Development and Implementation of a Performance-Related Specification for SR 9a, Florida: Final Report

Appendix A: Pavespec Inputs

Table A-1. Key Inputs to the PaveSpec 3.0 PRS Software
Input Value Source
Design
Design Life 20 years FL Design Manual
Pavement Type JPC Plans
Dowel Bar Diameter 1.25 in. FL Design
Transverse Joint Spacing 16 ft FL Design
PCC Modulus of Elasticity 4 x 106 lbf/in2 FL Design Manual
Transverse Joint Sealant Type Silicone FDOT
Modulus of Subgrade Reaction (k-value) 200 lbf/in2/in FDOT
Water-Cement Ratio 0.42 FDOT's current specs: max w/c = 0.5
Percent Subgrade Material Passing #200 14% (Range: 1% to 56%) FDOT
Base Permeability Somewhat Permeable FDOT
Base Thickness 48 in. FDOT
Base Modulus of Elasticity 30,000 lbf/in2 Project Team
PCC-Base Interface Unbonded Project Team
Base Erodibility Factor (1=ctb, 5=granular) 4 Project Team
Traffic
Specify Traffic for Year: 1 Plans
ADT (both directions) in Traffic Year: 28,500 Plans
ESAL Growth Rate 2.4% Plans
ESAL Growth Type Compound Project Team
Traffic Directional Factor 58% Plans
Percent Trucks 14% Plans
Percent Trucks in Outer Lane 65% FL Des Manual
Average Truck Load Equivalency Factor 1.67 ESALs/truck FL Des Manual
Climate
Average Annual Freezing Index 0°F-days DataPave
Average Annual Precipitation 51.2 in. DataPave
Average Annual Air Freeze-Thaw Cycles 18 LTPP/RPPR data
Average Annual No. of Days > 90°F 57 DataPave
Climate Zone Wet-Nonfreeze DataPave
Unit Costs
Transverse Joint Sealing $1.20 per ft Project Team
Longitudinal Joint Sealing $1.00 per ft Project Team
Transverse Crack Sealing $1.00 per ft Project Team
Local, Full-depth Repairs of Transverse Joints NA NA
Local, Partial-depth Repairs of Transverse Joints $50.00/yd2 Project Team
Local, Full Slab Replacements $137.76/yd2 Florida Cost Data
Local, Partial Slab Replacements N/A N/A
Global, AC overlay $11.00/yd2 Project Team
Global, PCC overlay N/A N/A
Global, Diamond grinding $3.01/yd2 Florida Cost Data
User Cost, % 5% Project Team
Basic Specification Information
Project Name 9A (I-295) Plans
Specification Level Level 1 PRS only Project Team
State Florida Plans
County Duval Plans
Project ID 209600-1-52-01 Plans
Traffic Direction EB and WB Plans
Dimensions and Lane Configuration
Lane Configuration Six, Divided Plans
Lane 1 (outer) Width 14 ft Plans
Lane 2 Width 12 ft Plans
Lane 3 Width 12 ft Plans
Shoulder Type Tied PCC Plans
Stress Load Transfer Efficiency 5% Project Team
Inner Lane Cracking is X% of Outer Lane Cracking 10% Project Team
Road Location Urban Plans
Starting Station 127+00 Plans
Ending Station 207+00 (Used 198+05.75) Plans
Definition of Pavement Performance
Predict Transverse Joint Faulting? Yes Project Team
Predict Transverse Joint Spalling? Yes Project Team
Predict Transverse Slab Cracking? Yes Project Team
Predict Decreasing Smoothness? Yes Project Team
Sample Concrete Strength for AQC? Yes Florida
Sample Slab Thickness for AQC? Yes Florida
Sample Air Content for AQC? No Florida
Sample Initial Smoothness for AQC? Yes Florida
Sample Percent Consolidation Around Dowels for AQC? No Florida
AQC Sampling and Testing
Strength, Sampling Method Cylinders Florida Existing Specifications
Strength, Timing of Cores (N/A for Cylinders) Florida Existing Specifications
Strength, Number of Samples Per Sublot 1 Florida Existing Specifications
Strength, Number of Replicates per Sample 2 Florida Existing Specifications
Strength, Target Timing of Testing 28 days Florida Existing Specifications
Thickness, Sampling Method Independent Cores Florida Existing Specifications
Thickness, Timing of Samples 3 days Project Team
Thickness, Number of Samples Per Sublot 2 Florida PRS
Thickness, Number of Replicates per Sample 1 Florida PRS
Initial Smoothness, Indicator Profile Index (0.2-in. blanking band) Florida Existing Specifications
Initial Smoothness, No. of Pass Locations Per Sublot 3 Florida PRS
Initial Smoothness, No. of Replicates Per Pass Location 2 Florida PRS
Initial Smoothness, Profilograph Reduction Method Manual Project Team
Consolidation, Timing of Samples NA NA
Consolidation, No. of Samples Per Sublot NA NA
Consolidation, No. of Replicates Per Sample NA NA
AQC As-Designed Target Value Definition
Determine target LCC by Estimate LCC through Simulation Project Team
Concrete Strength, Sampling Method Distribution Project Team
Concrete Strength, Mean 4,500 lbf/in2 Historic Data
Concrete Strength, Standard Deviation 610 lbf/in2 Historic Data
Slab Thickness, Sampling Method Distribution Project Team
Slab Thickness, Mean 12.5 in. Plans
Slab Thickness, Standard Deviation 0.5 in. Historic Data
Initial Smoothness, Sampling Method Distribution Project Team
Initial Smoothness, Mean 3.0 in./mi Florida Existing Specifications
Initial Smoothness, Standard Deviation 1.0 in./mi Historic Data
% Consolidation Around Dowels, Sampling Method NA Not Applicable
% Consolidation Around Dowels, Mean NA Not Applicable
% Consolidation Around Dowels, Standard Deviation NA Not Applicable
Simulation Control
Number of Lots to Simulate at Each Factorial Point 1,500 Project Team
Minimum No. of Sublots per Lot to Simulate 3 Florida PRS
Maximum No. of Sublots per Lot to Simulate 3 Florida PRS
Average Bid Price $30.00/yd2 Estimated
Analysis Period 40 years Project Team
Table A-. Maintenance and Rehabilitation Strategy
Maintenance Plan Summary
Transverse Joint Sealing Seal 50% of transverse joints every 20 years.
Longitudinal Joint Sealing Seal 50% of longitudinal joints every 20 years.
Transverse Crack Sealing Seal 100% of transverse cracks every 20 years.
Localized Rehabilitation Plan Summary
1. If lot average percent cracked slabs exceeds 10.00%, then apply full slab replacements to 100% of cracked slabs.
2. If lot average percent spalled joints exceeds 10.00%, then apply partial-depth repairs to 100% of spalled joints.
3. If cumulative percent cracked slabs exceeds 15.00%, then consider the sublot failed.
4. If cumulative percent spalled joints exceeds 30.00%, then consider the sublot failed.
5. If average transverse joint faulting exceeds 0.1000 in., then consider the sublot failed.
6. If IRI exceeds 150 in/mi, then consider the sublot failed.
7. If percent failed sublots exceeds 25%, then begin global rehab scenario 1 and STOP for this year.
Global Rehabilitation Summary
Prior to First Phase Repair 100% of outstanding spalled joints with partial-depth repairs. Repair 100% of outstanding cracked slabs with full slab replacements.
Phase1 Diamond Grinding; Assumed Life; 10 years; Starting IRI: 60in/mi; Ending IRI: 150 in/mi.
Phase 2 AC Overlay; Assumed Life: 10 years; Starting IRI: 60in/mi; Ending IRI: 150 in/mi.
Phase 3 AC Overlay; Assumed Life: 10 years; Starting IRI: 60 in/mi: Ending IRI: 150 in/mi.
Phase 4 AC Overlay; Assumed Life: 10 years; Starting IRI: 60 in/mi; Ending IRI: 150 in/mi.