| FHWA > Engineering > Pavements > Concrete > High Performance Concrete Pavements: Project Summary > Chapter 23 |
High Performance Concrete Pavements
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TEST CELL DESCRIPTION | SENSOR | NO. OF SENSORS |
|---|---|---|
| Jackson Street intersection: 75 mm - 1.2 m x 1.2-m panels (3 in. - 4 ft x 4-ft) Polypropylene fibers | Dynamic strain Static strain Thermocouple | 32 4 14 |
| Main Street intersection: 75 mm - 1.2 m x 1.2-m panels (3 in. - 4 ft x 4-ft) Polypropylene fibers | None | — |
| School Street intersection: 75 mm - 1.8 m x 1.8-m panels (3 in. - 6 ft x 6-ft) Polyolefin fibers | None | — |
On the Mn/Road project, a 342.9-mm (13.5-in.) full-depth asphalt pavement was whitetopped with a fiber-reinforced concrete overlay. The original asphalt pavement was constructed in 1993 on a silty-clay subgrade. The existing asphalt pavement was previously a transition zone that separated the 5- and 10-year mainline test cells. The test section was divided up into six separate test cells with various thicknesses and joint patterns. These cells were instrumented with strain, temperature and moisture sensors. A summary of the test cells is provided in Table 31.
| MnROAD TEST CELL DESCRIPTION | SENSOR | NO. OF SENSORS | |
|---|---|---|---|
| Cell 93 | 100 mm - 1.2 m x 1.2-m panels (4 in. - 4 ft x 4-ft) Polypropylene fibers | Dynamic strain Dynamic asphalt foil strain gauge Static strain Thermocouple Moisture | 32 2 8 14 12 |
| Cell 94 | 75 mm - 1.2 m x 1.2-m panels (3 in. - 4 ft x 4-ft) Polypropylene fibers | Dynamic strain | 32 |
| Cell 95 | 75 mm - 1.5 m x 1.8-m panels (3 in. - 5 ft x 6-ft) Polyolefin fibers | Dynamic strain Dynamic asphalt foil strain gauge Static strain Thermocouple Moisture | 32 2 8 12 12 |
| Cell 96 | 150 mm - 1.5 m x 1.8-m panels (6 in. - 5 ft x 6-ft) Polypropylene fibers | Dynamic strain | 32 |
| Cell 97 | 150 mm - 3 m x 3.7-m panels (6 in. - 10 ft x 12-ft) Polypropylene fibers | Dynamic strain Dynamic asphalt foil strain gauge Static strain Thermocouple Moisture | 32 2 8 16 12 |
| Cell 97b | 150 mm - 3 m x 3.7-m panels (6 in. - 10 ft x 12-ft) Polypropylene fibers Doweled | None | — |
The US 169 test sections were paved on September 17, 1997 and the I-94 test sections on October 23, 1997. All concrete was required to have an air content of 6.5 percent ± 1.5 percent and a flexural strength of 2757.9 kPa (400 lbf/in2) at 3 days so that the overlays could be opened to traffic. The flexural and compressive strengths for the concrete on US 169 are provided in Tables 32 and 33, respectively. The flexural strengths for both the polypropylene and polyolefin mixes were similar. The polypropylene concrete had slightly higher compressive strengths even though the w/c ratio for the polyolefin mix was lower. Increasing the fiber content in the polyolefin mix by 8 times that of the polypropylene mix contributed to the lower strength of the polyolefin concrete. Both mixes met the Minnesota Department of Transportation's (Mn/DOT's) flexural and compressive strength requirements.
| TIME OF STRENGTH TESTING | CONCRETE WITH POLYPROPYLENE FIBERS (JACKSON STREET INTERSECTION) (LBF/IN2) | CONCRETE WITH POLYOLEFIN FIBERS (MAIN STREET INTERSECTION) (LBF/IN2) |
|---|---|---|
| 28-day | 590 | 570 |
| TIME OF STRENGTH TESTING | CONCRETE WITH POLYPROPYLENE FIBERS (JACKSON STREET INTERSECTION) (LBF/IN2) | CONCRETE WITH POLYPROPYLENE FIBERS (SCHOOL STREET INTERSECTION) (LBF/IN2) | CONCRETE WITH POLYOLEFIN FIBERS (MAIN STREET INTERSECTION) (LBF/IN2) |
|---|---|---|---|
| 28-day | 4900 | 4900 | 4400 |
| 28-day | 5400 | 5900 | 5300 |
In addition to the material testing on the US 169 project, extensive material property testing was also performed on the concrete mixture used to construct the I-94 test sections. These material properties are summarized in Tables 34 through 36.
| TIME OF STRENGTH TESTING | CONCRETE WITH POLYPROPYLENE FIBERS (LBF/IN2) | CONCRETE WITH POLYOLEFIN FIBERS (LBF/IN2) |
|---|---|---|
| 1-day | 2000 | 1600 |
| 3-day | 3900 | 2900 |
| 7-day | 4800 | 4200 |
| 14-day | 5500 | 4800 |
| 28-day | 6100 | 5300 |
| TIME OF STRENGTH TESTING | CONCRETE WITH POLYPROPYLENE FIBERS (LBF/IN2) | CONCRETE WITH POLYOLEFIN FIBERS (LBF/IN2) |
|---|---|---|
| 7-day | 4.5 x 10-6 | 4.3 x 10-6 |
| 28-day | 4.8 x 10-6 | 4.4 x 10-6 |
| TIME OF STRENGTH TESTING | CONCRETE WITH POLYPROPYLENE FIBERS | CONCRETE WITH POLYOLEFIN FIBERS |
|---|---|---|
| 7-day | 0.19 | 0.19 |
| 28-day | 0.19 | 0.19 |
Additional information on the concrete mixture design and the construction of these test sections can be found in the report by Vandenbossche and Rettner (1998).
Climatic, static strain, and dynamic strain data are collected periodically throughout the year on the US 169 project. On the I-94 project, temperature, moisture, and static strain data were collected every 15 minutes since construction. Dynamic strain data were collected for both static and dynamic truckloads and in conjunction with FWD testing four times per year, once during each season. Distress, ride, and faulting data were also collected four times per year.
Distinct cracking patterns developed within each test section. The UTW test sections with a 1.22-m x 1.22-m (4-ft x 4-ft) joint pattern contained corner breaks and transverse cracks. The corner breaks occurred primarily along the inside longitudinal joint and the lane/shoulder (L/S) longitudinal joint while the transverse cracks developed in the panels adjacent to the shoulder. The transverse cracks typically develop approximately 1/3 of the length of the panel away from the transverse joint. The test section with the 1.83-m x 1.83-m (6-ft x 6-ft) joint pattern performed significantly better because the longitudinal joint does not lie in the inside wheelpath. This significantly reduces the edge and corner stresses. Very tight longitudinal cracks developed on the 152.4-mm (6-in.) overlay with a 1.83-m x 1.83-m (6-ft x 6-ft) joint pattern on I-94. Reflective cracking was not observed in any of the test sections, although reflective cracking has been found to occur in UTW placed on thicker HMA pavements, such as on I-94 (Vandenbossche 2003).
The strains measured on I-94 were consistently lower than those on US 169, even when measurements were made at higher HMA temperatures. The reduction in strain is a result of the increase in thickness and quality of the HMA on I-94 and an increase in the bond strength between the two layers. Increases in the temperature of the HMA also produce much smaller increases in strain on I-94 compared to US 169, except for the strains measured at mid-panel. Strains at mid-panel on the I-94 project approach those measured at mid-panel on the US 169 project. It was found that applying a load when the HMA temperature is high produces similar strains in the UTW regardless of the thickness of the HMA layer when a good bond is obtained (Vandenbossche 2003).
The strain measurements emphasize the importance of the support provided by the HMA layer. A reduction in this support occurs when the temperature of the HMA is increased or when the HMA begins to ravel. The results from the strain measurements and the cores pulled from the test section indicate the HMA ravels at a faster rate along the joints where there is greater access for the water to enter the pavement structure. The lane-shoulder joint is the most difficult to keep sealed and therefore the HMA along this joint was found to be more susceptible to stripping/raveling. Consideration should be given to sealing this joint to limit the water coming into contact with the HMA layer (Vandenbossche 2003).
Repairs were made on three of the six Mn/ROAD test sections on June 20, 2001, after over 4.7 million ESALs. The repairs were made to 13 different areas in the ultrathin whitetopping test sections. In the section with a 3-in overlay and 5-ft by 5-ft joint spacing, four panels were repaired (two locations). Eighteen panels were repaired (six locations) in the section with a 3-in overlay and 4-ft by 4-ft joint spacing. Nineteen panels were repaired (five locations) in the section with a 4-in overlay and 4-ft by 4-ft panels. A detailed description on the repair techniques used was provided by Vandenbossche and Fagerness (2002).
The test sections on US 169 were in service between September 1997 and September 1999. During that period, the sections accumulated approximately 670,000 equivalent single-axle loads (assuming a 152.4-mm (6-in.) portland cement concrete pavement and a terminal serviceability of 2.5). Additional information on the performance of these test sections can be found in the report by Vandenbossche (2002).
Three of the test sections on I-94 will be reconstructed in the summer of 2004. The new test sections will consist of a 127-mm (5-in.) and a 101.6-mm (4-in.) overlay with 1.52-m x 1.83-m (5-ft x 6-ft) panels. Half of each section will have sealed joints and the joints in the other half of each test section will remain unsealed. The monitoring activities will be similar to that for the original whitetopping test sections. The new test sections will be instrumented with temperature, moisture, and static and dynamic strain gauges.
Thomas Burnham
1400 Gervais Ave.
Maplewood, MN 55109
(651) 779-5606
Tom.Burnham@dot.state.mn.us
Vandenbossche, J. M. 2003. "Performance Analysis of Ultra-thin WhitetoppingIntersections on US-169." Transportation Research Record 1823. Transportation Research Board, Washington, DC.
---. 2002. The Construction and Performance of Ultra-thin Whitetopping Intersections on US-169. Final Report. Minnesota Department of Transportation, St. Paul.
Vandenbossche, J. M., and A. J. Fagerness. 2002. "Performance, Analysis and Repair of Ultra-thin and Thin Whitetopping at Mn/ROAD." Transportation Research Record 1809. Transportation Research Board, Washington, DC.
Vandenbossche, J. M., and D. L. Rettner. 1999. "One-Year Performance Summary of Whitetopping Test Sections at the Mn/ROAD Test Facility." Proceedings, International Conference on Accelerated Pavement Testing, Reno, NV.
---. 1998. The Construction of US-169 and I-94 Experimental Whitetopping Test Sections in Minnesota. Minnesota Department of Transportation, St. Paul.
| << Previous | Contents | Next >> |
Sam Tyson
Office of Asset Management, Pavement, and Construction
202-366-1326
E-mail Sam