Final Value Engineering (VE) Program Performance Measures
Attachment
Goal 1: Maximize the influence VE studies have on a project's cost and performance.
Outcome:
By increasing the number of VE study recommendations that are implemented, improvements in the project's cost-effectiveness and performance will be realized.
- Baseline: 2.0 (FY 2009)
- Target: 2.5 (FY 2016)
The baseline and target measures were developed using weighted averages of the data collected from the annual VE reporting cycles. These measures are based on a weighted average of 60% of the indicator for project construction costs saved and 40% of the indicator for VE study recommendations implemented. Both the national average and numeric average for each indicator will be compiled, tracked and reported.
Performance indicators:
- Percentage of VE study recommendations implemented
- National average:
- Baseline: 44 % (FY 2009)
- Target: 55 % (FY 2016)
- Performance indicator & metric: The data collected (question 11b) in the annual VE reporting cycle for each state DOT is converted to a numeric value and averaged as depicted in the following matrix:
- Baseline: 2.3 (FY 2009)
- Target: 2.8 (FY 2016)
| |
0 |
1 |
2 |
3 |
4 |
5 |
| % of Implemented Recommendations |
0-15% |
16-30% |
31-45% |
46-60% |
61-80% |
81-100% |
- Percentage of project construction costs saved
- National average:
- Baseline: 8.0 % (FY 2009)
- Target: 10.0 % (FY 2016)
- Performance metric: The data collected (question 10b & 12b) in the annual VE reporting cycle for each state DOT is converted to a numeric value and averaged as depicted in the following matrix:
- Baseline: 1.8 (FY 2009)
- Target: 2.4 (FY 2016)
| |
0 |
1 |
2 |
3 |
4 |
5 |
| % of Construction Project Cost Savings |
0-2.5% |
2.5-5% |
5-7.5% |
7.5-10% |
10-12.5% |
More than 12.5% |
Goal 2: Enhance the quality of VE programs.
Outcome:
To enhance both the strategic and day-to-day capacity (e.g., policy, procedures, functions, services) and quality of VE programs.
- Baseline: 2.5 (FY 2009)
- Target: 3.5 (FY 2016)
The baseline and target measures were developed using weighted average of the data collected from the annual VE reporting cycles. These measures are based on a weighted average of 30% for the state DOTs with a VE policy, 30% for the State DOTs with an established VE program, and 40% for the state DOT's conducting VE studies prior to completing 30% of the design of a project.
Performance indicators:
- Number of state DOTs with a VE policy.
- Baseline: 2.7 (FY 2009)
- Target: 4.1 (FY 2016)
Performance Metric: The data collected (question 1b) in the annual VE reporting cycle is converted to a numeric value and averaged as depicted in the following matrix:
| |
0 |
1 |
2 |
3 |
4 |
5 |
| VE Policy |
No policy documented or formal VE program commitment |
Documented commitment to conduct required VE studies (23 CFR 627) & 1 VE program element in policy |
2 VE program elements addressed in policy |
3-4 VE program elements addressed in policy |
5-6 VE program elements addressed in policy |
All 7 E program elements addressed in policy |
- Number of states with an established VE Program.
- Baseline: 3.1 (FY 2009)
- Target: 4.0 (FY 2016)
Performance Metric: The data collected (question 1a & 2a) in the annual VE reporting cycle is converted to a numeric value and averaged as depicted in the following matrix:
| |
0 |
1 |
2 |
3 |
4 |
5 |
| VE Policy |
No policy documented or formal VE program commitment |
1 VE program element identified or under development |
2 VE program elements identified or under development |
3 VE program elements identified or under development |
4 VE program elements identified or under development |
5 VE program elements identified or under development |
- Percentage of VE studies conducted prior to completing 30% of a project's design.
- Baseline: 1.9 (FY 2009)
- Target: 2.7 (FY 2016)
Performance Metric: This indicator reflects the percentage of the VE studies that state DOTs conduct prior to completing 30% of a project's design, using the data collected (question 4c) in the annual VE reporting cycle, is converted to a numeric value and averaged as depicted in the following matrix:
| |
0 |
1 |
2 |
3 |
4 |
5 |
| % of VE studies conducted before completing 30% of a project's design |
0-15 % |
15-30 % |
30-45 % |
45-60 % |
60-80 % |
80-100 % |
Goal 3: Improve FHWA's stewardship and oversight of the VE Program.
Outcome:
To enhance FHWA's consistency with providing oversight of the VE programs and involvement with studies.
- Baseline: 2.4 (FY 2009)
- Target: 4.3 (FY 2016)
The baseline and target measures were developed using weighted average of the data collected from the annual VE reporting cycles. These measures are based on a weighted average of 30% for the FHWA Divisions engaged in VE studies, 30% for the FHWA Divisions verifying all required VE studies are conducted, and 40% for the FHWA Divisions stewardship and oversight of VE programs and studies.
Performance indicators:
- Divisions are engaged in VE studies.
- Baseline: 3.1 (FY 2009)
- Target: 4.2 (FY 2016)
Performance Metric: The data collected (question 20a) in the annual VE reporting cycle is converted to a numeric value and averaged as depicted in the following matrix:
| |
0 |
1 |
2 |
3 |
4 |
5 |
| Participating in VE studies |
No involvement |
Rarely (0-20 %) |
Seldom (21-40 %) |
Occasionally (41-60 %) |
Frequently 61-80 % |
Normally (80-100 %) |
- Number of Divisions verifying all required VE studies are conducted.
- -Baseline: 3.0 (FY 2009)
- -Target: 5.0 (FY 2016)
Performance Metric: The data collected (question 20d) in the annual VE reporting cycle is converted to a numeric value and averaged as depicted in the following matrix:
| |
0 |
1 |
2 |
3 |
4 |
5 |
| Verification of VE studies conducted |
0-5 |
6-20 |
21-35 |
26-39 |
40-51 |
52 |
- Enhance the consistency of FHWA's stewardship and oversight of VE.
- Baseline: 1.4 (FY 2009)
- Target: 3.7 (FY 2016)
Performance Metric: The data collected (question 19a) in the annual VE reporting cycle is converted to a numeric value and averaged as depicted in the following matrix.
| |
0 |
1 |
2 |
3 |
4 |
5 |
| Integration of VE in Divisions stewardship & oversight agreements, risk assessment, & reviews conducted |
VE is not included in Divisions stewardship & oversight agreement
VE is not included in annual risk assessment process |
Identified in Divisions stewardship & oversight agreement, work plan or standards operating procedures:
- When VE studies need to be conducted
- VE integrated in the planning & design sections of agreement &/or plans
VE is considered in Divisions annual risk assessment process |
Identified in Division's stewardship & oversight agreement, work plan or standard operating procedures:
- State DOTs VE policies & procedures referenced
- Division's VE coordinator & role described
|
Identified in Division's stewardship & oversight agreement, work plan or standard operating procedures:
- Division's VE roles & responsibilities
- Division's participation in VE studies
|
Identified in Division's stewardship & oversight agreement, work plan or standard operating procedures:
- Divisions role in reviewing VE study recommendations
- Divisions role in verifying VE recommendations are implemented
|
Identified in Division's stewardship & oversight agreement, work plan or standard operating procedures:
- Division's role in the monitoring, & reporting of VE programs
- Division's role with supporting improving a State DOTs VE program
|
|