| FHWA > Asset Management > Case Studies > PMS: The Washington State Experience > PMS Applications in Engineering and Economic Analysis |
Transportation Asset Management Case Studies
|
| The international roughness index score was found to be the single best predictor of driver acceptability. |
In this study, drivers were placed in [selected vehicles in] real world driving scenarios and asked to reveal their opinions about pavement roughness. A total of 56 participants each evaluated 40 highway test segments and produced 2,180 separate "observations." Driver evaluations were collected with other data, such as speed and in-vehicle noise, and matched with driver-specific socio-demographic data and pavement-specific data from the Washington State Department of Transportation and its pavement management system.
Results from [the study] indicated that the international roughness index (IRI) is the single best predictor of driver-perceived road roughness and driver acceptability. Pavements with low IRI values generally corresponded with low roughness rankings and high levels of user acceptability. Other factors statistically associated with driver-perceived measures of road roughness included the presence of pavement maintenance, the presence of joints or bridge abutments, the age of the pavement surface, the vehicle type, levels of in-vehicle noise, the speed of vehicle, and the gender and income of the driver. 18
This example demonstrates the data mining capabilities of pavement management systems for conducting engineering analysis at both project and network level to [evaluate and understand positive and negative factors affecting] pavement performance.

WSDOT began placing Superpave designed mixes in 1996 and placed an increasing number each year (two percent in 1997 up to 47 percent in 2002), with full implementation [being] scheduled for 2004. Prior to 1996, WSDOT exclusively used the Hveem mix design procedure and AR4000W asphalt binder (conventional) on all hot-mix asphalt pavements.
A project-by-project comparison of the Superpave and conventional hot-mix asphalt projects was performed using the data contained in the WSPMS. Each Superpave project was compared to the previous overlay or construction (conventional mix) completed at the same location. The PSC, IRI, and rut depths were retrieved from WSPMS for both the Superpave and conventional mix projects at the same age. For all three pavement measures (PSC, IRI, and rutting), the project-by-project comparison was followed by the statewide comparison. 19
| Dowel-bar retrofit is considered cost effective since it is applied only to the faulted lane. |
In 1992, WSDOT constructed a test section to determine the appropriateness of dowel bar retrofit (DBR) and diamond grinding to restore the functionality of the concrete pavement as well as to provide a smooth riding surface. Due to the success of the test section, the first large-scale DBR project was constructed on Interstate 90 (Snoqualmie Pass vicinity) in 1993.
WSDOT continued to monitor this and all other sections of concrete pavement that have been retrofitted with dowel bars. Using data from the WSPMS, performance equations will be developed to relate truck volumes to faulting such that the performance life of dowel bar retrofit could be predicted. Based on the performance of the test section it is anticipated that dowel bar retrofit will extend the life of the concrete pavement by 10 to 15 years. It is estimated that over the next 20 years an additional 300 lane-miles of concrete pavement may require DBR. Since that time, WSDOT has rehabilitated over 300 miles of existing concrete pavement by dowel bar retrofitting followed by diamond grinding. The average construction costs for DBR is approximately $450,000 (2006 dollars) per lane-mile (includes all costs: PE, construction, traffic control, etc). The typical cost of a four-inch asphalt overlay, which is the minimum recommended overlay depth for rehabilitating a faulted concrete pavement, is approximately $525,000 per lane-mile (includes all costs). DBR is considered cost effective since it is only applied to the faulted lane while an asphalt overlay would be required on all lanes, shoulders, ramps, ramp tapers, etc., [significantly increasing the effective lane miles and cost for asphalt overlay.] 20
In the past, it has been difficult to assign a dollar value of the damage to pavement caused by studded tires. [With] improvements in technology, it is now possible to measure the actual amount of damage caused by studded tires on PCC pavements [and hence quantify the dollar value of damage]. [Transverse profile] measurements [conducted as part of the annual pavement condition survey] on PCC pavements indicate that the current damage due to studded tires is approximately $18.2 million (cost for removing studded tire wear by diamond grinding the concrete surface.) Over the last five years, WSDOT has constructed a number of PCC pavement test sections to determine what combination of materials could be used to help offset the damage caused by studded tires. Test section approaches have included increasing the concrete strength (making the concrete surface harder would make it more resistant to studded tires), modifying the aggregate gradation (making the aggregate gradation more uniform to minimize the smaller aggregate which is more susceptible to studded tire wear), adding the Hard-Cem product (this is a product that is typically used to harden industrial floors) and modifying the surface texture (carpet drag versus tining). 21
This is an excellent example of engineering uses of pavement management data to improve network level project scoping. The availability of the pavement management database has made it possible to develop SCOPER and to produce practical, more accurate design estimates at an early date, [when project funding needs are determined, but before project specific structural evaluations are made], to result in improved pavement design and performance within the state highway system. The initial scoping design is then available to WSDOT regional engineers as a preliminary estimate for their full design process. SCOPER estimates required overlay thickness approximately 80% of the time to produce designs within 10–15% of the final required design.
The SCOPER process uses the Asphalt Institute's component analysis method with modification to layer coefficient based on Washington characteristics [Asphalt 83; WSDOT 95a 22]. The approach requires that the total pavement structure be developed as a new design for the specified service conditions. The method takes into account pavement condition, type, and thickness of the pavement layers.
SCOPER uses a relationship between pavement structure and traffic to estimate the subgrade's stiffness. The existing structural integrity of the pavement is converted to an equivalent thickness of hot-mix asphalt, which is then subtracted from the required thickness for a new full depth hot-mix asphalt design to determine the required overlay thickness. 23
The WSPMS was used to assist pavement design engineers in selecting the proper asphalt binder grade for each individual project. The PG binder selection module [of WSPMS] accesses the project information concerning state route, milepost limits, roadway speed limit, traffic condition (free, slow, or standing) and the 15-year equivalent single-axle load (ESAL) for the selected project. The user then enters the expected overlay thickness, design ESALs, and geographical area, and the module provides recommendations for appropriate PG binder designation. 24

| << Previous | Contents | Next >> |
Nastaran Saadatmand
Office of Asset Management
202-366-1337
E-mail Nastaran