| Bridge Technology | ||
| FHWA >
Infrastructure >
Bridge >
Steel Fabrication >
Demo 102
|
||
Narrow-Gap Improved Electroslag Welding for Bridges
FHWA Demonstration Project DP-102Oregon Department of Transportation Maintenance Yard
October 13-15, 1998
OCTOBER 13, 8:00 AM -- OCTOBER 15, NOON
SESSION 1
Registration and Introductions
---Bruce Johnson, Bridge Engineer, FHWA
---Krishna Verma, Welding Engineer, FHWA
DEMONSTRATION WELD #1-(Introduction to NGI ESW)
Executive Overview
Introduction to electroslag welding
Advantages/disadvantages (compared to other processes)
Break
Development of Narrow Gap Improved ESW ( NGI-ESW)SESSION 2
Equipment Requirements
Fluxes and Filler Metal Consumable Requirements
Break
Setup and Operation
DEMONSTRATION WELD #2: (butt or transition weld)
Summary and Discussion: Day 1SESSION 3
Non Destructive Examination and Quality Assurance
Operator controls and adjustments or "What to Do if"
DEMONSTRATION Weld #3 (typical problems and real time adjustments)
Break
Weld Repair
Mechanical Properties
Distortion
DiscussionSESSION 4
RECAP: Factors Affecting Quality of NGI-ESW
Cost Comparison : NGI-ESW vs SAW
DEMONSTRATION WELD #4 (Transition or butt)
Vendor List : ESW Equipment
Specifications for NGI-ESW Proposed for Bridge Welding Code
Technical Support for NGI-ESW
Break
Workshop Summary: NGI-ESW
Questions/Discussion
Pass Out/Complete Questionnaire/Evaluation
Acknowledgments