RECIPIENT | PROJECT NUMBER |
COUNTY | POPULATION RANGE |
OWNERSHIP | PROGRAM | TYPE OF IMPROVEMENT |
TOTAL OBLIGATIONS |
ESTIMATED TOTAL COST |
---|---|---|---|---|---|---|---|---|
Alaska | 0001578 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 60,632,575.02 | 64,917,103.88 |
Alaska | 0001578 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 5,330,288.61 | 5,706,947.12 |
Alaska | 0001578 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | 6,200,472.25 | 6,638,621.26 |
Alaska | 0001578 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | 2,447,327.27 | 2,620,264.74 |
Alaska | 0001578 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 904,719.00 | 968,649.90 |
Alaska | 0001578 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 10,291,270.69 | 11,018,491.10 |
Alaska | 0001578 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 26,899.33 | 28,800.14 |
Alaska | 0001578 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 2,364.76 | 2,531.86 |
Alaska | 0001578 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 3,055,541.66 | 3,271,457.88 |
Alaska | 0001579 | Anchorage | >= 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | Bridge Replacement - Added Capacity | 33,694,139.32 | 36,075,095.63 |
Alaska | 0001579 | Anchorage | >= 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | Construction Engineering | 5,054,120.98 | 5,411,264.44 |
Alaska | 0001579 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 2,079,471.06 | 3,015,685.47 |
Alaska | 0001579 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 23,576,362.77 | 34,190,855.56 |
Alaska | 0001579 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | 0.00 | 21,422,517.93 |
Alaska | 0001579 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 86,304.46 | 184,806.11 |
Alaska | 0001579 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 978,491.78 | 5,788,629.31 |
Alaska | 0001579 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Traffic Management/Engineering - HOV | 20,776.34 | 32,857.30 |
Alaska | 0001579 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Traffic Management/Engineering - HOV | 235,555.29 | 372,525.20 |
Alaska | 0001579 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 237.90 | 509.42 |
Alaska | 0001579 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 2,697.18 | 5,775.58 |
Alaska | 0001579 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 80,889.29 | 173,210.48 |
Alaska | 0001579 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 917,096.25 | 1,963,803.52 |
Alaska | 0002432 | Northwest Arctic | >= 5,000 AND < 50,000 | Local | HIGHWAY INFRA PROGRAM APPORT | Construction Engineering | 1,355,195.07 | 1,489,716.47 |
Alaska | 0002432 | Northwest Arctic | >= 5,000 AND < 50,000 | Local | HIGHWAY INFRA PROGRAM APPORT | New Construction Roadway | 15,474,326.93 | 17,010,362.68 |
Alaska | 0002432 | Northwest Arctic | >= 5,000 AND < | Local | REDISTRIBUTION OF CERTAIN AUTH | New Construction | 2,809,429.41 | 3,088,303.19 |
Alaska | 0002432 | Northwest Arctic | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge New Construction | 4,313,001.81 | 4,741,125.43 |
Alaska | 0002432 | Northwest Arctic | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | 2,650,388.88 | 2,913,475.74 |
Alaska | 0002432 | Northwest Arctic | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | New Construction Roadway | 18,776,787.02 | 20,640,636.49 |
Alaska | 0002432 | Northwest Arctic | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Training | 38,986.10 | 42,856.00 |
Alaska | 0002469 | Northwest Arctic | >= 5,000 AND < 50,000 | Local | CONGESTION AIR QUALITY | New Construction Roadway | 2,577,895.86 | 2,833,786.81 |
Alaska | 0002469 | Northwest Arctic | >= 5,000 AND < 50,000 | Local | HIGH PRIORITY PROJECT SEC 1702 | New Construction Roadway | 901,033.02 | 990,472.71 |
Alaska | 0002469 | Northwest Arctic | >= 5,000 AND < 50,000 | Local | HIGH PRIORITY PROJECTS-TEA-21 | New Construction Roadway | 29,211.06 | 36,513.83 |
Alaska | 0002469 | Northwest Arctic | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | 3,505,934.37 | 3,853,945.66 |
Alaska | 0002469 | Northwest Arctic | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | New Construction Roadway | 20,016,181.63 | 22,003,057.74 |
Alaska | 0002469 | Northwest Arctic | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Training | 1,429.37 | 1,571.25 |
Alaska | 0003209 | Ketchikan Gateway | >= 5,000 AND < 50,000 | State | BRIDGE REPLAC & REHAB - DISC | Construction Engineering | 4,343,656.34 | 4,774,822.85 |
Alaska | 0003209 | Ketchikan Gateway | >= 5,000 AND < 50,000 | State | BRIDGE REPLAC & REHAB - DISC | Other | 15,733,383.30 | 17,295,133.89 |
Alaska | 0003209 | Ketchikan Gateway | >= 5,000 AND < 50,000 | State | BRIDGE REPLAC & REHAB - DISC | Preliminary Engineering | 272,910.00 | 300,000.00 |
Alaska | 0003209 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | FERRY BOATS & TERMINAL | Preliminary Engineering | 1,146,449.00 | 1,433,061.25 |
Alaska | 0003209 | Ketchikan | >= 5,000 AND < | State | HIGH PRIORITY PROJECT SEC 1702 | Other | 10,350,736.64 | 11,378,186.92 |
Alaska | 0003209 | Ketchikan Gateway | >= 5,000 AND < 50,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Right of Way | 4,548,500.00 | 5,000,000.00 |
Alaska | 0003209 | Ketchikan Gateway | >= 5,000 AND < 50,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Training | 19,584.02 | 21,528.00 |
Alaska | 0003209 | Ketchikan Gateway | >= 5,000 AND < 50,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Utilities | 64,019.23 | 70,374.00 |
Alaska | 000S735 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | BRIDGE PROGRAM - 15% OFF SYST | Bridge Replacement - No Added Capacity | 4,978.33 | 5,472.50 |
Alaska | 000S735 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | BRIDGE PROGRAM - 15% OFF SYST | Preliminary Engineering | 1,994,201.57 | 2,192,152.99 |
Alaska | 000S735 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | BRIDGE PROGRAM - 85% ON/OFF | Bridge Replacement - No Added Capacity | 713,661.98 | 784,502.56 |
Alaska | 000S735 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | BRIDGE PROGRAM - 85% ON/OFF | Preliminary Engineering | 245,769.29 | 270,165.21 |
Alaska | 000S735 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | BRIDGE REP & REHAB-15% OFF SYS | Preliminary Engineering | 25,916.75 | 28,489.34 |
Alaska | 000S735 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | BRIDGE REP & REHAB-65% ON SYS | Preliminary Engineering | 2,757.41 | 3,031.12 |
Alaska | 000S735 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | HIGH PRIORITY PROJECT SEC 1702 | Bridge Replacement - No Added Capacity | 1,451,601.92 | 1,595,693.00 |
Alaska | 000S735 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | HIGH PRIORITY PROJECT SEC 1702 | Construction Engineering | 291,859.05 | 320,830.00 |
Alaska | 000S735 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 16,143,326.27 | 17,745,769.24 |
Alaska | 000S735 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | 6,385,350.19 | 7,021,182.35 |
Alaska | 000S735 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 720,379.28 | 791,886.72 |
Alaska | 000S735 | Ketchikan | >= 5,000 AND < | Local | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | 1,766,760.21 | 1,942,135.00 |
Alaska | 000S735 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 216,396.71 | 237,877.00 |
Alaska | 000S735 | Ketchikan Gateway | >= 5,000 AND < 50,000 | Local | SURFACE TRANSPORTATION PROJECT | Preliminary Engineering | 499,915.00 | 499,915.00 |
Alaska | 0211065 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | 4R - Restoration & Rehabilitation | 26,526,393.97 | 29,473,771.07 |
Alaska | 0211065 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Construction Engineering | 4,868,251.87 | 5,409,168.74 |
Alaska | 0211065 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Preliminary Engineering | 3,481,800.00 | 3,484,800.00 |
Alaska | 0211065 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Training | 18,799.20 | 20,888.00 |
Alaska | 0211065 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Utilities | 1,144,493.94 | 1,208,746.00 |
Alaska | 0212015 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | CONSOLIDATED PRIMARY | Preliminary Engineering | 3,067,441.00 | 3,277,002.00 |
Alaska | 0212015 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Preliminary Engineering | 909,700.00 | 1,000,000.00 |
Alaska | 0212015 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 0.00 | 7,211,067.41 |
Alaska | 0212015 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | New Construction Roadway | 0.00 | 48,066,450.09 |
Alaska | 0212015 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | 33,064,543.96 | 35,972,676.66 |
Alaska | 0212015 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | 1,974,003.52 | 2,169,950.00 |
Alaska | 0212015 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 0.00 | 7,332.50 |
Alaska | 0212015 | Kenai Peninsula | >= 50,000 AND < | State | NATIONAL HIGHWAY SYSTEM | Preliminary Engineering | 7,881,543.00 | 8,213,600.00 |
Alaska | 0212015 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 5,688,865.04 | 5,924,259.34 |
Alaska | 0311032 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM ALLOC | Bridge Rehabilitation - Added Capacity | 5,299,015.49 | 5,825,014.28 |
Alaska | 0311032 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM ALLOC | Bridge Replacement - Added Capacity | 6,266,835.72 | 6,888,903.73 |
Alaska | 0311032 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | Construction Engineering | 3,398,193.50 | 3,735,510.06 |
Alaska | 0311032 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | HIGHWAY INFRASTRUCTURE | Preliminary Engineering | 1,508,152.72 | 1,919,350.87 |
Alaska | 0311032 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 0.00 | 39,000,000.00 |
Alaska | 0311032 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | 3,194,435.66 | 3,511,526.51 |
Alaska | 0311032 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | 500,299.82 | 549,961.32 |
Alaska | 0311032 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY SYSTEM | Right of Way | 114,114.98 | 125,442.43 |
Alaska | 0311032 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 12,886,297.84 | 14,165,436.78 |
Alaska | 0311032 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | 5,605,295.54 | 6,161,696.76 |
Alaska | 0311032 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Training | 92,811.23 | 102,024.00 |
Alaska | 0311032 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 2,134,929.52 | 2,346,850.08 |
Alaska | 0441008 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Construction Engineering | 2,509,415.10 | 2,788,239.00 |
Alaska | 0441008 | Matanuska- | >= 50,000 AND < | State | HSIP LIMITING FLEXIBLE | Preliminary Engineering | 3,493,592.10 | 3,882,769.00 |
Alaska | 0441008 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Safety | 14,526,850.64 | 16,142,044.16 |
Alaska | 0441008 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Training | 968.76 | 1,076.40 |
Alaska | 0441008 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Utilities | 1,255,828.78 | 1,395,365.31 |
Alaska | 0512005 | Anchorage | >= 200,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Preliminary Engineering | 909,700.00 | 1,000,000.00 |
Alaska | 0512005 | Anchorage | >= 200,000 | State | MINIMUM GUARANTEE - TEA-21 | Preliminary Engineering | 90,970.00 | 100,000.00 |
Alaska | 0512005 | Anchorage | >= 200,000 | State | REDISTRIBUTION OF CERTAIN AUTH | Preliminary Engineering | 14,637.00 | 16,089.92 |
Alaska | 0512005 | Anchorage | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 20,309,406.83 | 22,325,389.50 |
Alaska | 0512005 | Anchorage | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | 3,141,892.68 | 3,453,767.92 |
Alaska | 0512005 | Anchorage | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Facilities for Pedestrians and Bicycles | 524,100.91 | 576,125.00 |
Alaska | 0512005 | Anchorage | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 910,609.70 | 1,001,000.00 |
Alaska | 0512005 | Anchorage | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 2,104,964.00 | 2,314,922.37 |
Alaska | 0512005 | Anchorage | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | 963,737.09 | 1,059,401.00 |
Alaska | 0512005 | Anchorage | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Training | 1,429.37 | 1,571.25 |
Alaska | 0512005 | Anchorage | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 11,315,466.38 | 12,438,679.10 |
Alaska | 0617013 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | 4R - No Added Capacity | 5,458,200.00 | 6,000,000.00 |
Alaska | 0617013 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | Bridge Replacement - Added Capacity | 10,669,645.51 | 11,728,751.80 |
Alaska | 0617013 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | Construction Engineering | 1,896,203.79 | 2,084,427.60 |
Alaska | 0617013 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | Facilities for Pedestrians and Bicycles | 911,920.22 | 1,002,440.61 |
Alaska | 0617013 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | Utilities | 10,894.59 | 11,976.03 |
Alaska | 0617013 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | 8,460,620.12 | 9,300,450.83 |
Alaska | 0617013 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | 6,023,223.35 | 6,621,109.54 |
Alaska | 0617013 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 3,801,290.31 | 4,178,619.67 |
Alaska | 0617013 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Facilities for Pedestrians and Bicycles | 2,067,186.82 | 2,272,383.01 |
Alaska | 0617013 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 2,994.28 | 3,291.50 |
Alaska | 0617013 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 4,385,008.18 | 4,820,279.41 |
Alaska | 0651029 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | EQUITY BONUS EXEMPT LIM | 4R - Restoration & Rehabilitation | 2,568,502.48 | 2,823,461.00 |
Alaska | 0651029 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 19,979,190.50 | 21,962,394.75 |
Alaska | 0651029 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - No Added Capacity | 2,791,468.52 | 3,068,559.44 |
Alaska | 0651029 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 3,112,302.95 | 3,421,241.01 |
Alaska | 0651029 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | 636,522.69 | 699,705.98 |
Alaska | 0651029 | Fairbanks North | >= 50,000 AND < | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 1,958.40 | 2,152.80 |
RECIPIENT | PROJECT NUMBER | COUNTY | POPULATION RANGE | OWNERSHIP | PROGRAM | TYPE OF IMPROVEMENT | TOTAL OBLIGATIONS | ESTIMATED TOTAL COST |
Alaska | 0651029 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 1,178,062.00 | 1,295,449.08 |
Alaska | 0651029 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 112,802.80 | 124,000.00 |
Alaska | 0656005 | North Slope | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 0.00 | 28,859,546.28 |
Alaska | 0656005 | North Slope | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 0.00 | 8,110,121.72 |
Alaska | 0656005 | North Slope | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | 1,364,550.00 | 1,500,000.00 |
Alaska | 0656005 | North Slope | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 0.00 | 2,095.00 |
Alaska | 0656005 | North Slope | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 1,091,640.00 | 1,201,000.00 |
Alaska | 0657003 | North Slope | >= 5,000 AND < 50,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Preliminary Engineering | 363,880.00 | 400,000.00 |
Alaska | 0657003 | North Slope | >= 5,000 AND < 50,000 | State | HIGHWAY PROJECTS,DEMOS S378 | Preliminary Engineering | 940,000.00 | 940,000.00 |
Alaska | 0657003 | North Slope | >= 5,000 AND < 50,000 | State | INTERSTATE MAINTENANCE | Preliminary Engineering | 1,941,228.55 | 2,133,921.69 |
Alaska | 0657003 | North Slope | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | 37,819,336.54 | 41,573,416.00 |
Alaska | 0657003 | North Slope | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 3,252,547.75 | 3,575,407.00 |
Alaska | 0657003 | North Slope | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 978.84 | 1,076.00 |
Alaska | 0657003 | North Slope | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY SYSTEM | Preliminary Engineering | 2,589,048.18 | 2,846,046.19 |
Alaska | 0670001 | Fairbanks North | >= 50,000 AND < | State | EQUITY BONUS SP LIMITATION | 4R - Added Capacity | 12,641.63 | 13,896.48 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | 4R - Added Capacity | 3,144,758.24 | 3,456,917.93 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | Local | HIGHWAY INFRA PROGRAM APPORT | 4R - Added Capacity | 213,232.41 | 234,398.60 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | MINIMUM GUARANTEE - TEA-21 | Preliminary Engineering | 1,046,767.96 | 1,109,215.00 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 3,088,575.28 | 3,395,158.05 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 996,023.43 | 1,094,892.20 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Facilities for Pedestrians and Bicycles | 854,185.38 | 938,974.81 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 714.69 | 785.63 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 1,786,174.03 | 1,963,475.90 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 4,698,063.63 | 5,164,409.83 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 318,555.29 | 350,176.21 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | 1,181,430.42 | 1,298,703.33 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | 80,107.66 | 88,059.43 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Facilities for Pedestrians and Bicycles | 799,944.62 | 879,349.92 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Facilities for Pedestrians and Bicycles | 54,240.77 | 59,624.90 |
Alaska | 0670001 | Fairbanks North | >= 50,000 AND < | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 7,368,638.68 | 7,808,242.00 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Training | 669.29 | 735.73 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Training | 45.39 | 49.89 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 2,772,579.28 | 3,047,795.18 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 113,422.05 | 124,680.72 |
Alaska | 0670001 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | URBAN SYSTEM NON ATTRIBUTABLE | Preliminary Engineering | 235,925.00 | 255,000.00 |
Alaska | 0713013 | Valdez-Cordova | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | 15,010,050.00 | 26,124,401.30 |
Alaska | 0713013 | Valdez-Cordova | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | 1,728,430.00 | 2,613,143.99 |
Alaska | 0713013 | Valdez-Cordova | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 0.00 | 418,102.91 |
Alaska | 0713013 | Valdez-Cordova | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 532,419.00 | 1,180,248.00 |
Alaska | 0713013 | Valdez-Cordova | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | New Construction Roadway | 2,729,100.00 | 3,000,000.00 |
Alaska | 0713013 | Valdez-Cordova | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 0.00 | 2,152.80 |
Alaska | 0955016 | Juneau | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 1,399,262.79 | 15,688,207.43 |
Alaska | 0955016 | Juneau | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | 690,903.20 | 3,393,617.09 |
Alaska | 0955016 | Juneau | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Facilities for Pedestrians and Bicycles | 985,852.11 | 1,083,711.23 |
Alaska | 0955016 | Juneau | >= 5,000 AND < | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 1,048,237.09 | 1,860,303.51 |
Alaska | 0955016 | Juneau | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Training | 7,146.83 | 15,712.50 |
Alaska | 0955016 | Juneau | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 1,184,470.26 | 1,302,044.92 |
Alaska | 0956036 | Hoonah-Angoon | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | 3,197,324.26 | 9,867,799.73 |
Alaska | 0956036 | Haines | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | 9,850,687.55 | 30,401,862.37 |
Alaska | 0956036 | Haines | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 0.00 | 4,026,777.14 |
Alaska | 0956036 | Hoonah-Angoon | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 0.00 | 1,307,006.45 |
Alaska | 0956036 | Hoonah-Angoon | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 0.00 | 3,850.24 |
Alaska | 0956036 | Haines | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 0.00 | 11,862.26 |
Alaska | 0956036 | Haines | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 0.00 | 2,130,059.77 |
Alaska | 0956036 | Hoonah-Angoon | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 0.00 | 691,372.23 |
Alaska | 0965035 | Haines | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | 35,498,526.34 | 39,022,234.08 |
Alaska | 0965035 | Haines | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 5,869,126.44 | 6,451,716.43 |
Alaska | 0965035 | Haines | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 48,457.75 | 53,267.84 |
Alaska | 0965035 | Haines | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 959,587.95 | 1,054,840.00 |
Alaska | 0972016 | Skagway | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - No Added Capacity | 8,468,930.57 | 9,309,586.21 |
Alaska | 0972016 | Skagway | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 2,622,225.41 | 2,917,516.66 |
Alaska | 0972016 | Skagway | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | 2,509,976.38 | 2,761,259.32 |
Alaska | 0972016 | Skagway | < 5,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 60,946.26 | 66,996.00 |
Alaska | 0972016 | Skagway | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 9,392,437.43 | 10,324,763.58 |
Alaska | 0972016 | Skagway | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | 2,459,582.94 | 2,703,729.74 |
Alaska | 0972016 | Skagway | < 5,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Training | 85,933.90 | 94,464.00 |
Alaska | 0A13021 | Valdez-Cordova | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 33,485,222.39 | 35,851,415.84 |
Alaska | 0A13021 | Valdez-Cordova | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - No Added Capacity | 919,304.73 | 984,266.31 |
Alaska | 0A13021 | Valdez-Cordova | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 3,104,218.92 | 3,323,574.85 |
Alaska | 0A13021 | Valdez-Cordova | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | 1,793,280.00 | 1,920,000.00 |
Alaska | 0A13021 | Valdez-Cordova | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 2,466.69 | 2,641.00 |
Alaska | 0A13021 | Valdez-Cordova | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 493,619.00 | 528,500.00 |
Alaska | 0A15036 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | INTERSTATE MAINTENANCE | Utilities | 580,756.53 | 621,795.00 |
Alaska | 0A15036 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 39,547,701.44 | 42,342,292.76 |
Alaska | 0A15036 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 5,327,524.29 | 5,703,987.47 |
Alaska | 0A15036 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 2,876.72 | 3,080.00 |
Alaska | 0A15036 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 14,642,752.31 | 15,677,465.00 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | CONGESTION AIR QUALITY | 4R - Added Capacity | 1,857,152.00 | 1,988,385.00 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | CONGESTION AIR QUALITY | Construction Engineering | 278,573.00 | 298,257.00 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | EQUITY BONUS SP LIMITATION | Right of Way | 564,361.64 | 604,241.58 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | INTERSTATE MAINTENANCE | 4R - Added Capacity | 9,974,445.65 | 10,679,278.00 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | INTERSTATE MAINTENANCE | Construction Engineering | 2,088,034.52 | 2,236,583.00 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | INTERSTATE MAINTENANCE | New Construction Roadway | 0.00 | 3,839.88 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | INTERSTATE MAINTENANCE | Preliminary Engineering | 18,043.34 | 20,326.25 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | INTERSTATE MAINTENANCE | Right of Way | 2,788,047.00 | 2,985,061.00 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | INTERSTATE MAINTENANCE | Utilities | 2,025,219.28 | 2,187,647.35 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | NAT'L COOR INF IM PROGRAM | 4R - Added Capacity | 2,184,254.00 | 2,338,601.00 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | NAT'L COOR INF IM PROGRAM | Construction Engineering | 599,224.00 | 641,567.00 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | NAT'L COOR INF IM PROGRAM | Debt Service | 5,721.00 | 6,125.00 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | NAT'L COOR INF IM PROGRAM | Utilities | 1,323,774.45 | 1,417,317.40 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | NATIONAL HIGHWAY SYSTEM | Preliminary Engineering | 1,399,132.00 | 1,498,000.00 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | NATIONAL HIGHWAY SYSTEM | Right of Way | 15,878,000.00 | 17,395,484.97 |
Alaska | 0A16035 | Anchorage | >= 200,000 | N/A | REDISTRIBUTION OF CERTAIN AUTH | Right of Way | 108,032.43 | 115,666.42 |
Alaska | 0A24019 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | INTERSTATE MAINTENANCE | 4R - Added Capacity | 294,685.49 | 315,509.09 |
Alaska | 0A24019 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | INTERSTATE MAINTENANCE | Preliminary Engineering | 2,089,358.00 | 2,237,000.00 |
Alaska | 0A24019 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | INTERSTATE MAINTENANCE | Right of Way | 1,475,720.00 | 1,580,000.00 |
Alaska | 0A24019 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | INTERSTATE MAINTENANCE | Utilities | 140,059.97 | 149,957.14 |
Alaska | 0A24019 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 17,272,866.62 | 18,493,433.20 |
Alaska | 0A24019 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 1,718,022.41 | 1,839,424.42 |
Alaska | 0A24019 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | 392,130.56 | 419,840.00 |
Alaska | 0A24019 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | 833,277.44 | 892,160.00 |
Alaska | 0A24019 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 2,010.72 | 2,152.80 |
Alaska | 0A24019 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 1,257,204.03 | 1,346,042.86 |
Alaska | 0A24019 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY SYSTEM | 4R - Added Capacity | 224,252.92 | 240,099.49 |
Alaska | 0A24019 | Fairbanks North Star | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 115,200.00 | 130,000.00 |
Alaska | 0A31056 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 20,272,654.84 | 30,905,197.90 |
Alaska | 0A31056 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - Added Capacity | 793,900.00 | 850,000.00 |
Alaska | 0A31056 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | 5,127,071.58 | 5,489,370.00 |
Alaska | 0A31056 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 3,928,936.92 | 4,206,570.58 |
Alaska | 0A31056 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 9,340.00 | 10,000.00 |
Alaska | 0A31056 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 1,563,953.11 | 1,674,468.00 |
Alaska | 0A31057 | Anchorage | >= 200,000 | State | EMERGENCY RELIEF | 4R - Restoration & Rehabilitation | 14,832.81 | 14,832.81 |
Alaska | 0A31057 | Anchorage | >= 200,000 | State | EMERGENCY RELIEF | Construction Engineering | 2,224.90 | 2,224.90 |
Alaska | 0A31057 | Anchorage | >= 200,000 | State | INTERSTATE MAINTENANCE | 4R - Added Capacity | 168,172.12 | 180,055.80 |
Alaska | 0A31057 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 50,261,884.64 | 53,813,580.98 |
Alaska | 0A31057 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | 2,545,816.88 | 2,725,714.00 |
Alaska | 0A31057 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 4,420,863.48 | 4,733,258.55 |
Alaska | 0A31057 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 6,327,630.00 | 6,775,611.15 |
Alaska | 0A31057 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 4,933.39 | 5,282.00 |
Alaska | 0A31057 | Anchorage | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 2,702,758.76 | 2,893,746.00 |
Alaska | 0A31057 | Anchorage | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 6,611,542.43 | 7,078,739.22 |
Alaska | 0A33014 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | EQUITY BONUS EXEMPT LIM | Preliminary Engineering | 113,616.86 | 121,645.47 |
Alaska | 0A33014 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | EQUITY BONUS SP LIMITATION | Preliminary Engineering | 221,542.94 | 237,198.01 |
Alaska | 0A33014 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | EXTENSION OF ALLOC PROGRAMS | Preliminary Engineering | 1,653.25 | 1,770.07 |
Alaska | 0A33014 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | FAST ACT NATIONAL FREIGHT | 4R - No Added Capacity | 4,089.05 | 4,378.00 |
Alaska | 0A33014 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | FAST ACT NATIONAL FREIGHT | 4R - Restoration & Rehabilitation | 53,234,181.11 | 59,686,911.25 |
Alaska | 0A33014 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | FAST ACT NATIONAL FREIGHT | Bridge New Construction | 2,862,557.76 | 3,064,837.00 |
Alaska | 0A33014 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | FAST ACT NATIONAL FREIGHT | Construction Engineering | 8,793,239.64 | 9,818,253.47 |
Alaska | 0A33014 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | FAST ACT NATIONAL FREIGHT | Utilities | 508,932.86 | 544,896.00 |
Alaska | 0A33014 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | INTERSTATE MAINTENANCE | Preliminary Engineering | 4,002,190.00 | 4,286,000.00 |
Alaska | 0A33014 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 2,520,764.69 | 2,698,891.53 |
Alaska | 0A33014 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 0.00 | 371.28 |
Alaska | 0A33014 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | 124,471.80 | 133,267.45 |
Alaska | 0A33014 | Kenai Peninsula | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY SYSTEM | Preliminary Engineering | 887,300.00 | 950,000.00 |
Alaska | 0A41025 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | INTERSTATE MAINTENANCE | Right of Way | 4,924,989.00 | 5,273,007.00 |
Alaska | 0A41025 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 14,730,227.95 | 15,771,122.00 |
Alaska | 0A41025 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 3,205,439.43 | 3,445,352.00 |
Alaska | 0A41025 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | New Construction Roadway | 0.00 | 62,677.00 |
Alaska | 0A41025 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 934.00 | 1,000.00 |
Alaska | 0A41025 | Matanuska- | >= 50,000 AND < | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 2,655,590.63 | 2,843,244.77 |
Alaska | 0A41026 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Construction Engineering | 696,477.70 | 773,864.11 |
Alaska | 0A41026 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Preliminary Engineering | 883,041.05 | 981,156.72 |
Alaska | 0A41026 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Safety | 3,877,975.48 | 4,308,861.64 |
Alaska | 0A41026 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Training | 13,709.16 | 15,232.40 |
Alaska | 0A41026 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 37,158,691.16 | 40,847,192.66 |
Alaska | 0A41026 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | 7,161,980.45 | 7,873,750.34 |
Alaska | 0A41026 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 121,983.13 | 134,091.60 |
Alaska | 0A41026 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 5,303,289.91 | 5,829,713.00 |
Alaska | 0A41026 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 4,533,763.00 | 4,990,574.19 |
Alaska | 0A41026 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | 9,403,180.00 | 10,351,933.93 |
Alaska | 0A41029 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Construction Engineering | 1,332,192.02 | 1,456,272.32 |
Alaska | 0A41029 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Preliminary Engineering | 781,682.65 | 868,536.28 |
Alaska | 0A41029 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | HSIP LIMITING FLEXIBLE | Safety | 9,708,482.16 | 9,708,482.16 |
Alaska | 0A41029 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 38,190,184.37 | 40,888,848.36 |
Alaska | 0A41029 | Matanuska- | >= 50,000 AND < | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge New Construction | 2,674,191.91 | 2,863,160.50 |
Alaska | 0A41029 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | 22,368,299.46 | 24,790,806.40 |
Alaska | 0A41029 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Training | 20,107.15 | 21,528.00 |
Alaska | 0A41029 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 9,151,807.36 | 9,805,302.10 |
Alaska | 0A41029 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY SYSTEM | Preliminary Engineering | 6,280,568.80 | 6,905,000.00 |
Alaska | 0A41029 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | REPURPOSED EARMARK SUBJ TO LIM | Right of Way | 679,590.42 | 834,176.82 |
Alaska | 0A41029 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | REPURPOSED EARMARK SUBJ TO LIM | Utilities | 516,626.56 | 569,227.90 |
Alaska | 0A41029 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | REPURPOSED SPECIAL | Right of Way | 3,130,710.80 | 3,475,823.18 |
Alaska | 0A41034 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | Bridge Replacement - No Added Capacity | 12,130,796.57 | 12,988,004.89 |
Alaska | 0A41034 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | Construction Engineering | 0.00 | 96,730.00 |
Alaska | 0A41034 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - No Added Capacity | 0.00 | 11,249,174.77 |
Alaska | 0A41034 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | 2,648,014.22 | 3,032,292.69 |
Alaska | 0A41034 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | 3,982,452.10 | 4,263,867.34 |
Alaska | 0A41034 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 36,087.90 | 38,638.00 |
Alaska | 0A41034 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Training | 1,956.73 | 2,095.00 |
Alaska | 0A41034 | Matanuska- Susitna | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 494,525.91 | 529,471.00 |
Alaska | 9500140 | Statewide | N/A | State | AK HWY/AK MARINE HWY-EXEMPT | Ferry Boats | 2,731,423.02 | 2,731,423.02 |
Alaska | 9500140 | Statewide | N/A | State | FERRY BOATS & TERMINAL | Construction Engineering | 2,794,988.10 | 3,493,735.13 |
Alaska | 9500140 | Statewide | N/A | State | FERRY BOATS & TERMINAL | Ferry Boats | 31,110,325.33 | 38,887,906.66 |
Alaska | 9500140 | Statewide | N/A | State | FERRY BOATS & TERMINAL | Preliminary Engineering | 699,946.62 | 874,933.24 |