South Dakota 0014194 Pierre Area ; Replace Structure (Bridge), Intersection Improvements; On the following routes: 014, 014 E, 014 W 39,618,065.98 54,460,392.51
South Dakota 0083074 Winner Area; US83 Reconstruction - South of I-90 35,291,832.13 69,915,883.73
South Dakota 0100104 City of Sioux Falls; New roadway construction of Veterans Parkway Hwy 100 30,137,496.81 49,531,760.38
South Dakota 0901038 County of Meade; Reconstruct With PCCP Surf and Str.s and Exit 44 Interchange; On the following routes: 090 E, 090 W, 090 W1 27,742,634.31 31,245,574.49
South Dakota 0908095 County of McCook; Remove and Replace PCC, Pipe Work, Replace Str and Approach Grading, Deck Overlay, Polymer Chip Seal; On the following route I90E 35,212,670.15 39,254,628.14
South Dakota 0908097 County of McCook; Rural Interstate Reconstruction, Replace Bridge; Structure On the following routes 090W, 090E. 0.00 38,514,780.65
South Dakota 6480004 Pennington County; Reconstruction of Sheridan Lake Road 10,969,076.69 25,059,254.51