DETAILED PROJECT LEVEL DATA PURSUANT TO 23 U.S.C. 104(g)(3)(B) WITH AN ESTIMATED TOTAL COST OF $25,000,000 OR MORE
AS OF SEPTEMBER 30, 2021
RECIPIENT PROJECT
NUMBER
COUNTY POPULATION
RANGE
OWNERSHIP PROGRAM TYPE OF
IMPROVEMENT
TOTAL
OBLIGATIONS
ESTIMATED
TOTAL COST
Delaware 2011017 Kent >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 3,594,583.29 3,594,583.29
Delaware 2011017 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 5,000.00 5,000.00
Delaware 2011017 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 54,000.00 54,000.00
Delaware 2011017 Kent >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM New Construction Roadway 26,492,088.68 26,492,088.68
Delaware 2011017 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM New Construction Roadway 5,821,290.27 5,858,690.27
Delaware 2011017 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other 0.00 50,000.00
Delaware 2011017 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other 0.00 324,000.00
Delaware 2011017 Kent >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Rail/Hwy Crossing 391,775.12 391,775.12
Delaware 2011017 Kent >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV 1,011,909.08 1,011,909.08
Delaware 2011017 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV 68,047.49 68,047.49
Delaware 2011017 Kent >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Utilities 1,689,233.75 1,689,233.75
Delaware 2011017 Kent >= 50,000 AND < 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM New Construction Roadway 5,600,000.00 5,600,000.00
Delaware 2011017 Kent >= 50,000 AND < 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Other 0.00 8,906,078.07
Delaware 2011017 Kent >= 50,000 AND < 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Preliminary Engineering 1,922,374.45 2,402,968.06
Delaware 2011017 Kent >= 50,000 AND < 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Right of Way 7,522,955.22 7,522,955.22
Delaware 2015019 New Castle >= 200,000 State EQUITY BONUS EXEMPT LIM Construction Engineering 4,975.49 4,975.49
Delaware 2015019 New Castle >= 200,000 State EQUITY BONUS SP LIMITATION Construction Engineering 12,499.99 12,499.99
Delaware 2015019 New Castle >= 200,000 State FAST ACT NATIONAL FREIGHT Other 0.00 187,520.00
Delaware 2015019 New Castle >= 200,000 State FAST ACT NATIONAL FREIGHT Preliminary Engineering 1,974.72 1,975.72
Delaware 2015019 New Castle >= 200,000 State HIGHWAY INFRA PROGRAM APPORT 4R - Added Capacity 192,770.18 192,770.18
Delaware 2015019 New Castle >= 200,000 State HIGHWAY INFRA PROGRAM APPORT 4R - Added Capacity 955,333.00 955,333.00
Delaware 2015019 New Castle >= 200,000 State HIGHWAY INFRA PROGRAM APPORT Traffic Management/Engineering - HOV 491,456.54 491,456.54
Delaware 2015019 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM 4R - Added Capacity 3,415,845.33 8,383,883.19
Delaware 2015019 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM 4R - Added Capacity 9,693,330.82 10,883,788.46
Delaware 2015019 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering 982,524.52 1,007,149.56
Delaware 2015019 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering 1,701,000.00 2,766,358.32
Delaware 2015019 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Other 0.00 562,360.00
Delaware 2015019 New Castle >= 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Preliminary Engineering 699,999.00 699,999.00
Delaware 2015019 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Preliminary Engineering 407,505.96 407,505.96
Delaware 2015019 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Preliminary Engineering 2,355,030.93 2,355,030.93
Delaware 2015019 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Right of Way 4,400,000.00 5,500,000.00
Delaware 2015019 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Traffic Management/Engineering - HOV 58,757.05 58,757.05
Delaware 2015019 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Traffic Management/Engineering - HOV 1,485,108.47 1,485,108.47
Delaware 2015019 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Utilities 0.00 986,273.78
Delaware K008006 Kent >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM 4R - No Added Capacity 5,833,201.84 5,833,201.84
Delaware K008006 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - No Added Capacity 2,513,206.00 2,777,376.65
Delaware K008006 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - No Added Capacity 23,605,209.52 23,620,909.52
Delaware K008006 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 854,475.63 854,475.63
Delaware K008006 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 5,868,668.08 5,868,668.08
Delaware K008006 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other 0.00 63,476.00
Delaware K008006 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other 429,121.37 6,813,948.13
Delaware K008006 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Preliminary Engineering 341,600.00 427,000.00
Delaware K008006 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV 1,698,899.88 1,698,899.88
Delaware K008006 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY SYSTEM Construction Engineering 345,190.54 345,190.54
Delaware K008006 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY SYSTEM Preliminary Engineering 4,057,600.00 5,777,359.77
Delaware K008006 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY SYSTEM Right of Way 15,168,000.00 19,660,000.00
Delaware K008006 Kent >= 50,000 AND < 200,000 State REPURPOSED EARMARK SUBJ TO LIM 4R - No Added Capacity 2,207,752.68 2,207,752.68
Delaware K008006 Kent >= 50,000 AND < 200,000 N/A REPURPOSED SPECIAL 4R - No Added Capacity 1,878,688.00 1,878,688.00
Delaware K008006 Kent >= 50,000 AND < 200,000 State REPURPOSED SPECIAL 4R - No Added Capacity 8,472,666.44 8,472,666.44
Delaware K008011 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - No Added Capacity 15,288,979.75 19,301,224.69
Delaware K008011 Kent >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 195.00 195.00
Delaware K008011 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 3,484,363.73 4,355,454.66
Delaware K008011 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other 314,007.68 981,713.41
Delaware K008011 Kent >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Preliminary Engineering 164,051.75 205,064.69
Delaware K008011 Kent >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV 40,568.63 40,568.63
Delaware K008011 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV 591,525.87 739,407.34
Delaware K008011 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Utilities 76,986.98 96,233.73
Delaware K008011 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Utilities 193,201.24 241,501.55
Delaware K008011 Kent >= 50,000 AND < 200,000 State NATIONAL HIGHWAY SYSTEM 4R - No Added Capacity 1,135,436.39 1,419,295.49
Delaware K008011 Kent >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY SYSTEM Preliminary Engineering 2,146,908.46 2,683,635.58
Delaware K008011 Kent >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY SYSTEM Right of Way 1,990,987.14 2,488,733.92
Delaware N011031 New Castle >= 200,000 State CONGESTION AIR QUALITY 4R - Added Capacity 8,000,000.00 8,000,000.00
Delaware N011031 New Castle >= 200,000 State CONGESTION AIR QUALITY Construction Engineering 104,000.00 130,000.00
Delaware N011031 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity 9,510,169.18 16,022,048.37
Delaware N011031 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 39,124.89 48,906.11
Delaware N011031 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other 0.00 4,425,000.00
Delaware N011031 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Preliminary Engineering 995,527.04 995,598.46
Delaware N011031 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV 12,090.00 15,112.50
Delaware N011031 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV 1,412,253.74 1,412,253.74
Delaware N011031 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Utilities 176,000.00 220,000.00
Delaware N011031 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Utilities 1,788,385.20 1,796,385.20
Delaware N011031 New Castle >= 200,000 State NATIONAL HIGHWAY SYSTEM 4R - Added Capacity 193,222.75 193,222.75
Delaware N011031 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM 4R - Added Capacity 4,294,799.56 4,294,799.56
Delaware N011031 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering 1,926,958.29 1,926,958.29
Delaware N011031 New Castle >= 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Preliminary Engineering 500,000.00 500,000.00
Delaware N011031 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Preliminary Engineering 1,259,472.96 1,259,472.96
Delaware N011031 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Utilities 18,137.60 22,672.00
Delaware N029003 New Castle >= 200,000 State HIGH PRIORITY PROJECT SEC 1702 New Construction Roadway 1,567,949.49 1,959,936.87
Delaware N029003 New Castle >= 200,000 State HIGH PRIORITY PROJECT SEC 1702 Other 0.00 8,979,137.07
Delaware N029003 New Castle >= 200,000 N/A HIGH PRIORITY PROJECT SEC 1702 Preliminary Engineering 1,300,000.00 1,300,000.00
Delaware N029003 New Castle >= 200,000 State HIGH PRIORITY PROJECT SEC 1702 Preliminary Engineering 26,629.00 26,629.00
Delaware N029003 New Castle >= 200,000 State HIGH PRIORITY PROJECT SEC 1702 Preliminary Engineering 2,890,355.93 2,890,355.93
Delaware N029003 New Castle >= 200,000 State HIGH PRIORITY PROJECT SEC 1702 Right of Way 4,000,000.00 4,000,000.00
Delaware N029003 New Castle >= 200,000 State HIGHWAY INFRA PROGRAM APPORT New Construction Roadway 807,147.00 1,008,933.75
Delaware N029003 New Castle >= 200,000 State REDISTRIBUTION OF CERTAIN AUTH New Construction Roadway 21,137.60 26,422.00
Delaware N029003 New Castle >= 200,000 State REDISTRIBUTION OF CERTAIN AUTH New Construction Roadway 986,851.03 1,233,563.79
Delaware N029003 New Castle >= 200,000 State REDISTRIBUTION OF CERTAIN AUTH Other 0.00 46,500.00
Delaware N029003 New Castle >= 200,000 State REDISTRIBUTION OF CERTAIN AUTH Right of Way 2,368,876.02 2,368,876.02
Delaware N029003 New Castle >= 200,000 State REPURPOSED EARMARK SUBJ TO LIM New Construction Roadway 742,952.98 928,691.25
Delaware N029003 New Castle >= 200,000 State REPURPOSED SPECIAL New Construction Roadway 3,060,357.45 3,825,446.82
Delaware N029003 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering 4,819,863.86 6,024,829.82
Delaware N029003 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM New Construction Roadway 4,240,648.12 5,300,810.15
Delaware N029003 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM New Construction Roadway 11,267,996.90 14,084,996.13
Delaware N029003 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Other 0.00 1,429,720.00
Delaware N029003 New Castle >= 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Preliminary Engineering 900,000.00 900,000.00
Delaware N029003 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Preliminary Engineering 623,371.00 623,371.00
Delaware N029003 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Right of Way 2,751,123.98 2,751,123.98
Delaware N029003 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Traffic Management/Engineering - HOV 550,773.73 688,467.16
Delaware N029003 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Utilities 1,216,988.80 1,521,236.00
Delaware N029005 New Castle >= 200,000 State CONGESTION AIR QUALITY Construction Engineering 2,812,614.24 3,515,767.80
Delaware N029005 New Castle >= 200,000 State HIGH PRIORITY PROJECT SEC 1702 Bridge New Construction 5,939,914.43 7,424,893.04
Delaware N029005 New Castle >= 200,000 State HIGH PRIORITY PROJECT SEC 1702 Construction Engineering 669,250.16 836,562.70
Delaware N029005 New Castle >= 200,000 State HIGH PRIORITY PROJECT SEC 1702 Right of Way 3,602,708.37 3,602,708.37
Delaware N029005 New Castle >= 200,000 State HIGH PRIORITY PROJECT SEC 1702 Utilities 32,693.62 40,867.03
Delaware N029005 New Castle >= 200,000 State REDISTRIBUTION OF CERTAIN AUTH Bridge New Construction 486,282.80 607,853.50
Delaware N029005 New Castle >= 200,000 State REDISTRIBUTION OF TIFIA FUNDS Bridge New Construction 14,345.92 17,932.40
Delaware N029005 New Castle >= 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Bridge New Construction 7,774,574.30 9,718,217.88
Delaware N029005 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Bridge New Construction 9,642,711.97 12,053,389.95
Delaware N029005 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Other 527,693.82 659,617.27
Delaware N029005 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Utilities 627,612.56 784,515.70
Delaware N032013 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity 11,367,028.38 15,211,807.49
Delaware N032013 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 395,431.07 494,288.84
Delaware N032013 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 2,089,413.60 2,611,767.00
Delaware N032013 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other 0.00 404,147.26
Delaware N032013 New Castle >= 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Preliminary Engineering 298,023.20 372,529.00
Delaware N032013 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Preliminary Engineering 30,545.60 38,182.00
Delaware N032013 New Castle >= 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Right of Way 3,500,000.00 3,500,000.00
Delaware N032013 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV 890,268.08 1,112,835.10
Delaware N032013 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Utilities 189,920.19 237,400.24
Delaware N032013 New Castle >= 200,000 N/A NATIONAL HIGHWAY SYSTEM Preliminary Engineering 976,000.00 1,220,000.00
Delaware N032013 New Castle >= 200,000 State NATIONAL HIGHWAY SYSTEM Preliminary Engineering 9,034.40 11,293.00
Delaware N056041 New Castle >= 200,000 State EQUITY BONUS EXEMPT LIM Safety 4,260.80 5,326.00
Delaware N056041 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 416,698.40 520,873.00
Delaware N056041 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 3,220,824.80 4,592,501.00
Delaware N056041 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other 0.00 3,483,972.27
Delaware N056041 New Castle >= 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Preliminary Engineering 800,000.00 1,000,000.00
Delaware N056041 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Preliminary Engineering 564,494.48 705,618.10
Delaware N056041 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Preliminary Engineering 905,061.07 1,131,326.33
Delaware N056041 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Safety 17,000,000.00 32,093,182.97
Delaware N056041 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Safety 26,537,950.44 33,172,438.05
Delaware N056041 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV 1,461,325.98 1,826,657.48
Delaware N056041 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Utilities 0.00 1,116,974.00
Delaware N056041 New Castle >= 200,000 State REDISTRIBUTION OF CERTAIN AUTH Safety 312,746.62 390,933.28
Delaware N056041 New Castle >= 200,000 State REPURPOSED EARMARK SUBJ TO LIM Safety 446,930.00 558,662.50
Delaware N056041 New Castle >= 200,000 State REPURPOSED SPECIAL Safety 486,899.63 608,624.54
Delaware N056041 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Other 0.00 10,160.00
Delaware N056041 New Castle >= 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Preliminary Engineering 2,853,266.42 3,566,583.03
Delaware N056041 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Preliminary Engineering 97,461.92 121,827.40
Delaware N056041 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Safety 669,545.00 836,931.25
Delaware N056041 New Castle >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Safety 4,066,169.37 5,082,711.71
Delaware N056042 New Castle >= 200,000 State CONGESTION AIR QUALITY Safety 9,334,639.52 9,334,639.52
Delaware N056042 New Castle >= 200,000 N/A INTERSTATE MAINTENANCE Preliminary Engineering 2,160,000.00 2,700,000.00
Delaware N056042 New Castle >= 200,000 State INTERSTATE MAINTENANCE Safety 1,500,000.00 1,500,000.00
Delaware N056042 New Castle >= 200,000 N/A INTERSTATE MAINTENANCE Utilities 15,500.00 78,865.87
Delaware N056042 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity 14,420,791.44 14,420,791.44
Delaware N056042 New Castle >= 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 2,395,864.44 2,395,864.44
Delaware N056042 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 2,042,533.23 2,042,533.23
Delaware N056042 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Safety 5,726,465.04 5,726,465.04
Delaware N056042 New Castle >= 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV 604,135.56 604,135.56
Delaware N056042 New Castle >= 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Utilities 218,832.41 218,832.41
Delaware N056042 New Castle >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Utilities 164,893.83 164,893.83
Delaware N056042 New Castle >= 200,000 State NATIONAL HIGHWAY SYSTEM Construction Engineering 19,812.33 19,812.33
Delaware N056042 New Castle >= 200,000 State NATIONAL HIGHWAY SYSTEM Safety 2,849,686.69 2,849,686.69
Delaware N056042 New Castle >= 200,000 State REDISTRIBUTION OF CERTAIN AUTH 4R - Added Capacity 579,208.56 579,208.56
Delaware S014014 Sussex >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - No Added Capacity 0.00 21,182,142.12
Delaware S014014 Sussex >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering 0.00 5,125,000.00
Delaware S014014 Sussex >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other 0.00 9,323,916.87
Delaware S014014 Sussex >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Preliminary Engineering 2,400,000.00 2,400,000.00
Delaware S014014 Sussex >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Preliminary Engineering 247,642.45 247,642.45
Delaware S014014 Sussex >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Preliminary Engineering 682,026.34 682,026.34
Delaware S014014 Sussex >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV 0.00 729,204.00
Delaware S014014 Sussex >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Utilities 0.00 14,000.00
Delaware S014014 Sussex >= 50,000 AND < 200,000 State NATIONAL HIGHWAY SYSTEM Preliminary Engineering 141,279.24 141,279.24
Delaware S014014 Sussex >= 50,000 AND < 200,000 State SURFACE TRANSP BLOCK GRNT PRGM 4R - No Added Capacity 2,000,000.00 2,000,000.00
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE PROGRAM - 85% ON/OFF 4R - No Added Capacity 4,676,664.32 6,067,616.47
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE PROGRAM - 85% ON/OFF Bridge Rehabilitation - No Added Capacity 384,973.33 481,216.66
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE PROGRAM - 85% ON/OFF Preliminary Engineering 296,086.69 370,108.36
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE REP & REHAB-15% OFF SYS Bridge Rehabilitation - No Added Capacity 68,800.00 86,000.00
Delaware S050007 Sussex >= 50,000 AND < N/A BRIDGE REP & REHAB-15% OFF SYS Construction Engineering 1,485,234.57 2,009,146.05
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE REP & REHAB-15% OFF SYS Utilities 0.00 7,745,909.00
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE REP & REHAB-20% ON/OFF Construction Engineering 157,431.06 196,788.83
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE REP & REHAB-20% ON/OFF Preliminary Engineering 493,959.34 617,449.18
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE REP & REHAB-65% ON SYS 4R - No Added Capacity 3,748,081.59 4,685,101.99
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE REP & REHAB-65% ON SYS Bridge Rehabilitation - No Added Capacity 360,000.00 450,000.00
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE REP & REHAB-65% ON SYS Construction Engineering 37,632.00 47,040.00
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE REP & REHAB-65% ON SYS Preliminary Engineering 4,549,960.78 16,802,149.84
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE REP & REHAB-65% ON SYS Utilities 239,517.50 401,260.64
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE REPLAC & REHAB - DISC 4R - No Added Capacity 248,339.00 310,423.75
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE REPLAC & REHAB - DISC Construction Engineering 0.00 87,354.66
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE REPLAC & REHAB - DISC Preliminary Engineering 5,591,970.00 6,989,962.50
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A BRIDGE REPLAC & REHAB - DISC Right of Way 0.00 39,591.02
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A HIGHWAY BRIDGE PROGRAM 4R - No Added Capacity 1,285,000.00 1,606,250.00
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A INTERSTATE MAINTENANCE Preliminary Engineering 31,800.00 39,750.00
Delaware S050007 Sussex >= 50,000 AND < N/A MINIMUM GUARANTEE - TEA-21 4R - No Added Capacity 3,714,840.74 4,643,550.92
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY SYSTEM Construction Engineering 33,358.74 41,698.43
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY SYSTEM Other 0.00 3,088,504.57
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM 4R - No Added Capacity 6,000,000.00 7,555,446.54
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Utilities 0.00 1,218,000.00
Delaware S050007 Sussex >= 50,000 AND < 200,000 N/A TECHNOLOGY DEPLOYMENT GRANTS T Construction Engineering 216,367.66 270,459.58