30,868,567.00 |
Kentucky | 0757144 | Boone Co. | I-71/75 INFRA Project | 146,598,062.39 | 193,585,628.00 |
Kentucky | 0758107 | Kenton Co. | Brent Spence Bridge Maintenance | 18,000,000.00 | 39,437,530.00 |
Kentucky | 0801098 | Trigg | Marshall - Construct a bridge and approaches on US 68/KY 80 over Kentucky Lake. | 62,835,944.87 | 194,111,589.46 |
Kentucky | 0801101 | Trigg - Construct a bridge and approaches on US 68/KY 80 over Lake Barkley. | 80,232,736.43 | 200,263,582.00 |
Kentucky | 0801104 | Trigg County - Aurora-Cadiz Road: Reconstruct (US 68) | 31,328,123.00 | 31,328,123.00 |
Kentucky | 0806044 | Pike Co., US 460 - Construct twin bridges on relocated US 460 at Pond Creek. | 19,057,522.95 | 29,624,550.00 |
Kentucky | 0806047 | Pike County | US 460 | 40,217,891.30 | 78,687,600.00 |
Kentucky | 1271120 | RUSSELL CO, US 127 - RELOCATE US 127 FROM THE NORTH BANK OF THE CUMBERLAND RIVER TO THE JAMESTOWN BYPASS. | 35,549,477.80 | 35,549,477.80 |
Kentucky | 2653043 | Jefferson & Oldham Cos. | I-MOVE KY Design-Build | 90,928,914.42 | 189,000,000.00 |
Kentucky | 2681033 | FAYETTE CO., KY 4 - WIDEN NEW CIRCLE ROAD | 46,019,590.00 | 46,019,590.00 |
Kentucky | 2759135 | Boone Co. | I-275/Graves Rd XCHNG | Design-Build | 74,760,935.00 | 75,300,935.00 |
Kentucky | 2759136 | Kenton Co; address pavement condition on pcc pavement on I-275 | 34,471,030.00 | 34,471,030.00 |
Kentucky | 3020007 | Henderson - I-69 Bridge over Ohio River | 53,820,000.00 | 254,720,000.00 |
Kentucky | 4611009 | Pulaski Co | KY 461 | BUILD Grant | 57,928,400.00 | 66,910,500.00 |
Kentucky | 4714034 | +-Pavement Reconstruction on I-471 from MP 0.0 (US27) to MP 5.72 (Ohio State Line) | 53,570,178.60 | 53,570,178.60 |
Kentucky | 5053031 | Henderson Co.- US 60 Bridge over Green River | 35,687,527.40 | 35,687,527.40 |
Kentucky | 5129016 | MERCER, GARRARD COS. KY 152 - REPLACE BRIDGE AND APPROACHES | 36,157,719.51 | 36,157,719.51 |
Kentucky | 5225005 | Boone Co. - KY 536-reconstruct to a 5-lane urban section | 29,121,600.00 | 29,216,400.00 |
Kentucky | 6000167 | Bridging KY Design-Build No.1 | 35,416,077.10 | 106,291,750.01 |
Kentucky | 6411039 | Calloway Co. BUILD | Improvements along US 641 | 28,940,000.00 | 57,696,965.00 |
Kentucky | 8200014 | Boone: Reconstruct & widen KY237 from Rogers Ln to KY18 - Grade, drain & surface | 24,928,420.00 | 25,088,420.00 |