U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000


Skip to content
Facebook iconYouTube iconTwitter iconFlickr iconLinkedInInstagram

Federal Highway Administration Research and Technology
Coordinating, Developing, and Delivering Highway Transportation Innovations

 
REPORT
This report is an archived publication and may contain dated technical, contact, and link information
Back to Publication List        
Publication Number:  FHWA-HRT-16-053     Date:  October 2016
Publication Number: FHWA-HRT-16-053
Date: October 2016

 

Application and Validation of Remaining Service Interval Framework for Pavements

CHAPTER 4. APPLICATION AND VALIDATION OF RSI FRAMEWORK AT THE PROJECT LEVEL

INTRODUCTION

Data collected as part of the LTPP Program provided an excellent opportunity to apply the comprehensive LCCA-based RSI methodology in a project-level demonstration and subsequent reporting of project treatment needs within the context of the RSI concept and terminology. In practice, network-level LCCA is possible if each section in the network has detailed data, typically called project-level data; the analysis shown in this chapter can be extended to each project section in the network. In this example, LTPP data is being used as representative project-level data.

Thyagarajan et al. presented a methodology for incorporating structural measurements to track flexible pavement structural condition over time and assessing future rehabilitation needs at a network level to address structural adequacy in addition to surface condition at LLCC.(35) The article showed that mechanistic-empirical pavement analysis tools such as CalME can be used to determine structural performance extension from a selected treatment applied at a given condition.(5) The estimated benefit (performance extension) combined with treatment cost are used in the LCC analysis to identify the optimum treatment sequence. Mechanistic-empirical analysis also enables the quantification of the monetary loss of delaying the optimum treatment. This chapter describes the application of the methodology proposed by Thyagarajan et al. using data from LTPP test section 06-0505 in which both structural and function conditions have been monitored at regular interval as part of LTPP monitoring efforts.(35) Figure 18 depicts the flowchart for this methodology. Finally, the identified optimum treatments are reported using the RSI terminology.

This figure shows the flow of the project level validation effort. The flowchart contains two segments: CalME validation and treatment optimization. The flow in the CalME validation segment starts from input box “LTPP section properties, construction event, traffic,” which flows to analysis box “Mechanistic analysis with CalME,” the output of which flows to analysis box “Validation of CalME performance prediction with field measurement” along with inputs from “LTPP FWD deflection and backcalculated moduli, and measured fatigue cracking, rutting and IRI.” The results from the CalME validation segment then flow to analysis box “Treatment scenarios” in the treatment optimization segment. “Treatment scenarios” then flow to analysis box “Mechanistic analysis with CalME,” the output of which flows to analysis box “Performance prediction” along with inputs from analysis box “Use tensile strain as a structural measure.” The output from “Performance prediction” then goes to decision box “At or above acceptable LOS over analysis period,” from which “No” goes back to analysis box “Treatment scenarios” while “Yes” goes forward to the analysis box “Life cycle cost analysis.” Two arrows extend from this box. The first loops back to the initial box labeled “Treatment scenarios.” The second extends downward toward analysis box “Optimum treatment sequence,” along with the input from analysis box “Use tensile strain as a measure for remaining value.”

FWD = Falling weight deflectometer.
Figure 18. Flowchart. Project-level validation.

LTPP TEST SECTION

The LTPP database includes periodical measurements on distress performance, structural evaluation, and traffic for each monitored section. In addition, the data collection effort includes section inventory, material testing (laboratory and field), climate, and M&R data. LTPP InfoPaveTM offers a gateway to LTPP data as well as to findings from data analyses and extensive documentation for the many aspects of LTPP experiment design, data acquisition, quality control, and data dissemination. LTPP test section 06-0505 in California, which was part of LTPP’s Specific Pavement Studies on Rehabilitation of Asphalt Concrete Pavements (SPS-5 experiment) was used in this project.(36) The layer types and construction events for the selected section are summarized in table 13. The pavement section was constructed in June 1966, and the M&R history for the section was available from January 1987 when the section was included in the LTPP Program. The first recorded treatment event was a mill and overlay applied in February 1992. The section was taken out of study from the LTPP Program in June 2007.

Table 13. Construction events and layer information for LTPP test section 06-0505.
Layer Information Construction Events
CN 1: Initial Structure January 1987 CN 2: Mill and Overlay February 1992 CN 3: Crack Sealing March 2000 CN 4: Resurfacing July 2000
Layer Number Layer Type Layer Material Description Thickness (inch) Thickness (inch) Thickness (inch) Thickness (inch)
1 Subgrade (untreated) Coarse-grained soils: poorly graded sand with silt        
2 Unbound (granular) subbase Soil-aggregate mixture (predominantly coarse-grained) 20 20 20 20
3 Bound (treated) base Cement aggregate mixture 5.2 5.2 5.2 5.2
4 AC layer Hot mixed, hot laid AC, dense graded 4.7 3 3 3
5 AC layer Hot mixed, hot laid AC, open graded 0.5 0 0 0
6 AC layer Hot mixed, hot laid AC, dense graded   3.1 3.1 3.1
7 AC layer Plant mix (emulsified asphalt) material, cold laid       0.2
CN = Construction number.
Blank cell = Layer 1 (subgrade) thickness is not measured (assumed to be semi-infinite) and/or layers 6 and/or 7 do not exist.

 

Figure 19 shows the measured traffic loading for LTPP test section 06-0505. As shown in this figure, an annual traffic growth of 1 percent was computed by fitting a linear trend to the data. Figure 20 shows the measured pavement roughness (IRI), and figure 21 shows AC fatigue cracking and AC rutting for this test section over time. As shown in these figures, the construction events detailed in table 13 reduced the measured amount of roughness, rutting, and cracking.

The graph shows the annual traffic on Long-Term Pavement Performance (LTPP) test section 06-0505 through different years. The x-axis is the time between 1990 and 2010. The y-axis is the traffic between 0 and 1,400 kESALs. The data points show a sinusoidal trend around 1,000 kESALs. A linear trend line fitted to the data show 1 percent traffic growth from 1992. 
Figure 19. Graph. Annual traffic on LTPP test section 06-0505.

 

The graph shows the profile (International Roughness Index (IRI)) measured on Long-Term Pavement Performance (LTPP) test section 06-0505 over the service period. The x-axis is the service period between August 1987 and July 2009. The y-axis is the profile (IRI) between 0 and 250 inches/mi. The profile starts at 80 inches/mi and continuously increases over the service period. The two construction events, construction number (CN)2: Mill and Overlay and CN 3: Crack Seal and Resurfacing, have reduced the profile values at the time of application.

Figure 20. Graph. Measured profile on LTPP test section 06-0505.

 

 The graph shows the fatigue cracking and asphalt concrete (AC) rutting measured on Long-Term Pavement Performance (LTPP) test section 06-0505 over the service period. The x-axis is the service period between August 1987 and July 2009. There are two y-axes. The primary y-axis is the LTPP measured cracking between 0 and 4,500 ft2/ ft. The secondary y-axis is the LTPP measured rutting between 0 and 0.45 inch. Both cracking and rutting continuously increase over the service period, and the two construction events, construction number (CN)2: Mill and Overlay and CN 3: Crack Seal and Resurfacing, have reduced them at the time of application.

Figure 21. Graph. Measured fatigue cracking and AC rutting on LTPP test section 06-0505.

Figure 22 shows the resilient modulus value at different temperatures and monitoring periods for the AC mixes used in layers 4 and 6 (see table 13). As shown in this figure, at 77 °F, the resilient modulus of both AC mixes is about 1,300 ksi. The resilient modulus test was also performed on the subbase material in April 2003. Figure 23 shows the effect of confining pressure on resilient modulus for the granular subbase layer. The resilient modulus of subbase material at a confining pressure of 5 ksi is approximately 12 ksi.

The graph is a column chart comparing resilient modulus values of asphalt concrete mix reported for Long-Term Pavement Performance (LTPP) test section 06-0505 by four different tests conducted at three different test temperature. Among the four tests, one was conducted at January 1990 on layer number 4, and three tests were conducted on October 2003 on layer number 6. The y-axis is the resilient modulus between 0 and 3,000 ksi. The x-axis is the three test temperatures 41, 77, and 104 °F. At each test temperature, resilient modulus values were similar among the four tests and have a resilient modulus of 2,000, 1,250, and 600 ksi at test temperatures of 41, 77, and 104 °F, respectively.

Figure 22. Graph. Resilient modulus of AC mix at different service periods for LTPP test section 06-0505.

 

The graph shows the resilient modulus of subbase material at five different confining pressures for Long-Term Pavement Performance (LTPP) test section 06-0505. The y-axis is the resilient modulus between 0 and 40 ksi. The x-axis is the confining pressure between 0 and 25 psi. Three resilient modulus values at each of the five confining pressures (3, 5, 10, 15, and 20 psi) are presented. The resilient modulus values vary gradually from 8 ksi at a confining pressure of 3 psi to 30 ksi at a confining pressure of 20 psi.

Figure 23. Graph. Resilient modulus of subbase material at different confining pressures for LTPP test section 06-0505.

Periodic FWD testing was conducted on LTPP test section 06-0505 starting in January 1990 prior to construction event 2 (mill and overlay; see table 13). LTTP InfoPaveTM also contained FWD-derived backcalculated layer moduli values for the section in question computed using the EVERCALC backcalculation program. Figure 24 presents the backcalculated modulus for each structural layer of LTPP test section 06-0505. The surface temperatures measured during FWD testing are available for after February 1992. The temperature correction procedure incorporated in the EVERCALC program was used to compute AC layer modulus at a reference temperature of 77 °F, and the resulting temperature-corrected AC layer moduli are also shown in figure 24 along with the trend line. For comparison purposes, the lab-measured AC resilient moduli from figure 22 are also shown in figure 24.

The graph shows backcalculated moduli values for each layer: asphalt concrete (AC), stabilized treated base, coarse subgrade 2 ft, and coarse subgrade from Long-Term Pavement Performance (LTPP) test section 06-0505. The y-axis shows the layer modulus in a logarithm scale between 1 and 10,000 ksi. The x-axis shows the test dates between August 1987 and October 2006. The AC layer modulus varies between 300 and 500 ksi between May1990 and January 2004. The stabilized treated base layer modulus varies between 7 and 12 ksi between May 1990 and January 2004. The coarse subgrade 2-ft layer modulus varies between 13 and 26 ksi between May 1990 and January 2004. The coarse subgrade layer modulus varies between 19 and 31 ksi between May 1990 and January 2004. In addition, the temperature-corrected AC layer modulus identified as LTPP_FWD_AC@77 °F was included in the graph along with a trend line that shows that the AC modulus was 380 ksi in September 1992 and increased to 460 ksi in October 1994 and then gradually decreased to 130 ksi around January 2004. Also, the graph shows the AC layer modulus computed from lab test at 77 °F, which are around 1,300 ksi at two test dates around May 1990 and January 2004. 
Figure 24. Graph. LTPP backcalculated layer moduli for LTPP test section 06-0505.

CaLME ANALYSIS

The CalME analysis software was used in this project to predict past and future performance and then to compare the predicted performance with the measured LTPP performance. The CalME software takes into account the progressive deterioration of the pavement structure over the design period and can also consider sequence of treatments during the analysis period to preserve and provide acceptable or above acceptable LOS over the analysis period. It is important to note that the CalME transfer functions were calibrated for California conditions and are therefore applicable to the LTPP test section 06-0505.

Barstow Daggett County Airport in California is the closest first-order weather station for LTPP test section 06-0505; it is about 12 mi west of the section. Figure 25 shows the hourly air temperature profile for the section over a 3-year period. The monthly average temperature shown in the figure is the temperature used in the CalME analysis.

 The graph shows both hourly and average monthly temperature profile over 3 years near Long-Term Pavement Performance LTPP) test section 06-0505. The x-axis shows the dates between August 1981 and June 1985. The y-axis shows the temperature between 0 and 160 °F. The average temperature has sinusoidal variation with a minimum and maximum temperature of 60 °F and 100 °F variation repeated within each year between January 1982 and December 1984.

Figure 25. Graph. Three-year air temperature profile near LTPP test section 06-0505.

Figure 26 shows the layer moduli computed by CalME using the pavement section, layer properties, traffic, and climate data for LTPP test section 06-0505. The section was already in service when included in the LTPP Program; therefore, the AC properties at the time of initial construction were not available. Accordingly, default AC layer properties were assumed for layer 4 defined in table 13. Figure 26 shows the effect of seasonal fluctuation and structural deterioration on the computed layer moduli. The AC layer moduli for layers 4 and 6 show a gradual decrease over the analysis period. For comparison purposes, the AC resilient moduli from the laboratory and the FWD backcalculation (temperature corrected) and the subbase resilient moduli from the laboratory are also included in the figure. Note that all AC layers are treated as a single layer for backcalculation; therefore, the FWD-derived AC moduli are an estimate of the combined AC layers at the time of FWD testing. As shown in figure 26, significant differences exist between the laboratory-derived AC moduli and those derived from FWD backcalculation. Both sets of data were obtained directly from the LTPP database.

 The graph shows CalME-calculated moduli values for each layer: asphalt concrete (AC) layers 4 and 6, base, subbase, and subgrade for Long-Term Pavement Performance (LTPP) test section 06-0505. The y-axis is the layer modulus in a logarithm scale between 10 and 10,000 ksi. The x-axis is the test dates between 1982 and 2008. The layer modulus for AC layer number 4 varies sinusoidally between 270 and 1,600 ksi annually in 1983 and gradually decreases to 100 and 200 ksi annually in 2005. The layer modulus for AC layer number 6 varies sinusoidally between 250 and 2600 ksi annually in 1992 and gradually decreases to 130 and 180 ksi annually in 2005. The layer modulus for the base layer varies sinusoidally between 15 and 19 ksi annually in 1983 and gradually decreases to 12 and 13 ksi annually in 2005. The layer modulus for subbase layer varies sinusoidally between 22 and 30 ksi annually in 1983 and gradually decreases to 21 and 22 ksi annually in 2005. The layer modulus for subgrade layer varies sinusoidally between 15 and 22 ksi annually in 1983 and gradually decreases to 13 and 14 ksi annually in 2005. In addition, the temperature-corrected AC layer modulus identified as LTPP_FWD_AC@77 °F was included in the graph that shows that the AC modulus was 380 ksi in 1992 and increased to 600 ksi in 1996 and then decreased to 140 ksi in 2004. Also, the graph shows the AC modulus for layers 4 and 6 computed from lab tests at 77 °F, which are around 1,300 ksi in 1990 and 2004, respectively. The graph also shows the subbase layer modulus computed from lab tests, which is around 20 ksi when tested in 2003.

Figure 26. Graph. CalME-computed layer moduli for test section 06-0505.

Figure 27 and figure 28 compare the CalME estimated and LTPP measured fatigue cracking and rutting, respectively. These two figures clearly show that the CalME program can replicate actual field performance and therefore can be used with confidence in scheduling future treatment activities.

 The graph compares the fatigue cracking measured by the Long-Term Pavement Performance (LTPP) Program and estimated by CalME on LTPP test section 06-0505 over the service period. The x-axis is the service period between February 1982 and July 2009. There are two y-axes. The primary y-axis is the LTPP-measured alligator cracking between 0 and 5,000 ft2. The secondary y-axis is the CalME-estimated alligator cracking between 0 and 1.5 ft/ft2. Both LTTP-measured cracking and CalME-estimated cracking have similar trends and continuously increase over the service period, and the two construction events, marked as construction number (CN)2: Mill and Overlay and CN 3: Crack Seal and Resurfacing, have reduced them to zero at the time of application.

Figure 27. Graph. LTPP-measured versus CalME-estimated fatigue cracking for LTPP test section 06-0505.

 

 The graph compares the rutting measured by the Long-Term Pavement Performance (LTPP) Program and estimated by CalME on LTPP test section 06-0505 over the service period. The x-axis is the service period between February 1982 and July 2009. The y-axis is the LTPP-measured or CalME-estimated rutting ranging between 0 and 0.5 inch. Both LTTP-measured and CalME-estimated rutting have similar trends and continuously increase over the service period. The two construction events, marked as construction number (CN) 2: Mill and Overlay, and CN 3 and 4: Crack Seal and Resurfacing, have reduced them at the time of application.

Figure 28. Graph. LTPP-measured versus CalME-estimated rutting for test section 06-0505.

INTEGRATED MECHANISTIC AND LCC ANALYSES

In this section, the optimum treatments were scheduled for LTPP test section 06-0505 based on pavement conditions in 1997. The methodology proposed in Thyagarajan et.al was used to couple both mechanistic and LCC analyses and to identify the optimum sequence of treatment types and timings that minimizes the LCC.(35)

In 1997, the last treatment applied to LTPP test section 06-0505 was mill and overlay (CN 2; see table 13) as part of the LTPP SPS-5 experiment (AC overlays on existing AC pavements).(36) A resurfacing was applied in 2000 when significant cracking was observed on the surface. Preservation treatments such as resurfacing often retard the pavement deterioration and therefore are effective when the pavement structural condition is still good. Preservation treatment applied to structurally weak pavement only temporarily conceals the structural deterioration that occurs under the surface, thereby limiting future treatments to only costlier treatments such as thick overlays. The availability of continuous pavement structural data coupled with integrated mechanistic and LCC analysis would identify the appropriateness of the selected treatment type (preservation versus rehabilitation) in serving the objective of maintaining the pavement at or above an acceptable LOS while minimizing LCC over its service period.

Five different treatment scenarios were evaluated with the CalME program using the LTPP test section 06-0505 pavement condition data for 1997. In all scenarios, the minimum LOS was established as maintaining the pavement below an IRI threshold value of 140 inches/mi. The five scenarios were as follows:

Figure 29 shows the amount of fatigue cracking estimated by CalME for these five scenarios. As expected, the fatigue performance is a function of both treatment type and its time of application. Table 14 shows the LCCA for the five treatment scenarios. The table includes the performance extension computed by CalME for each treatment scenario to reach a cracking level of 0.15ft/ft2. The costs for the resurfacing, mill and overlay, and mill and thicker overlay treatments were assumed to be $60,000, $300,000, and $400,000, respectively. A 4-percent discount rate was used in the LCCA. In 1997, the tensile strain at the bottom of the AC layers due to the application of a 9,000-lb load with 120-psi tire pressure and 12-inch dual tire spacing was estimated to be 163 microstrain, as computed by Jacob Uzan Layered Elastic Analysis (JULEA) using the CalME computed modulus.(37)

In-service pavements may be subjected to a sequence of construction events. Accordingly, in a network-level LCCA, the asset value of each pavement section at the analysis year is an important parameter required for comparing equivalent treatment strategies. For this analysis, the asset value of the section was assumed to be $250,000. The net present value (NPV) and EUAC are also shown in table 14.

 The graph compares the fatigue cracking estimated by CalME for five treatment scenarios on Long-Term Pavement Performance (LTPP) test section 06-0505 over the service period. The x-axis shows the service period between 1995 and 2009. The y-axis shows the fatigue cracking between 0 and 0.5 ft/ft2. A threshold line for fatigue cracking at 0.15 ft2/ft was extended through the service period. For scenario 1, the fatigue cracking occurred at the beginning of 1998, crossed the threshold line in mid-1999, and reached a maximum value of 0.4 ft2/ft in early 2000. The cracking then reduced to 0 ft/ft2, reached the threshold line near the end of 2003, and then rapidly increased to 0.5 ft2/ft at the end of 2004. In scenario 2, the fatigue cracking occurred in early 2002, reached the threshold line around the end of 2003, and then dropped to 0 ft/ft2. Cracking then again appeared around mid-2005 and rapidly increased to 0.5 ft2/ft at the end of 2006. In scenario 3, the fatigue cracking occurred at the end of 2005, reached the threshold line around the end of 2007, and then rapidly increased to 0.5 ft2/ft in early 2009. In scenario 4, the fatigue cracking occurred in mid-2006, reached the threshold line around the end of 2009, and then increased to 0.4 ft2/ft at the end of 2010. In scenario 5, the fatigue cracking occurred in early 2002, reached the threshold line around the end of 2003, and then dropped to 0 ft/ft2. Cracking then again appeared around early 2006 and rapidly increased to 0.5 ft2/ft in mid-2008.

Figure 29. Graph. CalME-estimated fatigue cracking for five treatment scenarios on LTPP test section 06-0505.

Table 14. LCCA for LTPP Section 06-0505 in 1997.
Scenario Overlay Treatment Performance Extension from 1997 (years) NPV of Future Treatment Cost in 1997 ($) EUAC ($) Pretreatment Tensile Strain, microstrain (year) Tensile Strain in 2003 (microstrain) NPV to Bring the Pavement to State of Good Repair ($) Revised EUAC ($)
1 Resurfacing
in 2000

(current LTPP scenario)
5.8 53,340 59,636 242 (2000) 362 369,466 75,152
2 Resurfacing in 2000 + mill and overlay in 2003 9 290,434 72,685 362 (2003) 162 290,434 72,685
3 Mill and overlay in 2000 10.2 266,699 62,684 242 (2000) 148 266,699 62,684
4 Mill and overlay in 1998 11.8 288,462 58,136 179 (1998) 141 288,462 58,136
5 Resurfacing in 2000 + mill and thicker overlay in 2003 10.2 369,466 75,152 362 (2003) 147 369,466 75,152

 

Mill and overlay treatments applied in 1998, 2000, and 2003 (scenarios 4, 3, and 2, respectively) yielded different performances, as shown by the performance extension in table 14. Mill and overlay treatment applied in 1998 (scenario 4), when there was little or no surface cracking, yielded the best performance in terms of time extension. Comparing scenario 2 and 3, the latter of the two (mill and overlay in 2000 instead of resurfacing in 2000 and mill and overlay in 2003) is a more optimal treatment sequence. In scenario 2, the AC layer has been significantly damaged by 2003, when the mill and overlay was applied. As such, the delayed mill and overlay (scenario 2) did not perform as well as if it had been applied when the structure was still in good condition, as is the case with scenarios 3 and 4.

Table 14 also shows that the mill and overlay in 1998 (scenario 4), prior to the appearance of surface cracks, is the optimum treatment. When surface distresses such as fatigue cracking are used as the pavement structural indicator, it is difficult to identify the optimum treatment timing because by the time surface distresses appear, the pavement structure may already have deteriorated to a point where lower-level treatments, such as preservation, may not be effective. Accordingly, fatigue cracking can be viewed as a lagging indicator of pavement structural condition, which limits cost-effective alternatives that would otherwise have been possible. Also, the fatigue cracking measured at the pavement surface is effectively covered by any surface treatment and therefore may not be a reliable pavement structural measure in subsequent assessments.

Use of Tensile Strain as Structural Indicator

Structural parameters computed from deflection measurements can be used as leading pavement structural indicators instead of lagging indicators such as surface cracking. Continuous pavement structural evaluations, such as those performed using traffic speed deflection devices (TSDDs) provide an excellent opportunity to identify the optimum treatment that yields the LLCC and thereby leading to more efficient PMSs.(38) Past studies have used curvature indices computed from deflection basins to correlate with the horizontal tensile strain at the bottom of the AC layer (hereafter referred simply as tensile strain).(35,39–46) The correlation was verified on the test section used in this analysis. The CalME computed layer moduli values for LTPP test section 06-0505 were used along with the JULEA program to compute tensile strains and the Surface Curvature Index as a function of time, as shown in figure 30.(37) Surface Curvature Index is defined as the difference between the measured deflection at the center of the load and the deflection 12 inches away from the load. A strong correlation between tensile strain and Surface Curvature Index is shown in figure 31.

 The graph compares the tensile strain and Surface Curvature Index on Long-Term Pavement Performance (LTPP) test section 06-0505 over the service period. The x-axis shows the service period from 1982 to 2006. There are two y-axes. The primary y-axis shows the horizontal tensile strain at the bottom of the asphalt concrete layer ranges between 0 and 450 microstrain. The secondary y-axis shows the Surface Curvature Index, which ranges between 0 and 10 mil. Both tensile strain and the Surface Curvature Index represented in the different y-axes show similar trends. Initial tensile strain is 200 microstrain in 1983, and then it decreases gradually to 160 microstrain in 1986 before increasing again to 200 microstrain in 1991. Then tensile strain again decreases to 130 microstrain in 1994 and increases to 420 microstrain in 2004. In the case of Surface Curvature Index, initial Surface Curvature Index is 4.5 mil in 1983, and then it decreases gradually to 3.5 mil in 1986 before increasing again to 4.5 mil in 1991. Tensile strain then again decreases to 2.9 mil in 1994 and increases to 
9 mil in 2004.

Figure 30. Graph. Tensile strain and Surface Curvature Index as a function of time for LTPP test section 06-0505.

 

The graph shows the correlation between tensile strain and Surface Curvature Index on Long-Term Pavement Performance (LTPP) test section 06-0505. The x-axis shows the Surface Curvature Index, which ranges from 0 to 8 mil. The y-axis shows the horizontal tensile strain at the bottom of the asphalt concrete layer and ranges from 0 to 350 microstrain. A linear trend line is fitted to the data with an R2 value of 0.9773. The tensile strain ranges between 140 and 300 microstrain, and Surface Curvature Index ranges between 2.9 and 6.4 mil. 
Figure 31. Graph. Tensile strain and Surface Curvature Index correlation for LTPP test section 06-0505.

Figure 32 shows tensile strains as a function of time for the five scenarios under consideration, which were computed using the JULEA program based on the CalME computed layer moduli values.(37) The figure shows that tensile strains can be a structural evaluation parameter that, unlike fatigue cracking, can continue to be an effective structural indicator after surface treatments. Also, the use of tensile strain as structural performance indicator provides continuity in tracking structural condition even after any given M&R activity.

 The graph compares the tensile strain computed from the CalME layer modulus for five treatment scenarios on Long-Term Pavement Performance (LTPP) test section 06-0505 over the service period. The x-axis shows the service period from 1995 to 2009. The y-axis shows the tensile strain from 0 to 400 microstrain. A threshold line for tensile strain at 250 microstrain extends through the service period. For scenario 1, the initial tensile strain is 140 microstrain in 1995 and then gradually increases and crosses the threshold line at end of 2000 and reaches a maximum value of 400 microstrain in mid-2004. In scenario 2, the tensile strain decreases from 360 to 160 microstrain in 2003. After a small dip to 150 microstrain in 2004, the tensile strain gradually increases to 325 microstrain in 2009. In scenario 3, the tensile strain decreases from 240 to 150 microstrain in 2000. After a small decrease to 125 microstrain in 2001, the tensile strain gradually increases to 270 microstrain in 2009. In scenario 4, the tensile strain decreases from 180 to 135 microstrain in 1998. After a small decrease to 120 microstrain in 1999, the tensile strain gradually increases to 210 microstrain in 2009. In scenario 5, the tensile strain decreases from 360 to 145 microstrain in 2003. After a small decrease to 130 microstrain in 2004, the tensile strain gradually increases to 270 microstrain in 2009.

Figure 32. Graph. Tensile strain computed from the CalME layer modulus for different scenarios.

Comparing figure 29 and figure 32, the relative merits of using tensile strains instead of fatigue cracking as a structural indicator are summarized as follows:

Reasonable remaining values for pavements at the end of an analysis period can also be computed using tensile strains because they consider the total remaining structural capacity of the pavement rather than using prorated values based on the last treatment. Therefore, in contrast to surface condition measures such as cracking (which are ineffective pavement structural condition indicators once new treatments are applied), tensile strains computed from deflection measurements are able to continuously track the structural deterioration of the pavement system as a whole. This includes contributions from future treatments, including both rehabilitation treatments that add to structural capacity and preservation treatments that often slow down further deterioration.

In the LCCA, tensile strains were used in comparing the five scenarios and in identifying optimum treatment. For the last treatment sequence in each scenario, pretreatment tensile strains and the year of treatment application were also included in table 14. In addition, tensile strain at 2003 (for a 6-year analysis period) was included in the table. Based on EUAC, scenarios 1 and 4 have the lowest cost and would be considered the optimum treatments because both scenarios provide acceptable or above acceptable LOS over the analysis period. However, in 2003, the pavement in scenario 1 would have high deterioration, as shown by the high tensile strain value of 362, while the pavement in scenario 4 would still be in good structural condition, as shown by the tensile strain of 141. Therefore, with a short analysis period (such as 6 years), preventive treatments that have low costs associated with them would be selected, which can lead to rapid deterioration of the pavement structure. Accordingly, for comparison of treatment strategies, it is important to include the remaining value of the pavement or to include the treatment cost that will bring the pavement to a state of good repair at the end of the analysis period. In this LCCA, standardization was obtained by choosing the treatments that produce a pavement with a tensile strain around 150 microstrain at the end of the analysis period. The cost of the thicker overlay required to bring the pavement to such tensile strain level was added to scenario 1, and the revised EUAC is shown in the last column in table 14 for each scenario.

RSI

Comparing the revised EUAC, scenario 4 was found to be the optimum one. Table 15 shows the RSI computed for LTPP test section 06-0505 using the comprehensive LCCA methodology. A similar approach to each pavement section in a network can provide a planned sequence of treatments from which unconstrained budget requirements for PMS can be estimated. Table 15 also includes the RSI for the current treatment scenarios used in the LTPP test section.

Table 15. RSI for LTPP test section 06-0505.
Scenario Type RSI Preservation (year) RSI Rehabilitation (year) RSI Reconstruction (year)
Current 2000 1992  
Optimum   1992, 1998  
Blank cell = Not applicable.

 

SUMMARY

The following observations sumarize the most important findings and conclusions from the RSI concept validation effort presented in this chapter:

 

 

Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000
Turner-Fairbank Highway Research Center | 6300 Georgetown Pike | McLean, VA | 22101