Rhode Island | 0032018 | Bridge Group 32 - I-95 Cranston and Providence | 18,576,136.55 | 25,257,009.01 |
Rhode Island | 0037012 | Bridge Group 51A - Rt 37 C-2 | 12,763,073.59 | 35,931,572.56 |
Rhode Island | 0138060 | Pell Bridge Ramps Phase 2, Newport | 800,000.00 | 28,989,567.17 |
Rhode Island | 0200005 | Reconstruction of the Washington Bridge #200, East Providence, Providence, GARVEE added Wash Ped Bridge (03/01/2012) Eng:Pavia | 79,296,887.37 | 84,666,401.64 |
Rhode Island | 0250010 | Replacement of the Sakonnet River Bridge No. 250 - GARVEE; Added Fed Hwy funds 09/21/2011 - GARVEE funds exhausted | 158,106,513.65 | 351,493,853.80 |
Rhode Island | 0403016 | Rel Rte 403 - B 1009 added 7/27/05, For Prev Auth. see FMIS W96A, See State Remarks Field for addtl projects - GARVEE PROJECT | 100,649,114.37 | 134,174,770.05 |
Rhode Island | 0550003 | Replacement of Pawtucket Bridge No. 550 (Engineer: Faraj) | 58,596,673.71 | 91,392,744.78 |
Rhode Island | 0578005 | Design Build Services for the Reconstruction of the I-95 Viaduct Northbound, Providence - GARVEE Funds | 7,978,488.29 | 148,575,150.00 |
Rhode Island | 0600005 | Bridge Group 49 - Henderson. South Angell Street to North Broadway Cities of Providence & East Providence | 11,600,000.00 | 68,330,415.81 |
Rhode Island | 0700006 | Design-Build for I-195 West Bound - Washington Bridge Phase 2 - Bridge Group 57TB-10; Providence & East Providence | 2,900,000.00 | 32,830,000.00 |
Rhode Island | 1954055 | IWAY C7 C9 C8 C6A C10,11 Adv. Sig 9/08, Lscp C-A 8/09, C13 7/10, Lscp B 11/11, Dmnd Grnd. 06/12, C14 11/12, C15 02/13 | 335,488,079.93 | 561,915,990.58 |
Rhode Island | 2950002 | Design-Build Services for I-295 Bridges - Contract 2, Cranston - GARVEE FUNDS | 5,925,882.96 | 40,688,508.03 |
Rhode Island | 610X001 | Design Build Services for the Reconstruction of the US Rte 6/Rte 10 Interchange, Providence - GARVEE Funds | 27,878,135.31 | 415,000,000.00 |
Rhode Island | BLDG001 | Pell Bridge Ramps Phase 2, Newport | 20,000,000.00 | 25,000,000.00 |
Rhode Island | BLDG002 | Bridge Group 57TB-10 - Design-Build of the Washington Bridge North - Phase 2 | 25,000,000.00 | 31,125,000.00 |
Rhode Island | FRIP001 | GARVEE, Freight Rail Improvement Project, added AMTRAK Force Account, 6/20/2005 | 33,899,111.95 | 47,017,206.62 |
Rhode Island | INFR001 | I-95 Viaduct Northbound - Providence | 60,355,000.00 | 75,443,750.00 |
Rhode Island | TIGR003 | Bridge Group 51A - Rt 37 C-2 | 20,000,000.00 | 25,000,000.00 |