RECIPIENT | PROJECT NUMBER |
PROJECT TITLE | TOTAL OBLIGATIONS |
ESTIMATED TOTAL COST |
---|---|---|---|---|
Massachusetts | 001S977 | BOSTON- BRIDGE REHABILITATION, B-16-029, ROUTE 99 (ALFORD STREET) OVER MYSTIC RIVER | 48,952,697.40 | 61,291,671.75 |
Massachusetts | 002S318 | SHREWSBURY- WORCESTER- BRIDGE REHABILITATION, S-14-001=W-44-018, STATE ROUTE 9 (BELMONT STREET) OVER LAKE QUINSIGAMOND (AKA - KENNETH F. BURNS BRIDGE | 35,831,034.01 | 116,121,177.17 |
Massachusetts | 002S372 | QUINCY- WEYMOUTH- BRIDGE REPLACEMENT, Q-01-001=W-32-001, STATE ROUTE 3A (WASHINGTON STREET) OVER THE FORE RIVER | 83,788,152.59 | 290,959,615.98 |
Massachusetts | 002S386 | BOSTON- CAMBRIDGE- BRIDGE REHABILITATION, B-16-009=C-01-002, CAMBRIDGE STREET OVER THE CHARLES RIVER (MEMORIAL DRIVE & STORROW DRIVE) (AKA - LONGFEL | 94,397,915.48 | 337,781,419.67 |
Massachusetts | 002S421 | AMESBURY- NEWBURYPORT- SALISBURY- BRIDGE REPLACEMENT ON ROUTE I-95, A- 07-016=N-11-007, OVER MERRIMACK RIVER (WHITTIER BRIDGE) & A-07-017 OVER EVANS P | 88,347,722.60 | 345,599,248.01 |
Massachusetts | 002S425 | FALL RIVER- INTERCHANGE IMPROVEMENTS AT ROUTE I-195/ROUTE 79/ROUTE 138 INCLUDING BRAGA BRIDGE PHASE 2 CLEANING/PAINTING AND STRUCTURAL REPAIRS | 121,715,284.60 | 278,751,904.97 |
Massachusetts | 002S462 | OAK BLUFFS- TISBURY- BRIDGE REPLACEMENT, O-01-001=T-04-001, BEACH ROAD OVER LAGOON POND DRAWBRIDGE | 36,606,220.80 | 45,675,136.00 |
Massachusetts | 002S748 | BEVERLY- RECONSTRUCTION & SIGNAL IMPROVEMENTS ON ROUTE 1A (RANTOUL STREET & CABOT STREET), FROM CABOT STREET (SOUTH) TO 440 FEET NORTH OF BLAINE AVEN | 21,269,055.13 | 27,512,019.28 |
Massachusetts | 002S760 | EVERETT- MEDFORD- BRIDGE REPLACEMENTS, REVERE BEACH PARKWAY (ROUTE 16), E-12-004=M-12-018 OVER THE MALDEN RIVER (WOODS MEMORIAL BRIDGE) & M- 12-017 OV | 17,816,689.89 | 86,546,471.13 |
Massachusetts | 002S797 | NHPP/CM/STP-002S(797), CANTON- NORWOOD- WESTWOOD- RAMP CONSTRUCTION ON I-95 (NB) & IMPROVEMENTS ON DEDHAM ST/CANTON STREET, | 56,414,890.66 | 69,859,808.53 |
Massachusetts | 002S937 | WEYMOUTH- ABINGTON- RECONSTRUCTION & WIDENING ON ROUTE 18 (MAIN STREET) FROM HIGHLAND PLACE TO ROUTE 139 (4.0 MILES) INC | 67,138,069.70 | 86,957,224.75 |
Massachusetts | 002S969 | BEDFORD- BILLERICA- MIDDLESEX TURNPIKE IMPROVEMENTS, FROM CROSBY DRIVE NORTH TO MANNING ROAD, INCLUDES RECONSTRUCTION OF B-04-006 (PHASE III) | 33,776,618.42 | 43,143,038.53 |
Massachusetts | 002S991 | HANOVER- NORWELL- BRIDGE REPLACEMENT, H-06-010, ST 3 OVER ST 123 (WEBSTER STREET) & N-24-003, ST 3 OVER HIGH STREET | 32,757,346.89 | 41,518,695.79 |
Massachusetts | 0032020 | HADLEY- RECONSTRUCTION ON ROUTE 9, FROM MIDDLE STREET TO MAPLE/SOUTH MAPLE STREET | 7,034,420.80 | 30,051,565.62 |
Massachusetts | 0034007 | EVERETT- RECONSTRUCTION OF FERRY STREET, SOUTH FERRY STREET AND A PORTION OF ELM STREET | 23,626,416.58 | 39,929,034.73 |
Massachusetts | 0035003 | WALPOLE- RECONSTRUCTION ON ROUTE 1A (MAIN STREET), FROM THE NORWOOD T.L. TO ROUTE 27, INCLUDES W-03-024 OVER THE NEPONSET RIVER | 20,504,631.49 | 26,023,774.36 |
Massachusetts | 0035043 | BARNSTABLE- INTERSECTION IMPROVEMENTS AT IYANOUGH ROAD (ROUTE 28) AND YARMOUTH ROAD | 23,214,527.43 | 31,499,191.33 |
Massachusetts | 0036009 | NEEDHAM- NEWTON- RECONSTRUCTION OF HIGHLAND AVENUE, NEEDHAM STREET & CHARLES RIVER BRIDGE, N-04-002, FROM WEBSTER STREET (NEEDHAM) TO ROUTE 9 (NEWTON | 28,632,126.92 | 34,473,238.80 |
Massachusetts | 0036278 | BOSTON- RECONSTRUCTION OF MELNEA CASS BOULEVARD | 25,410,209.78 | 32,068,747.22 |
Massachusetts | 003S024 | RAYNHAM- BRIDGE REPLACEMENT, R-02-013 (3PA), US 44 (CAPE HIGHWAY) OVER SR 24 | 20,771,026.32 | 26,294,532.90 |
Massachusetts | 003S054 | BOSTON- BRIDGE REPLACEMENT, B-16-016, NORTH WASHINGTON STREET OVER THE BOSTON INNER HARBOR | 131,450,721.06 | 211,876,058.30 |
Massachusetts | 003S070 | AGAWAM- WEST SPRINGFIELD- BRIDGE REPLACEMENT, A-05-002=W-21-014, ROUTE 147 OVER THE WESTFIELD RIVER & INTERSECTION & SIGNAL IMPROVEMENTS @ 3 LOCATION | 21,718,892.61 | 28,384,361.14 |
Massachusetts | 003S103 | DANVERS- BRIDGE REPLACEMENT, D-03-018, ST 128 OVER WATERS RIVER | 20,409,854.68 | 25,852,223.18 |
Massachusetts | 003S113 | HAVERHILL- BRIDGE REPLACEMENT, H-12-039, I-495 (NB & SB) OVER MERRIMACK RIVER | 82,118,927.03 | 107,311,915.85 |
Massachusetts | 003S179 | SOMERVILLE-BRIDGE PRESERVATION,S-17-031,I-93 NB AND SB FROM ROUTE 28 TO TEMPLE STREET | 30,191,202.76 | 38,101,253.46 |
Massachusetts | 003S180 | CHELSEA- ROUTE 1 VIADUCT REHABILITATION (SB/NB) ON C-09-007 & C-09-011 | 167,153,833.83 | 209,325,017.29 |
Massachusetts | 003S201 | NORTHFIELD- BIKE/PED BRIDGE CONSTRUCTION TO REPLACE N-22-002, SCHELL BRIDGE OVER THE CONNECTICUT RIVER | 24,002,744.70 | 30,108,430.88 |
Massachusetts | 003S263 | LYNN- SAUGUS- BRIDGE REPLACEMENT, L-18-016=S-05-008, ROUTE 107 OVER THE SAUGUS RIVER (AKA - BELDEN G. BLY BRIDGE) | 65,886,573.00 | 103,929,811.24 |
Massachusetts | 003S390 | ASHLAND- RECONSTRUCTION ON ROUTE 126 (POND STREET), FROM THE FRAMINGHAM T.L. TO THE HOLLISTON T.L. | 18,744,594.46 | 25,114,574.27 |
Massachusetts | 003S398 | TAUNTON- INTERCHANGE IMPROVEMENTS AT ROUTES 24 & 140, INCLUDING REPLACING T-01-045 AND T-01-046 | 84,602,148.43 | 142,076,039.78 |
Massachusetts | 003S468 | BOSTON- ROADWAY, CEILING, ARCH & WALL RECONSTRUCTION AND OTHER CONTROL SYSTEMS IN SUMNER TUNNEL | 61,622,450.03 | 136,505,450.00 |
Massachusetts | 0911173 | SPRINGFIELD- VIADUCT DECK REPLACEMENT OF S-24-061 ON I-91 (EARLY ACTION) | 145,512,264.00 | 182,871,805.00 |
Massachusetts | 091S001 | NORTHAMPTON– BRIDGE REPLACEMENT, N-19-059, I-91 OVER US ROUTE 5 AND B&MRR, BRIDGE REPLACEMENT, N-19-060, I-91 OVER HOCKANUM ROAD AND IMPROVEMENTS TO I | 37,893,038.68 | 51,847,295.94 |
Massachusetts | 0931524 | MEDFORD- BRIDGE REPLACEMENT ON I-93 CORRIDOR | 40,178,227.67 | 98,127,600.00 |
Massachusetts | 0931528 | METHUEN- INTERCHANGE RECONSTRUCTION ON I-93 AT ROUTE 110/113 ROTARY, INCLUDING REMOVAL OF M-17-017 & M-17-018, REHAB OF M-17-007 & NEW BRIDGE CONSTRU | 57,287,750.10 | 71,901,206.00 |
Massachusetts | 0951108 | ATTLEBORO- BRIDGE REPLACEMENT, A-16-053, I-95 (NB & SB) OVER NORTH AVENUE | 22,035,711.95 | 27,624,439.93 |
Massachusetts | 0952121 | LEXINGTON- BURLINGTON- INTERSTATE MAINTENANCE & RELATED WORK ON I-95 | 27,896,672.38 | 32,609,277.84 |
Massachusetts | 0952122 | NEEDHAM- WELLESLEY- 6 BRIDGE LOCATIONS ON I-95/ROUTE 128: N-04-020, N-04-021, N-04-022, N-04-026, N-04-027, N-04-037 & W-13-023 (ADD-A-LANE CONTRAC V | 158,723,488.01 | 199,812,320.02 |
Massachusetts | 0954001 | DANVERS- TOPSFIELD- BOXFORD- ROWLEY- INTERSTATE MAINTENANCE AND RELATED WORK ON I-95 | 27,460,207.87 | 31,138,837.08 |
Massachusetts | 1906031 | WORCESTER- WEST BOYLSTON- INTERSTATE MAINTENANCE & RELATED WORK ON I- 190, INCLUDING W-44-124, I-190 OVER ROUTE 12 & RAMP B | 20,732,236.89 | 33,342,477.72 |