Construction Program Management and Inspection Guide
Appendix G (continued)
 |
DIVISION OFFICE FINAL ACCEPTANCE CHECKLIST FOR FEDERAL-AID "N" PROJECTS |
| PROJECT INFORMATION |
| EA No. | | Federal-aid No. | |
| Project Description | |
| District/County/Route/KP | |
| Date Awarded | | Approval Date | |
| Time Started | | Work Started | |
| Contract Days | | Final No. Working Day | |
| Original Completion Date | | State Acceptance Date | |
| Liquidated Damages (no. of days and total $ amount) | |
| SUBMITTALS | SUBMITTED? | DATE |
| Material Certification (CM 6-1.1) | Yes | No | N/A | |
| Form FHWA-47M | Yes | No | N/A | |
| Proposed Final Estimate | Yes | No | N/A | |
| Last Statement of Working Days | Yes | No | N/A | |
| Contractor's Written Statement of Claims (Submitted Separately) | Yes | No | N/A | |
| List of CCOs | Yes | No | N/A | |
| (Approved and Pending) | Yes | No | N/A | |
| (Participating/Non-Participating) | Yes | No | N/A | |
| List of Time Extensions | Yes | No | N/A | |
| (FHWA Approved/Not Approved) | Yes | No | N/A | |
| Form CEM-2402 (F) Final Report | Yes | No | N/A | |
| Utilization of DBE | Yes | No | N/A | |
| Environmental Commitments Completed | Yes | No | N/A | |
| ADDITIONAL INFORMATION |
Labor Compliance Problems |
Any Other Changes |
(ORIGINAL: PROJECT FILE; CC: FHWA, WITH PROPOSED FINAL ESTIMATE)
|