U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000
Virginia Division
The FHWA Risk Management Plan identifies the major risk areas in implementing the American Recovery and Reinvestment Act of 2009 (Recovery Act). For the consideration of the Division Offices, example checklists have been developed for use in “visible monitoring” efforts. The Contract Administration Checklist focuses on the risks in procurement, bidding, and management of contract changes.
Federal Project Number: | |
State Project Number: | |
Project Name/Route Number and Section |
|
County: | |
Project Description | |
Authorization Date | |
Advertisement Date | |
Letting Date: |
Regulations and Guidance
23
CFR 635 A, B, C & D – Construction and Maintenance
Headquarters memorandum dated July 12, 1963, Subject: Participation in Engineering
Errors
https://www.fhwa.dot.gov/programadmin/contracts/071263.cfm
Headquarters memorandum dated September 8, 1978, Subject: Participation in
the Cost of Corrective Work Resulting from Construction Engineering Errors
https://www.fhwa.dot.gov/programadmin/contracts/090878.cfm
FHWA Policy Letter dated November 15, 1996
https://www.fhwa.dot.gov/programadmin/contracts/111596.cfm
FHWA Policy Memo dated September 18, 1990
https://www.fhwa.dot.gov/programadmin/contracts/091890.cfm
Contract Administration Core Curriculum Participant's Manual and Reference
Guide
https://www.fhwa.dot.gov/programadmin/contracts/coretoc.cfm
Guidelines on Preparing Engineer's Estimate, Bid Reviews and Evaluation
https://www.fhwa.dot.gov/programadmin/contracts/ta508046.cfm
Engineer's Estimate: | |
Low Bid: | |
Percent over/under Engineer's Estimate: | |
High Bid: | |
Number of Bids: | |
Number of Competitive Bids: (A competitive bid is a bid within 20% of the low bid) |
Reference Guidelines on Preparing Engineer's Estimate, Bid Reviews and Evaluation https://www.fhwa.dot.gov/programadmin/contracts/ta508046.cfm |
||||
---|---|---|---|---|
Reference | Item | Yes | No | N/A |
635.112 | PS&E was approved and project authorized prior to advertisement | |||
635.112 | Project advertised for at least 3 weeks | |||
Competition adequate see table below | ||||
635.114 | Unit prices do not differ significantly from the estimate | |||
Unit prices do not differ significantly from other bidders | ||||
Unit prices do not differ significantly from similar projects in the same letting? | ||||
635.114 | No significant mathematical unbalancing of the bids | |||
635.114 | No material unbalancing of the bids | |||
No errors in the engineer's estimate | ||||
No problems with the bid documents identified | ||||
Bidders acknowledged receipt of all addenda | ||||
49 CFR 29 | Apparent low bidder not suspended or debarred (General Services Administration's Excluded Parties Listing System - https://www.epls.gov/ ) | |||
No issues with the identity/geography of the bidders | ||||
49 CFR 26 | DBE participation meets the DBE goal | |||
Conditional items of authorization adequately addressed | ||||
Low bidder considered responsive | ||||
Deferral contrary to the public interest | ||||
Potential for savings, if the project is re-advertised | ||||
635.114 | Project will be awarded to the low bidder | |||
Comments: |
Assessing Competition (This table can be used as a guideline for assessing competition)
Number of competitive bids * (*Range = low bid + 20 percent) |
Competition May be considered adequate when low bid does not exceed ** |
---|---|
5 | 120 percent of engineer's estimate |
4 | 115 percent of engineer's estimate |
3 | 110 percent of engineer's estimate |
2 | 105 percent of engineer's estimate |
1 | The engineer's estimate |
The State transportation agency's (STA) bid information contains agency Engineer's Estimate, which may be CONFIDENTIAL! The responsible FHWA transportation engineer will not discuss the details of the estimate with anyone other than the FHWA or State contact.
Reference | Item | Yes | No | N/A |
---|---|---|---|---|
635.120 | Major change in plans or contract provisions or major extra work | |||
635.120 | Use of force account procedures necessary | |||
635.120 | Scope clearly defined | |||
635.120 | Need adequately justified | |||
635.120 | Independent cost estimate developed | |||
635.120 | Costs adequately justified | |||
635.120 | Contract modification executed in a timely manner | |||
635.120 | Appropriate approvals documented | |||
635.120 | Change in contract time submitted at the same time as the contract change or extra work | |||
635.121 | Contract time extension fully justified and adequately documented | |||
Comments: |
Table of Contents | (continued) |