Skip to contentUnited States Department of Transportation - Federal Highway AdministrationSearch FHWAFeedback

Pavements

<<PreviousContentsNext>>

CPTP Status Report - Task 65 Engineering ETG Review Copy

Appendix B - CPTP Project Details


Task 9 (00) - Influence of Sealing Transverse Contraction Joints on the Performance of Concrete Pavements

Contracting Dates: March 2003 to March 2006
Contract Amount: $528,748 (FHWA share = $397,948/ ProTech share = $130,800)
Contractor: ProTech Engineering, Inc.
Principal Investigator: Kathleen T. Hall
FHWA Contract Manager: Jim Sherwood

Project Goals/Objectives: The goals of this project are to 1) evaluate the effect on long-term performance of unsealed transverse joints in concrete pavements with different pavement cross-sections and slab dimensions, traffic levels, and climatic conditions, 2) evaluate the effect of different transverse joint sealant materials and configurations on the long-term performance of concrete pavement in various climatic regions, and 3), determine the cost-effectiveness of sealing transverse contraction joints for different pavement designs and materials over a range of climatic zones and traffic levels.

Background: Currently, 96 percent of the state highway agencies require transverse joint sealing, adding about 2 to 7 percent to the initial construction cost of their pavements and even more when considering resealing activities and life-cycle cost analysis. If the use of narrow, unsealed joints on short jointed concrete pavements can provide equally long-term pavement performance as sealed joints, states can save millions of dollars in construction and maintenance costs by eliminating joint sealing on those projects. Reduction in traffic delays during sealant maintenance and increases in worker safety are possible benefits from the elimination of sealants where they are not found cost-effective.

Status: The contract for this project was awarded in March 2003. In the first quarter, a report was produced: Review of Literature on Concrete Pavement Joint Sealing Practices, Performance, and Cost-Effectiveness which covered 51 references. The references mostly cover joint sealing in concrete pavements at original construction, although there is some mention of resealing. Work was planned for the quarter recently completed, on subtask 2, to survey opinions and experiences. As the subtask 1 literature review yielded little detail on the cost specifics, and since these costs would be out of date anyway, a particular effort in subtask 2 was planned to obtain joint sealing cost data from contractors and material and equipment suppliers. Work is currently being conducted on a field data collection plan, with a preliminary field testing program being conducted in Phoenix in February 2004 and the bulk of the field work being conducted in early summer 2004.

Available Reports/Articles/Presentations:

FHWA RFP Objectives, Scope of Work and Proposed Work Plan; Contractor's Work Plan

Other Related Reports/Articles/Presentations/Studies:

LTPP Data Analysis: Relative Performance of Jointed Plain Concrete Pavement with Sealed and Unsealed Joints. Prepared by Kathleen T. Hall and James A. Crovetti, December 2000.

Hall, K.T., C.E. Correa, and A.L. Simpson, 2003, Performance of Rigid Pavement Rehabilitation Treatments in the Long-Term Pavement Performance SPS-6 Experiment, Transportation Research Record 1823, Transportation Research Board, Washington, DC.

Hall, K.T., L.D. Evans, J.A. Crovetti, C.E. Correa, and L. Scofield, 2000, Performance of Arizona's SPS-4 Joint Sealing Environment, Proceedings, Seventh International Conference on Concrete Pavements, International Society for Concrete Pavements, College Station, TX.

HPCP Summary Report, FHWA-IF-02-026, March 2002, includes two Illinois projects and one Ohio project containing unsealed joints.

Task 10 (00) - Revision of ISLAB 2000 for Subbase/Pavement Interaction

Contracting Dates: June 2000 to September 2001
Contract Amount/IPRF Contract: $40,000
Contractor: ERES Consultants
Principal Investigator: Lev Khazanovich
IPRF Contract Manager: Steven Waalkes

Project Goals/Objectives: Revise the ISLAB 2000 analysis program to account for interaction between the concrete slab and the underlying layer.

Background: One of the main drawbacks of many finite element programs is their ability to adequately model the interface condition between the PCC slab and the underlying layer. The existing finite element programs for pavement analysis assume either zero or full bond (no slippage) for the interface condition. In reality, the amount of layer slippage under a heavy wheel load is somewhere between these two extremes. Having a capability to model and specify the varying levels of slippage between the slab and an underlying layer would greatly improve our ability to fine tune concrete pavement design.

Status: An appropriate mathematical model has been identified, involving a 40 degree-of-freedom stiffness element to address layer interaction. The ISLAB-2000 computer code has been modified to include the layer interface model. The ISLAB-2000 graphical user interface (GUI) has been modified to allow the user to enter new structural model parameters (friction parameters, horizontal joint stiffness, horizontal restraint).

The Users Guide and installation CD were delivered to IPRF on Aug. 14, 2002. The project has been invoiced to the extent of budget by contractor. Work on this project was suspended in June 2002 per direction of IPRF. No further activity or deliverable is expected.

Available Reports/Articles/Presentations:

IPRF RFP Objectives, Scope of Work and Proposed Work Plan; Contractor's Work Plan

Task 11 (00) - Workshops on Concrete Pavement Technology for State DOT Pavement Engineers

Contracting Dates:

  • June 2000 for 2000 Workshop for DOT pavement engineers. 2000 Workshop held on August 10-11
  • April 2001 for 2001 Workshop for DOT pavement engineers. 2001 Workshop held June 28-29
  • April 2001 for 2001 Professor's Seminar. 2001 Professor's Seminar held June 18-20, 2001

Duration: Annual State DOT Workshops for 4 years. Professor's Seminar in 2001
Contract Amount/IPRF Contract: $60,000 in FY00, $105,000 in FY01
Contractor: American Concrete Pavement Association
Principal Investigators: Larry Cole and Jerry Voigt
IPRF Contract Manager: Daniel Frentress

Project Goals/Objectives: Conduct two-day workshops on current concrete pavement technology for state DOT engineers.

Background: Improvements to the design, construction, rehabilitation, and asset management of concrete pavements will only be made when technological advances are put into use. State Departments of Transportation are the primary agents for such advancement as they are responsible for building and maintaining the large majority of highways in the U.S. Therefore, it is essential for key state DOT engineers to become familiar with new concrete pavement technology. One effective method for transferring technology is through workshops. Workshops are effective when leading authorities present new technology, followed by ample time for participants to share experiences and viewpoints. However, this format is only effective in changing DOT practices when key state DOT staff members are participants. It is important that the right representatives from the state DOTs, as well as pavement experts from the FHWA Regional Resource Centers, participate.

Additionally, college professors of civil engineering can educate students on new technology. University professors, who teach pavement technology, are invited for updates on the latest advances in concrete pavements, including products and findings from the Concrete Pavement Technology Program.

Status: The first state DOT workshop, entitled "Concrete Pavement Design - 2000 and Beyond" was held August 10-11, 2000, in Breckenridge, Colorado. Many positive comments were received from participants regarding the workshop's format, discussion topics, and quality of presentations. The second state DOT workshop was held in San Francisco, CA on June 28-29, 2001. The 2001 Professor's Workshop took place on June 18-20, 2001 in Skokie, IL.

No further activity is anticipated. The ACPA has been conducting Professor Workshops annually since 2002.

Available Reports/Articles/Presentations:

IPRF RFP Objectives, Scope of Work and Proposed Work Plan; Contractor's Work Plan

Conference presentations CDs are available.

Task 12 (00) - Develop a Plan to Investigate the Impacts of Pavement Cracking on Long-Term Performance

Contracting Dates: October 2000 to November 2000
Contract Amount/IPRF Contract: $10,000 Total ($5,000 to two Contractors)
Contractor: Construction Technology Laboratories, Inc. and ERES Consultants
Principal Investigator: Shiraz Tayabji (CTL) and Michael Darter (ERES)
IPRF Contract Manager: Gerald Voigt

Project Goals/Objectives: Conduct a thorough literature search and compile a summary report of the impacts of pavement cracking on long-term concrete pavement. Prepare a research plan to address the impacts of pavement cracking on long-term performance.

Background: Uncontrolled cracking in concrete pavements can be the result of many factors. While such cracking is undesirable, the long-term effects on pavement performance and durability are not clear. Key questions include: What type of cracks affect pavement performance and durability? How does cracking affect performance of pavements built on different bases? How many cracks can be tolerated without significantly affecting ride quality? When is crack repair or slab replacement needed?

Status: The feasibility studies were completed and both concluded that enough information was available to determine the potential for success of a study of the impact of cracking on pavement performance. This task is now complete.

Available Reports/Articles/Presentations:

IPRF RFP Objectives, Scope of Work and Proposed Work Plan; Contractor's Work Plan.

ERES Proposed Research Plan, December 2000

CTL Proposed Research Plan, December 2000

Task 13 (00) - Determine Actual Pavement Life Cycle Costs

Contracting Dates: August 2000 to January 2002
Contract Amount/IPRF Contract: $180,000
Contractor: ERES Consultants
Principal Investigator: Michael Darter
IPRF Contract Manager: Steven Waalkes

Project Goals/Objectives: Conduct comprehensive life cycle cost analyses for three specific highway sections, and prepare and distribute reports disclosing the results.

Background: Many state DOTs have developed life cycle cost analysis models, and frequently conduct such analyses as part of a pavement type selection process. The FHWA has provided some additional guidance on the use and application of life cycle costing, particularly in the area of probabilistic modeling procedures. Unfortunately, very rarely do agencies ever determine actual life cycle cost data from existing projects to assess the reasonableness of their approach or assumptions.

Status: This was a 100% industry funded project. Life cycle cost studies were completed in Tennessee, Utah, and Oklahoma. Individual reports/flyers have been produced for distribution by ACPA.

Available Reports/Articles/Presentations:

A Comparison of Pavement Performance and Costs, Interstate 40, Tennessee. ACPA Special Report SR991P. 2000.

A Comparison of Pavement Performance and Costs, Interstate 15, Utah. ACPA Special Report SR992P. 2000.

A Comparison of Pavement Performance and Costs, Interstate 40, Oklahoma. ACPA Special Report SR993P. 2001.

Other Related Reports/Articles/Presentations/Studies:

A Comparison of Pavement Performance and Costs, Interstate 985 and State Rout 400, Georgia. ACPA Special Report SR994P. 2003.

Gharaibeh, N.G. and M.I. Darter, 2001, Benefits and Costs of Jointed Plain Concrete Pavement Design Features, Transportation Research Record 1778, Transportation Research Board, Washington, DC.

Task 14 (00) - AURORA 2000 Pavement System Analysis Tool

Contracting Dates: October 1997 to June 2002
Contract Amount/IPRF Contract: $2,610,000
Contractor: Transtec Group, Inc.
Principal Investigator: Robert Rasmussen
IPRF Contract Manager: Larry Cole

Project Goals/Objectives: Develop a set of system analysis tools for pavements

Background: The work was initiated in 1997 to develop a state-of-the-art, mechanistic pavement design selection and evaluation system. During the course of the work, it has evolved into a system of tools which address planning, design, construction, and economics and packages these tools in a common, user-friendly Windows interface

Status: As the result of a technical review by the project panel, the final deliverables were submitted on September 29, 2000. Software was demonstrated to federal and state DOT and industry representatives at San Francisco Technology Transfer Workshop on June 28-29, 2001. Project is complete.

Contract to perform independent evaluation of Aurora 2000 has been awarded (during Fall 2003) to Quality Engineering Solution. Completion of the independent evaluation is expected in January 2004.

Available Reports/Articles/Presentations:

No reports or other products are available for public release.

Task 15 (01) - Long-Term Plan for Concrete Pavement Research and Technology

Contracting Dates:
IPRF Contract: June 2001 to June 2002
FHWA Contract: February 2003 to mid-2004

Contract Amount:
IPRF Contract: $220,831
FHWA Contract: $413,471 plus industry match of $103,373

Contractor: Iowa State University
Principal Investigator: Ted Ferragut
FHWA Contract Manager: Jim Sherwood

Project Goals/Objectives: Develop a Long-Term Plan and to develop an Action Plan to implement the Long-Term Plan

Background: Task 15 was originally conceived and initiated to address the need for focus and direction in Concrete Pavement Technology Program activities beyond the current work and resources. The Long-Term Plan being developed through this endeavor will chart a path from the current state-of-the-practice to a new generation of concrete pavements. It is intended to guide concrete pavement research, development and technology activities both within and outside of the Concrete Pavement Technology Program, and FHWA's post-TEA-21 Infrastructure Technology Program.

Status: Work on this project resumed (under a new cooperative agreement) in March 2003. The contractor's updated work plan was discussed at a meeting with the project technical panel in early July, and has been revised based on their input. The most significant change recommended by the panel is the addition of a by-invitation "summit" to the planned outreach effort. The project team is striving to complete the plan well in advance of the contract end date, such that the scheduled delivery date for the project deliverables is January 2004. An in-depth discussion of this project is planned for the October 6-7 meeting.

Available Reports/Articles/Presentations:

IPRF RFP Objectives, Scope of Work and Proposed Work Plan; Contractor's Work Plan

FHWA RFP Objectives, Scope of Work and Proposed Work Plan; Contractor's Work Plan

4th Outreach Info

  • 4th Outreach Workshop Flyer - November 11, 2003
  • 4th Outreach Program Welcome
  • 4th Outreach Workshop Agenda
  • Task 15 Research Plan Development Process
  • Task 15 Long Range Concrete Pavement Research Plan - Working "Flag" Copy - Product Summary Table - October 12, 2003
  • Concrete Pavement Technology Long Range Plan Handouts - November 11, 2003
  • Email regarding 4th Outreach Workshop dated November 6, 2003.

Concrete Pavement Technology Long Term Research and Technology Plan - FHWA, ACPA, and AASHTO - Official "Flag" version 1.1.

Power Point presentation - Long Term Planning and Implementation Concrete Pavement Technology - MCC Outreach Meeting - October 2003.

Power Point presentation - Long Term Planning and Implementation Concrete Pavement Technology - TRB CRICP Meeting - October 2003.

Concrete Pavement Technology Long Term Research and Technology Plan - FHWA, ACPA, and AASHTO - Official "Flag" version 2.0.

Top 10 Major Technology Tracks - Draft "Flag" Copy Addendum

Ferragut, T.R., D. Harrington, and M. Brink, 2002, Road Map to the Future, Public Roads, Volume 66, No. 1, Federal Highway Administration, Washington, DC.

Task 16 (01) - Smoothness Criteria for Concrete Pavements

Contracting Dates: Start Date April 2003 - 30 month duration project
Contract Amount/FHWA Contract: $500,000
Contractor: Soil and Materials Engineers, Inc.
Principal Investigator: Starr Kohn
FHWA Contract Manager: Mark Swanlund

Project Goals/Objectives: To determine what profile characteristics are objectionable, how to measure them, what causes them, and how to avoid creating them; specifically to:

  1. Determine the limits and value of smoothness specifications for concrete pavement.
  2. Determine a method to identify and correct localized roughness features in concrete pavement

Background: Research has shown that concrete pavements built smooth initially stay smooth longer than pavements built rough initially. To provide smoother pavements, many agencies utilize incentive and disincentive provisions in their construction contracts. These provisions provide a financial incentive to contractors who exceed the require pavement smoothness while penalizing contractors who build a pavement rougher than specified. Forty-five of 52 State Highway Agencies (SHAs) utilize specifications for pavement smoothness for construction acceptance for concrete pavement. Of the SHA's using smoothness specifications for concrete pavements most currently use a profilograph or other response-type roughness meter. However, there is growing trend to change the measurement device to inertial profiler and to more advanced roughness indices (International Roughness Index, IRI). AASHTO is currently considering adoption of a Provisional Standard for Pavement Smoothness based upon inertial profilers and IRI.

While there is substantial experience with inertial profilers and IRI for pavement management, the use of inertial profilers and IRI as a construction quality control and quality assurance device is relatively new. There are aspects of using inertial profilers and IRI for quality control and acceptance of concrete pavement that require a more thorough understanding before improved pavement smoothness specifications can be implemented on a widespread basis.

Status: Work in progress. The initial meeting of the Technical Advisory Panel was held in June 2003.

Available Reports/Articles/Presentations:

FHWA RFP Objectives, Scope of Work and Proposed Work Plan; Contractor's Work Plan

Power Point presentation - Smoothness Criteria for Concrete Pavements. Presentation given by Starr Kohn, SME, October 6-7, 2003 in Woods Hole, MA.

Smoothness Criteria for Concrete Pavements - Soil and Materials Engineers, University of Michigan Transportation Research Center, and APR Consultants.

Smoothness Criteria for Concrete Pavements Literature Review - SME, UMTRI, and APR, June 13, 2003.

Other Related Reports/Articles/Presentations/Studies:

CD-ROM Proceedings, Fourth Annual Pavement/Materials and Testing Workshop, FHWA Office of Pavement Technology and Office of Infrastructure Research and Development, Pavement Smoothness, Friction, Tire/Pavement Noise, and Texturing, Arlington, VA, December 9-11, 2003.

TPF-5(063), Improving the quality of Profiler Measurement, LTPP related pooled funds study.

Karamihas, S.M., R.W. Perera, T.D. Gillespie, and S.D. Kohn, 2001, Diurnal Changes in Profile of Eleven Jointed PCC Pavements, Proceedings, Seventh International Conference on Concrete Pavements, International Society for Concrete Pavements, College Station, TX.

Perera, R.W. and S.D. Kohn, 2002, Issues in Pavement Smoothness: A Summary Report, NCHRP Project 20-51(1), Transportation Research Board, Washington, DC.

Perera, R.W. and S.D. Kohn, 2001, LTPP Data Analysis: Factors Affecting Pavement Smoothness, NCHRP Project 20-50(8/13), Transportation Research Board, Washington, DC.

Task 51 (99) - Mobile Concrete Laboratory

Contracting Dates: Start date October 1, 2002 - 3-year contract plus 2 option years
Contract Amount: $1.9 million, including travel costs for 3 years
Contractor: SaLUT, Inc.
Principal Investigators: Jon Mullarky and Leif Wathne
FHWA Contract Manager: Gary Crawford

Project Goals/Objectives: Introduce Federal, State, and local transportation personnel to state-of-the-art concrete technology for materials selection and mixture design, as well as for field and laboratory testing.

Background: Transferring new technology to highway construction agencies and contractors is often a slow process. The Mobile Concrete Laboratory (MCL), initiated by FHWA, attempts to shorten the acceptance time for new technologies and research through further refinement of these technologies. In many cases, the technologies are validated in the field on actual projects, results are documented, and recommendations are made to the participating agency and the researcher. New technologies are also introduced to state highway agencies (SHA's) and industry through demonstrations at the job site, equipment exhibitions at events attended by decision makers, teaching personnel how the new technology can be used, and publishing articles on the results of the MCL activities.

Status: During FY 2003, MCL has provided services to the LTPP program to evaluate the use of the impact-echo technique on existing concrete pavements to measure thickness in lieu of taking destructive cores. MCL has eight ongoing equipment loans to highway agencies evaluating these new technologies. The laboratory was on display at the Concrete Paving Conference in Austin, TX. The MCL staff also arranged and made technical presentations at an Admixture Workshop for New Jersey DOT, a High-Volume Fly Ash Workshop for Colorado DOT, and a Mixture Design Workshop at the Fourth Annual Pennsylvania Concrete Seminar. Technical presentations were made at the Texas Concrete Pavement Workshop; the Self-Consolidating Conference in Chicago, IL; the ACPA First Annual Concrete Pavement Conference in Albany, NY; and the SCAN Conference in Raleigh, NC.

At this time, MCL is committed to FY 2003 projects in Florida and continued work in Pennsylvania. Requests have been received for MCL participation in field projects in California, Indiana, Iowa, Utah and North Carolina.

Available Reports/Articles/Presentations:

FHWA RFP Objectives, Scope of Work and Proposed Work Plan; Contractor's Work Plan
FHWA Mobile Concrete Laboratory Flyer, FWA-IF-00-028 - August 2000.

Mobile Concrete Laboratory Project Reports - 9902 CA - Use of Fast-Setting Hydraulic Cement Concrete for Interstate Concrete Pavement Rehabilitation, I-10, Pomona, California Revised Field Test Report, date unknown.

Mobile Concrete Laboratory Project Reports - 9903 SD - I-94 Pavement Replacement - Richardton, North Dakota, Summer, 1999, Summary Report, date unknown.

Mobile Concrete Laboratory Project Reports - 9904 SD - Tensile Bond Strength of a High Performance Concrete Bridge Deck Overlay - I-90, Sturgis, South Dakota, Summer, 1999, date unknown.

Mobile Concrete Laboratory Project Reports - 0005 NE - Summary report 0005, US 275, Valley, Nebraska, Fall 2000, date unknown.

Mobile Concrete Laboratory Project Reports - 0202 - Woodrow Wilson Bridge Foundation Concrete Thermal Modeling, date unknown.

Mobile Concrete Laboratory Project Reports - 0204 - Summary Report, Kernville Viaduct HPC Deck Concrete, Johnstown, PA, Summer 2002, date unknown.

Mobile Concrete Laboratory Project Reports - 0205 - US 23, Future I-26 New Interstate Concrete Paving Madison County, North Carolina, Summer, 2002, date unknown.

Mobile Concrete Laboratory Project Reports - 0207 AZ - LTPP Impact-Echo Thickness Determinations I-10, Maricopa County, Arizona, Summary Report, December 2002.

FHWA Mobile Concrete Laboratory - Transferring Advanced Concrete Technology to Our Partners, date unknown.
Mobile Concrete Library - List of: Peer Review Papers, Journal Articles, and Presentations.

Crawford, G.L., L. Wathne, and J.I. Mullarky, 2002, On the Road Testing Roads, Public Roads, Volume 66, No. 1, Federal Highway Administration, Washington, DC.

Task 52 (98) - Quality Concrete Rehabilitation and Preservation (SP-205)

Contracting Dates: Started in 1997 - Ongoing
Contract Amount: $300,000
Contractor: State Departments of Transportation
FHWA Contract Manager: Sam Tyson

Project Goals/Objectives: Special Project 205 will develop guidance on concrete pavement rehabilitation and repair techniques as well as strategies that emphasizes the do's and don't's, and why and when for CPR and preventive maintenance of concrete pavements. The following repair techniques were covered: Full-depth repairs, Partial-depth repairs, Retrofit load transfer, Grooving and grinding, Subsealing, and Joint Resealing.

Background: SP-205 will evaluate the effect of timing on the performance of maintenance and non-overlay rehabilitation strategies. Also the performance of the individual rehabilitation and maintenance strategies for Portland cement concrete pavements will be studied and documented. The last major FHWA effort on concrete pavement rehabilitation was in the mid 1980's. It is time to re-examine the performance of CPR techniques available and to evaluate the influence of new equipment and materials on cost effectiveness of the repairs and maintenance.

Status: Field demonstration project were constructed in MN (Retrofit load transfer), OR (removing ruts due to studded tire wear), WI (partial depth repair), and OK (monolithic bonded overlay and dowel bar retrofit). Only the OR construction report has been received. The field reviews have been completed. The final report needs to be prepared.

Available Reports/Articles/Presentations:

FHWA RFP Objectives, Scope of Work and Proposed Work Plan; State DOT Work Plans

Hunt, L., 1999, Millabrading Test Evaluation: Norwood Road - M.P. 287.02 (Southbound Interstate 5), Construction Report, Report No. FHWA-OR-RD-00-02, Oregon Department of Transportation, Salem, OR.

Burwell, Brent and John Benson, Contractor combines retrofit and overlay to take time and cost off project, ( I-40 in Sequoyah County, OK), Roads and Bridges, April 2002.

Correa, Angel, CD-ROM of pictures taken during SP-205 field reviews.

Correa, Angel, PowerPoint presentation, SP-205, Quality CPR, to AASHTO, (MI, MN, SD, and GA field reviews).

SP-205 Work Plan, October 23, 1996 and draft RFP to prepare the final report for SP 205 (never awarded).Note: Draft RFP proposes Implementation Package to include final report and technical briefs (on the six techniques) in paper copy and electronic format, one-hour PowerPoint presentation, and develop workshop presentation materials and conduct a train the trainer workshop.

FHWA has produced updated Technical Bulletin's on Full and Partial Depth Patching based in part on field reviews.

Contract underway to QES to update Retrofit Load Transfer guidelines.

NHI Course 131062, PCC Pavement Evaluation and Rehabilitation, FHWA, October 2001. (CD-ROM containing presentations, Instructor's Guide, Reference Manual, and Participant's Workbook available)- Contains information on additional CPR techniques.

NHI 131103,(PM-3), Design and Construction of Quality Preventive Maintenance Treatments, (Course material now being finalized- same techniques being addressed as in SP-205-Available in 2004).

Pavement Preservation Compendium, FHWA-IF-03-21, FHWA, September 2003.

Highway Infrastructure Preservation, TR News Number 228, September-October 2003.

Larson, R.M., D. Petersen, and A. Correa, 1998, Retrofit Load Transfer: Special Demonstration Project SP - 204, Report No. FHWA-SA-98-047, Federal Highway Administration, Washington, DC. Note: Join Technical Bulletin with ACPA, Video (Fit to be Tied), and brochure also available.

Task 53 (98) - High Performance Concrete Pavements (TE-30)

Contracting Dates: Start 1995 - Ongoing
Contract Amount: Approximately $500,000 annually
Contractor: Various State Departments of Transportation
FHWA Contract Manager: Mark Swanlund

Project Goals/Objectives: The goals of the TE-30 Project are to construct selected highway projects to explore the applicability of innovative concrete pavement design and construction concepts and monitor the performance of those projects over at least a 5-year period.

Background: Under Test and Evaluation Project 30 (TE-30), High Performance Concrete Pavement (HPCP), the FHWA is exploring the applicability of innovative portland cement concrete (PCC) pavement design and construction concepts in the United States. Suggested innovation areas for the program include increased service life, decreased construction time, reduced life-cycle costs, reduced maintenance costs, ultra-smooth ride quality pavements, use of recycled or waste products, use of innovative construction equipment or procedures, and use of innovative quality initiatives. An example project is MN/DOT's design for 60-year PCC design which incorporated use of w/cm below 0.40, requirement for graded aggregate to minimize paste volume, slag cement requirement to achieve low permeability concrete, and stainless steel clad dowels to prevent corrosion.

Status: A report documenting the status of the projects constructed under the TE-30 program was produced in 2001. A new contract has been released to document new projects that have been added to the program and to update performance data on other projects. State highway agencies involved in the program continue to monitor the performance of their projects, and many have prepared construction and status reports.

A contract was awarded during fall 2003 to update the status of the TE-30 projects.

Available Reports/Articles/Presentations:

FHWA RFP Objectives, Scope of Work and Proposed Work Plan; State DOT Work Plans

General:

Public Roads - Fine-Tuning Innovative Technologies by Mark Swanlund, July/August 2002.

High Performance Concrete Pavements: Project Summary by Kurt Smith, Publication No. FHWA-IF-02-026, March 2002, Federal Highway Administration.

Status of High-Performance Concrete Pavements Constructed Under FHWA's TE-30 Program. By Kurt Smith and Mark Swanlund. Seventh International Conference on Concrete Pavements, Orlando, FL, September 2001.

State Reports:

Illinois

  • Gawedzinski, M, 1997, Fiber Composite Dowel Bar Experimental Feature Construction Report, Illinois Department of Transportation, Springfield, IL.
  • Gawedzinski, M., 2000, TE-30 High Performance Rigid Pavements Illinois Project Review, Illinois Department of Transportation, Springfield, IL.

Iowa

  • Cable, J.K., 1998, Evaluation of Mix Time on Concrete Consistency and Consolidation, Proceedings, Crossroads 2000 Conference, Ames, Iowa.
  • Cable, J.K. and L.L. McDaniel, 1998a, Effect of Mix Times on PCC Properties Iowa DOT Project HR-1066, Iowa Department of Transportation, Ames, IA.
  • Cable, J.K. and L.L. McDaniel, 1998b, Demonstration and Field Evaluation of Alternative Portland Cement Concrete Pavement Reinforcement Materials, Iowa DOT Project HR-1069, Iowa Department of Transportation, Ames, IA.

Kansas

  • Kansas Department of Transportation, 1998, High Performance Concrete Pavement, K-96 Reno County, 1998 Annual Report, Kansas Department of Transportation, Topeka, KS.
  • Kansas Department of Transportation, 1999, High Performance Concrete Pavement, K-96 Reno County, 1999 Annual Report, Kansas Department of Transportation, Topeka, KS.
  • Wojakowski, J.B., 1998, High Performance Concrete Pavement, Report No. FHWA-KS-98/2, Kansas Department of Transportation, Topeka, KS.

Maryland

  • Goulias, D. and C. Schwartz, 1999, High Performance Portland Cement Concrete Pavement. Project Work Plan, University of Maryland, Department of Civil and Environmental Engineering, College Park, MD.

Michigan

  • Buch, N., R. Lyles, and L. Becker, 2000, Cost Effectiveness of European Demonstration Project: I-75 Detroit, Report No. RC-1381, Michigan Department of Transportation, Lansing, MI.
  • Federal Highway Administration, 1992, Report on the 1992 U.S. Tour of European Concrete Highways, FHWA-SA-93-012, Federal Highway Administration, Washington, DC.
  • Federal Highway Administration, 1994, Michigan Demonstration Project-I-75, Detroit Michigan (European Concrete Pavement), FHWA-SA-95-045, Federal Highway Administration, Washington, DC.
  • Larson, R.M., S. Vanikar, and S. Forster, 1993, U.S. Tour of European Concrete Highways (U.S. TECH), Follow-Up Tour of Germany and Austria-Summary Report. FHWA-SA-93-080. Federal Highway Administration, Washington, DC.
  • Smiley, D.L., 1995, First Year Performance of the European Concrete Pavement on Northbound I-75-Detroit, Michigan, Research Report R-1338, Michigan Department of Transportation, Lansing, MI.
  • Weinfurter, J.A., D.L. Smiley, and R.D. Till, 1994, Construction of European Concrete Pavement on Northbound I-75-Detroit, Michigan, Research Report R-1333, Michigan Department of Transportation, Lansing, MI.

Minnesota

  • Minnesota Department of Transportation, 2000, New JPCP Test Cells at the MN/ROAD Project, Minnesota Department of Transportation, Maplewood, MN.
  • Rettner, D., 1999, I-35W High Performance Rigid Pavement Work Plan, Minnesota Department of Transportation, Maplewood, MN.
  • Turgeon, C., 2003, Minnesota's High Performance Concrete Pavements: Evolution of the Practice, Preprint Paper, 2003 Annual Meeting of the Transportation Research Board, Washington, DC.
  • Rangaraju, P.R., Development of Some Performance-Based Material Specifications for Minnesota's High Performance Concrete Pavement, Preprint Paper, 2003 Annual Meeting of the Transportation Research Board, Washington, DC.

Mississippi

  • Mississippi Department of Transportation, 1999, High Performance Concrete Pavement, Work Order Document, Work Order DTFH71-99-TE30-MS-12 (State Study No. 137), Mississippi Department of Transportation, Jackson, MS.

Missouri

  • Missouri Department of Transportation, 2000, Test Sections-Unbonded Concrete Overlay. Internal Technical Summary, Missouri Department of Transportation, Jefferson City, MO.

New Hampshire

  • Goodspeed, C.H., 1999, High Performance Concrete for Bridge and Pavement Applications, CD-ROM (with HPCP definitions, presentation files and computer program).

Ohio

  • Hawkins, B.K., A.M. Ioannides, and I.A. Minkarah, 2000, To Seal or Not to Seal: Construction of a Field Experiment to Resolve an Age-Old Dilemma, Preprint Paper No. 00-0552, 79th Annual Meeting of the Transportation Research Board, Washington, DC.
  • Ioannides, A.M., I.A. Minkarah, B.K. Hawkins, and J. Sander, 1999, Ohio Route 50 Joint Sealant Experiment-Construction Report (Phases 1 and 2) and Performance to Date (1997-1999), Ohio Department of Transportation, Columbus, OH.
  • Ohio Research Institute for Transportation and the Environment, 1998, Measurement of Dowel Bar Response in Rigid Pavement, ORITE-1, Ohio Department of Transportation, Columbus, OH.
  • Sargand, S.M., 2000, Performance of Dowel Bars and Rigid Pavement, Draft Final Report, Ohio Department of Transportation, Columbus, OH.

South Dakota

  • Ramakrishnan, V. and N. S. Tolmare, 1998, Evaluation of Non-Metallic Fiber Reinforced Concrete in New Full Depth PCC Pavements, Report No. SD96-15-F, South Dakota Department of Transportation, Pierre, SD.

Virginia

  • Ozyildirim, C., 2000, Evaluation of High-Performance Concrete Pavement in Newport News, VA, Draft Interim Report, Virginia Transportation Research Council, Charlottesville, VA.
  • Ozyildirim, C., 2001, Evaluation of High-Performance Concrete Pavement in Newport News, VA, Preprint Paper 01-3173, 80th Annual Meeting of the Transportation Research Board, Washington, DC.

Wisconsin

  • Crovetti, J.A., 1999, Cost Effective Concrete Pavement Cross-Sections, Report No. WI/SPR 12-99, Wisconsin Department of Transportation, Madison, WI.
  • Crovetti, J.A. and D. Bischoff, 2001, Construction and Performance of Alternative Concrete Pavement Designs in Wisconsin, Preprint Paper No. 01-2782, 80th Annual Meeting of the Transportation Research Board, Washington, DC.
  • Kuemmel, D.A., J.R. Jaeckel, A. Satanovsky, S.F. Shober, and M.M. Dobersek, 1996, Noise Characteristics of Pavement Surface Texture in Wisconsin, Transportation Research Record 1544, Transportation Research Board, Washington, DC.
  • Kuemmel, D.A., R.C. Sonntag, J.A. Crovetti, Y. Becker, J.R. Jaeckel, and A. Satanovsky, 2000, Noise and Texture on PCC Pavements-Results of a Multi-State Study, Report Number WI/SPR-08-99, Wisconsin Department of Transportation, Madison, WI.

Task 54 (99) - Repair and Rehabilitation of Concrete Pavements

Contracting Dates: February 2000 to December 2003
Contract Amount: $612,211
Contractor: Texas A&M Research Foundation
Principal Investigator: Dan Zollinger
FHWA Contract Manager: Jim Sherwood

Project Goals/Objectives: The goal of this project is to develop systematic, user-friendly guidelines for use by state highway agencies in 1) selecting between the better approach between concrete repair and concrete rehabilitation, and 2) selecting specific materials and repair/rehabilitation techniques in order to optimize performance and service life.

Background: The selection of appropriate maintenance and rehabilitation strategies for existing concrete pavements is a complex and involved process. There are a wide range of variables that must be considered in the process, including projected traffic loadings; structural and functional characteristics of the existing pavement; material types, conditions, and properties; environmental factors; and geometric constraints. Many of these factors are closely related to one another and the interactions between them are often extremely complex and difficult to isolate. Consequently, improved guidance is needed on the identification and selection of appropriate repair or rehabilitation treatments, including the selection of appropriate materials and techniques.

Status: A set of four reports has been completed and the computer program for the analysis of rehabilitation strategies (SAPER) is undergoing final modifications. A contract modification was awarded to make the deliverables comply with Section 508, to coordinate full and partial depth pre-cast repairs of a CRCP in the Houston District, and to work on a European Format Project on "pavement strengthening." The European project will analyze accelerated load and field tests. Final project deliverables are anticipated by early 2004.

Available Reports/Articles/Presentations:

FHWA RFP Objectives, Scope of Work and Proposed Work Plan; Contractor's Work Plan

Zollinger, D.G., K. Smith, and S. Tayabji, 2001, A Framework for Repair and Rehabilitation Treatment Selection for Portland Cement Concrete Pavements, Proceedings, Seventh International Conference on Concrete Pavements, International Society for Concrete Pavements, College Station, TX.

Zollinger, D.G., S.D. Tayabji, and K.D. Smith, June 2003, Repair and Rehabilitation of Concrete Pavements, Volume I: Executive Summary and Key Rehabilitation Considerations, Draft Final Report, Federal Highway Administration, Washington, DC.

Zollinger, D.G., S.D. Tayabji, K.D. Smith, and J. Liu, June 2003, Repair and Rehabilitation of Concrete Pavements, Volume II: Guidelines for Pavement Condition Assessment and Evaluation, Draft Final Report, Federal Highway Administration, Washington, DC.

Zollinger, D.G., S.D. Tayabji, and K.D. Smith, June 2003, Repair and Rehabilitation of Concrete Pavements, Volume III: Summary of Pavement Rehabilitation Techniques and Strategy Development, Draft Final Report, Federal Highway Administration, Washington, DC.

Liu, J., D.G. Zollinger, S.D. Tayabji, and K.D. Smith, June 2003, Repair and Rehabilitation of Concrete Pavements, Volume IV: Strategic Analysis of Pavement Evaluation and Repair (SAPER), Draft Final Report, Federal Highway Administration, Washington, DC.

Liu, J., D.G. Zollinger, S. D. Tayabji, and K. D. Smith, January 2004, SAPER: Tool for Selecting Concrete Pavement Repair and Rehabilitation Treatments, Preprint Paper, 2004 Meeting of the Transportation Research Board.

Task 55 (99) - Accelerated Load Testing of Ultra-Thin Whitetopping

Contracting Dates: 1998 to 2003
Contract Amount: $325,000
Contractor: FHWA R&D at Turner-Fairbank Highway Research Center
Principal Investigator: Jim Sherwood
FHWA Contract Manager: Jim Sherwood

Project Goals/Objectives: To construct and test UTW sections at the FHWA's Accelerated Loading Facility, in order that data can be collected, to evaluate and develop design procedures. Note: an IPRF Contractor has developed an updated ACPA UTW design method, based on stationary finite element models.

Background: FHWA and the American Concrete Pavement Association began a cooperative agreement in 1998. Response data was collected on eight sections of UTW, at the Accelerated Load Facility (ALF).

Status: Field tests are complete. About $325,000 in contract funds operated the two ALF machines for about 18 months of ALF testing, over the period May 1998 to December 2000. The FHWA Principal Investigator is preparing a final FHWA Report on the Project.

The loading of the eight UTW lanes and data collection is complete, including development of an ALF-UTW database. Assistance continues to be given to the ACPA and their contractors in data analysis. About 100 more 150 mm cores were extracted to conduct the Iowa shear test for bond between the PCC and HMAC materials, and to determine the shear strengths of the existing HMAC layers. In practically every case the bond strength was higher than the shear strength of the HMAC. Sections were removed in the spring of 2002 for construction of the next ALF experiment on modified asphalt concrete pavements.

The two study objectives were to provide a database of accelerated load tests of ultra thin whitetopping, and to evaluate current mechanistic models. An Accelerated Load Facility (ALF)/ Ultra thin Whitetopping (UTW) database version 1 was produced. In addition an extensive analysis has been conducted of the separate pavement response database. The finding was that current stationary load finite element models used for UTW, fail to capture the fundamental behavior. This analysis plus a User's Manual for the ALF/UTW database will comprise the Final Report.

Available Reports/Articles/Presentations:

No reports or other products are available.

<<PreviousContentsNext >>
 
This page last modified on 06/01/06
 

FHWA
United States Department of Transportation - Federal Highway Administration