FY 2024 FHWA Earmark Repurposing Questions & Answers
The purpose of these questions and answers (Q&As) is to provide technical advice to the Federal Highway Administration's (FHWA) division offices and State departments of transportation (State DOTs) on the repurposing of earmarked funding for Federal-aid projects pursuant to section 124 of the Department of Transportation Appropriations Act, 2024 (title I of division F of Public Law 118-42) (hereinafter "Repurposing Provision"). Unless otherwise indicated, the requirements described in these Q&As are found in the Repurposing Provision.
Except for the statutes and regulations cited, the contents of these Q&As do not have the force and effect of law and are not meant to bind the public in any way. These Q&As are intended only to provide clarity to States and territories regarding existing requirements under the law or agency policies.
- 1: What is the purpose of the Repurposing Provision?
- Answer 1: The purpose of the Repurposing Provision is to make funding available from earmarks and designated projects that have not been advanced by State DOTs. The limitations in the Repurposing Provision are to ensure the projects are obligated promptly and used in the same geographic area as the original earmark to provide funding for other needed projects eligible under the Surface Transportation Block Grant Program (STBG) (23 U.S.C. 133(b)), or the Territorial and Puerto Rico Highway Program (THP) (23 U.S.C. 165).
- 2: Must earmarks be repurposed?
- Answer 2: No. If an earmark is not repurposed, then it will remain unchanged and available for obligation.
- 3: Should all earmark repurposing requests be submitted this Federal fiscal year?
- Answer 3: Yes. Each FHWA division office should work with its respective State to ensure the division office has adequate time to review, approve, and submit all transfer requests in the Fiscal Management Information System (FMIS) Fund Control module prior to the submission deadline, September 6, 2024. If earmarks are not submitted for repurposing, the earmarks will remain unchanged with the original period of availability.
- 4: What is the basis for the requirement that applicable earmarks be designated before October 1, 2013?
- Answer 4: The Repurposing Provision states that an earmark must be authorized to be appropriated or appropriated "more than 10 fiscal years prior to the current fiscal year." The provision became effective in Fiscal Year (FY) 2024. As such, 10 years before FY 2024 is FY 2014, which began on October 1, 2013. Congress did not include earmarks under the Moving Ahead for Progress (MAP-21) which was authorized in FY 2012. Thus, for an earmark to be eligible, it must be identified in a prior law, report, or joint explanatory statement, which was authorized to be appropriated or appropriated before the end of FY 2013.
- 5: What does the requirement that the project be within the same geographic area and within 25 miles of the earmark mean?
- Answer 5: The repurposed funds may be obligated only on a new or existing project within 25 miles of the original earmark designation in the State. The 25-mile area can
be determined from any reasonable point from the location of the earmark, but the new or existing project must remain within the State.
- 6: Can the State choose an "area wide" project, such as a traffic signal upgrade program project in a specific city or county?
- Answer 6: Yes; however, to ensure the integrity of the earmark and use of funds, the "area wide" project must be limited to work within the 25-mile area of the
original earmark, and the project description should be clearly defined and
eligible under FHWA project authorization guidance. For example, the State may
not repurpose an earmark for an unidentified list of resurface projects in the
25-mile area.
- 7: If the earmark was for
‘Highway xx in an identified city,' is the 25-mile range from anywhere in the
city?
- Answer 7: No. The 25-mile radius is from any point on the specified highway or work
location in the identified city.
- 8: If an earmark is described as
"Statewide" or "anywhere in the State" in the authorizing legislation, how does
the 25-mile rule apply?
- Answer 8: Because the earmark is already authorized to be used anywhere in the State, the
25-mile rule is met regardless of where in the State the repurposed project is
located. The repurposed funds are only limited for use within the State for
which the funds were earmarked.
- 9: If Congress changed the
description of an earmark at any point prior to this provision, can it still be
repurposed?
- Answer 9: Yes. The repurposing should be based on the latest project description,
including applicable earmarks for which the original description was
subsequently revised by Congress provided it was authorized to be appropriated
or appropriated more than 10 fiscal years prior to the current fiscal year.
- 10: If an earmark was repurposed
under the FY 2016, through FY 2023 Repurposing Provisions or is repurposed
under the FY 2024 Repurposing Provision, can it be changed again?
- Answer 10: No. Once repurposed under the FY 2016 through FY 2023 Repurposing Provisions or
the FY 2024 Repurposing Provision, the project description no longer meets the
requirement of the Repurposing Provision that the project be described in
applicable legislation or a report identified by Congress and, as such, cannot
be further repurposed.
- 11: Can discretionary awards made
by the Secretary without Congressional identification be repurposed?
- Answer 11: No. If the project was not identified by Congress in applicable legislation or
report and the Secretary used discretion to select projects in a discretionary
program, the funds may not be repurposed under the Repurposing Provision.
- 12: Can earmarked funds that were
transferred to another agency be repurposed under the Repurposing Provision?
- Answer 12: No. The Repurposing Provision applies only to funds being administered by FHWA.
- 13: If an earmark was revised
during the 2012 repurposing activity for specific 2003 to 2006 earmarks carried
out by the Secretary, can the earmark be repurposed under this action?
- Answer 13: No. The description of the earmark has been changed by that action and is no
longer as "identified" in applicable legislation.
- 14: If earmarks were obligated
10% or more as of October 1, 2023, and the earmarked funds subsequently were deobligated after October 1, 2023, does the project then
qualify under the "less than 10%" provision and not require project closeouts?
- Answer 14: No. The Repurposing Provision provides a specific cut-off date for the 10%
requirement, which is October 1 of the current fiscal year (i.e. October 1,
2023). Earmarks that are obligated 10% or more as of October 1, 2023, must be
closed in the Fiscal Management Information System (FMIS) and final vouchered
before they can be considered for repurposing. All of
the funds deobligated from the closed project(s) for
the earmark may be considered for repurposing. Project closure may occur at any
time before the deadline for repurposing earmarks.
- 15: Can funds deobligated
after October 1, 2023, also be repurposed?
- Answer 15: Yes. But if the obligation amount exceeded 10% on October 1, 2023, the earmark
project(s) must still be final vouchered and closed in FMIS.
- 16: What does "have been closed
and for which payments have been made under a final voucher" really mean for
earmarks that are 10% or more obligated?
- Answer 16: A closed project means closed in FMIS. If the project is not a FMIS project,
the State must certify the project is closed. Final voucher paid means the
State has requested final payment from FHWA based on final project estimates.
The State should consider if additional funding is needed to make the started
earmark project functional before it considers repurposing the remaining
earmark funds. All projects related to the earmark must have a final voucher
and be closed for the funds to be eligible for repurposing.
- 17: If a portion of the funds for
an earmark was previously transferred to another agency, can the remaining
balance retained by FHWA be used for repurposing?
- Answer 17: Yes. The State must certify that the project is closed and may repurpose the
remaining balance that is administered by FHWA. Stated differently, if funds
were previously transferred to another agency, only funds returned to FHWA
(currently administered by FHWA) can be repurposed under this provision.
- 18: Earmark funds are obligated
on two different Federal-aid project agreements, each for 5% of the earmark
amount. Must both project agreements be closed to repurpose the balance?
- Answer 18: Yes. If the total amount obligated from the earmark meets or exceeds the 10%
limit, then all projects must be final vouchered and closed.
- 19: Do earmarks that are final
vouchered and closed need to have been authorized to be appropriated or
appropriated before FY 2014?
- Answer 19: Yes. All earmarks must have been authorized
to be appropriated or appropriated in legislation before FY 2014 to be
considered for repurposing.
- 20: What are the requirements to
obligate funds repurposed under the Repurposing Provision?
- Answer 20: Standard Federal-aid requirements will apply for obligation. The obligation of
the funds must be for the project identified during repurposing. Please see the
FHWA's Office of the Chief Financial Officer's (HCF) memo titled "Project Funds
Management Guide for State Grants" dated May 23, 2018, for
additional information.
- 21: How long are the funds and obligation
authority available for obligation?
- Answer 21: From the date a repurposing request is
submitted by the State, funds may be obligated up to 3 years after the fiscal
year of the request. Therefore, repurposed funds from requests submitted in FY
2024 must be obligated by September 30, 2027. Unobligated balances will lapse
on that date.
- 22: Does the FY 2024 Repurposing
Provision change the time by which FY 2016 through FY 2023 repurposed earmarks
must be obligated?
- Answer 22: No. The FY 2016, FY 2017, FY 2018, FY 2019, and FY 2020 repurposed earmarked
funding not obligated by September 30, 2019, September 30, 2020, September 30,
2021, September 30, 2022, and September 30, 2023
respectively, has lapsed. The FY 2021 repurposed earmarked funding must be
obligated by September 30, 2024, the FY 2022 repurposed earmarked funding must
be obligated by September 30, 2025, the FY 2023 repurposed earmarked funding
must be obligated by September 30, 2026.
- 23: What happens if earmarked
funding repurposed in FY 2021 is not obligated by September 30, 2024?
- Answer 23: Funding repurposed under the FY 2021 Repurposing Provision must be obligated on
the project designated in the FY 2021 repurposing request by September 30,
2024. If the funds are not obligated by September 30, 2024, then the funds will
lapse and will no longer be available for obligation, resulting in the loss of
the funds.
- 24: Will FHWA grant any
extensions to the September 30, 2024, obligation deadline for the FY 2021
repurposed earmarks?
- Answer 24: No. The Repurposing Provision explicitly states that the repurposed funds
expire three fiscal years after the fiscal year of repurposing. FHWA does not
have the authority to extend this deadline.
- 25: How can Divisions/States
track the unobligated balances that have been repurposed?
- Answer 25: In FMIS, the Divisions/States can use the repurposed program codes to track the
unobligated balances of funds repurposed.
- 26: Is there a limited time period to expend obligations?
- Answer 26: For funds from the Highway Trust Fund (i.e., contract authority), the obligated
funds are available until expended, but the project can become inactive if it
is not proceeding. For funds from the General Fund (i.e., appropriated budget
authority), the funds will be cancelled 5 years after the period of
availability, September 30, 2032, and will no longer be available for
expenditure.
- 27: Can earmark project funds
from expired programs be repurposed?
- Answer 27: Earmark funds that are in an expired fund category for a program can be
repurposed only in limited circumstances. Only expired funds from the Highway
Trust Fund that have been deobligated in the current
fiscal year can be repurposed. The repurposed project must then be obligated in
the same fiscal year (e.g., before the end of FY 2024), pursuant to 23 U.S.C.
118(c). The expired status of the funds cannot be changed, which means that
they will lapse at the end of the fiscal year if not properly obligated.
Examples of programs to which this may apply are the Public Lands Highways
Discretionary Program and the Transportation, Community, and System
Preservation Program (TCSP) where Congress designated the projects from these
discretionary programs. If the project was not specifically designated by
Congress, then it is not eligible for repurposing. A new program code will need
to be identified and a demo ID provided, after which the State will follow the
standard repurposing process. Due to the need to obligate these funds by the
end of the FY 2024, such requests should be identified for priority processing.
- 28: Does the list of earmarks and
allocated funds prepared by HCF identify the only earmarks and allocated funds
that can be considered for repurposing?
- Answer 28: No. The list may not include all the earmarks and funding programs that may be
eligible under the Repurposing Provision. However, it will give States a
summation of the projects that could be considered. States should work with
their FHWA division offices to ensure all earmarks and allocated funds listed
or otherwise identified meet the repurposing eligibility criteria and the
amount of funds is available. If a State identifies an earmark that is not
listed, it should provide the name, the original amount, and the legislation
for the earmark. The funds must be allocated in FMIS before the repurposing
process can take place. In addition, if an earmark is not on the list, it may
require the Financial Systems Team to establish a new program code for the repurposed
funding.
- 29: Why are some of the demo IDs
repeated on the earmark lists?
- Answer 29: Some demo IDs have multiple program codes and were identified from more than
one law, so the report filter created more than one line for the demo ID.
Please refer to the FMIS N25A report for details on the correct program code
and the amount of funding available for each program code.
- 30: Some earmarks are missing
from the published list on FHWA's website compared to the lists we obtained
from other sources. Where are those projects?
- Answer 30: A few earmarks were allocated under two different program codes, specifically
- SAFETEA-LU HPP earmarks.
In some instances, one program code was obligated more than 10% and the other
program code was not. If the earmark, in total, has obligations 10% or greater,
then it is not eligible unless the FMIS project agreement(s) has been final
vouchered and closed. Such instances will not be on the FHWA published list of
projects less than 10% obligated. Please review the FMIS N25A report to ensure
the earmark meets the less than 10% obligated requirement. The projects may be
on the list of earmarks obligated greater than 10%.
- 31: Why are there negative
unobligated balances on the FMIS N25A report for some earmarks (or Demo IDs)?
- Answer 31: Some demo contract authority was permitted to be used on other demos for
various reasons, including advance funding authority under the High Priority
Projects program. If your State has a demo with a negative unobligated balance,
you should identify which demo was used to balance the funds. A State should
not transfer funds if the funds were used under a different demo even if the
balance appears on the N25A as unobligated.
- 32: Who has the authority to
request repurposing of an earmark that appears to be for a local agency?
- Answer 32: The Repurposing Provision provides the authority for a State to repurpose any
earmark that was designated on or before September 30, 2013 "located within the
boundary of the State or territory". The only requirement for the State is that
the repurposed project must be within 25 miles of the designation, within the
State, and eligible for STBG or THP.
- 33: Should the State use the
repurposed transfer form (FHWA 1575 (ERP 2023)) to request repurposing?
- Answer 33: No. The Repurposed Earmark Transfer Request process has been automated within
the Fiscal Management Information System (FMIS). The State, FHWA division office, and the FHWA
Office of the Chief Financial Officer (HCF) will process earmark repurposing
requests as provided in the attached procedures using the FMIS Fund Control
module.
- 34: How detailed does the new
project description on the repurpose request need to be?
- Answer 34: The project description should clearly define the scope of work and the project
location that the funds will be obligated on before the end of the availability
period. Please see the HCF memo titled "Project Funds
Management Guide for State Grants" dated May 23, 2018, for
additional information. The project description does not need to specify the
phase of work, i.e., preliminary engineering (PE), right-of-way activities, or
construction. The State should provide
the information of the new project(s) description(s) and the amount of funds
for each project of the repurpose request in the "Enter Detail #, Pooled Fund
Project Description, or any additional information" section of the FMIS
transfer request.
- 35: Can "placeholder" or "backup"
projects be identified during repurposing process?
- Answer 35: No. The actual projects the State plans to obligate funds on must be identified with the amount of repurposed funds to be obligated on that project. Token amounts of funding for a project will not be considered.
- The State should identify the amount it intends to obligate to each project, understanding that some
adjustments might occur due to estimates. For example, if the earmark has
$300,000 available, and the State identifies 3 projects on which it intends to obligate
$100,000 each, each project should get $100,000, with minor adjustments for
estimates. The State should not distribute the funds to multiple projects and
then, for example, obligate all the funding on one of them. Also, see questions
#38, and #39.
- 36: Does the Federal-aid number
need to be identified at the time of repurposing?
- Answer 36: No, the Federal-aid number can be identified later at the time of obligation.
- 37: Do any Federal-aid
requirements need to be met before the funds can be repurposed to the new
project, including being on the STIP?
- Answer 37: No. Federal-aid requirements must be addressed before obligation (23 CFR
630.106(a)(2)), but not before the earmark funds are approved for repurposing.
The only requirement is identifying the eligible project(s) for use of the
earmark funds.
- 38: How specific should the
amount be for the project identified to receive the repurposed funds?
- Answer 38: The amount should be a realistic amount the State intends to obligate for the
project based upon the current project cost estimate. "Token" amounts may not
be identified with the intent to provide options for the earmark funding use.
See Question #35.
- 39: If the project estimate is
more than was anticipated when the repurpose request was submitted, can a State
DOT obligate more funds to a repurposed earmark project from other projects
identified on the repurpose transfer request?
- Answer 39: Question #35 specifies that the amount and projects identified on the
repurposed transfer request need to be specific. Thus, only minor modifications
should be made between identified projects on a repurposed transfer request.
The State should use other funding sources if the final estimate significantly
exceeds the funds identified for a project rather than significantly
redistributing earmark funds identified for another project.
- 40: What is the purpose of the
earmark certification section?
- Answer 40: The certification statements for both the State DOT and the FHWA Division
Administrator (DA) provide clearly defined and consistently applied assurance
that the requested repurposing meets the eligibility criteria set forth in the
Repurposing Provision.
- 41: What is FHWA's role in
determining which earmarks to repurpose and on what projects to utilize the
repurposed funds?
- Answer 41: The FHWA divisions work with States to ensure the Repurposing Provision's
requirements are met for repurposing, such as the requirements that: an
eligible earmark has less than 10% of the funds obligated or the State has
demonstrated that it was complete; the repurposed project is for an eligible
activity; and the repurposed project is within 25 miles of the original
location and is in the same State as the original earmark. However, it is a State's decision as to which eligible earmarks to repurpose
and on which qualified projects to utilize those repurposed funds.
- The DA's approval of a State's repurposing request constitutes FHWA's concurrence
that (1) the repurposed earmark request meets the criteria for repurposing, and
(2) any new proposed projects are STBG (or THP) eligible, was authorized to be
appropriated or appropriated more than 10 FYs prior to the current FY, within
25 miles of the earmark description, and within the State.
- 42: Can the DA delegate approval
of these requests?
- Answer 42: The DA can delegate the approval to the Deputy Division Administrator (DDA) or
Chief Operating Officer (COO). The DA's approval (or DDA/COO's approval, as
delegated) is required to ensure the appropriate level of, and multi-discipline
review has been completed.
- 43: Can States request an
extension to submit earmark repurposing requests beyond the September 6, 2024 deadline, if the State does not intend to obligate
before the end of the fiscal year?
- Answer 43: No. Extensions cannot be considered. For requests to be processed before the
end of the fiscal year and to be considered valid for processing, FHWA division
offices must submit repurposing requests in the FMIS Fund Control module by the
deadline provided.
- 44: Must the State do any annual
reporting?
- Answer 44: Yes. States must submit an annual report as required by the Repurposing
Provision.
- However, FHWA will
facilitate these reports by providing the States a consolidated report
containing the project identified and approved for repurposing during the
fiscal year. The State should provide the FHWA division office a letter
certifying the accuracy of the list. The reports are required only from States
that made a request to repurpose earmarks. Once the FY 2024 earmark repurposing
requests are fully processed for all States, FHWA will provide additional
information to the States about the exact process and timeline.
- 45: To whom should the State send
the certification letter and what does it need to include?
- Answer 45: The State or territory should send the certification letter to the DA. The
letter should state that the funds from the earmark projects shown in the
attachment (which HCF will provide) will be obligated only for the respective
projects which are eligible under the Repurposing Provision (section 124 of the
Department of Transportation Appropriations Act, 2024, title I division F of
Pub. L. 118-42). The letter may address any corrections that are consistent
with and that do not change the original request as submitted in the FMIS Fund
Control module. Please ensure the list of projects is attached to the letter.
- 46: Can FHWA prioritize certain
projects for processing?
- Answer 46: No. Repurposing requests will be
processed on a first-come-first-serve basis. If the State needs a request
processed early, it should submit early. If a project is advancing before the
repurpose request can be processed, the State DOT should use an advance
construction authorization for the project. Other funds may not be obligated as
a placeholder.
- 47: Is obligation limitation
associated with repurposed funds subject to August Redistribution?
- Answer 47: No. While some obligation limitation may be subject to August Redistribution
prior to repurposing, such as the limitation for allocated programs, once funds
are repurposed, the associated obligation limitation is no longer subject to
August Redistribution.
- 48: Are earmarks that are not
subject to obligation limitation required to use annual formula limitation
after repurposing?
- Answer 48: No. Only funds that are subject to obligation limitation and do not have
obligation limitation remaining available will need to use annual formula
obligation limitation.
- 49: How can the State determine
how much obligation limitation is available for the earmark?
- Answer 49: If the funds have not been allocated in FMIS, the relevant program office
should be able to provide that information. If the funds have been allocated,
first go to the "Fund Control Menu" in FMIS and look up the applicable program
code. See the "Limitation Type" column. Then go back to the "Fund control"
menu, select "Limitation – Balances". Select the appropriate limit type and
determine if the limit is "Limit by Demo".
- 50: What is the difference
between Contract Authority (CA) and Obligation Limitation (or authority)? How
does it impact the ability to obligate these repurposed funds?
- Answer 50: The CA (also referred to as the "funds") is the actual amount of funding
authorized to be used for a purpose by Congress in the applicable legislation
and may be obligated in advance of appropriations. The CA is typically provided
in multi-year laws. To limit the CA from multi-year legislation into the annual
budget and appropriations process, Congress establishes a maximum amount of the
CA that can be obligated in each fiscal year in an appropriation act. This is
referred to as obligation authority (OA) or obligation limitation (used
interchangeably in FHWA). The States receive annual formula OA based upon a
ratio of the amount of CA the State receives that must be used in conjunction
with apportioned funds. States may also receive OA in conjunction with certain
allocated program funds. "Special OA" may be provided for an extended period,
such as the fiscal year plus 3 years, or may be provided as "available until
expended." The amount of OA is typically less than the CA. For this reason,
many of the earmarks have more CA available than OA. In this case, the State
must use annual formula OA for any excess CA if they wish to obligate the
balance exceeding the OA originally provided for the earmark. Annual formula OA
will not be impacted when the funds are repurposed. The annual formula OA will
only be impacted in the FY the funds are obligated.
- Finally, some CA is provided as "exempt" from
obligation limitation and is not subject to any limitation when obligated.
- It should be noted that
most Federal funds, other than those from the Highway Trust Fund, are provided
as appropriated budget authority (BA), typically within an appropriations act.
The appropriated BA does not require additional OA to be obligated because
appropriated BA is limited directly by the appropriations which made it
available. Unless stated otherwise in law, appropriated BA is available to be
obligated for one year.
- 51: What are the various types of
obligation limitation that could be affected by earmark repurposing?
- Answer 51: Please see Appendix 1 in this document for an explanation of the obligation
limitation.
- Question 52: If the earmark has more CA than OA, and the State does not wish to use the
formula OA for the repurposed funds, does the State need to repurpose the full
amount available for the earmark?
- Answer 52: Yes,
the State should repurpose the full amount of CA even if it does not plan to
use formula OA to obligate the excess CA. This is an acceptable variance from
Question #35 to take into account the excess CA.
- 53: Can the repurposed funds be
used to replace previously obligated funds on an existing project?
- Answer 53: No. Pursuant to 23 CFR 630.110(a), properly obligated funds may not be
replaced. A State may use repurposed funds to add additional funds to a project
due to a need for additional obligations or to convert advance construction as long as that project is identified at the time the
repurposing is originally requested.
- 54: If a repurposed project is
completed, can excess funds deobligated from the
project due to cost underruns be re-obligated on another project?
- Answer 54: Once a project is repurposed, the project description no longer meets the
requirement of the Repurposing Provision that the project be described in
applicable legislation or a report identified by Congress and, as such, cannot
be further repurposed. Therefore, if a repurposed project is completed and
excess funds are deobligated, the unobligated funds
may be used only on another project from the same earmark identified on the
previously submitted repurposed transfer request. In addition, for contract
authority funding after the period of availability, the reobligation
must occur in the same fiscal year as the deobligation.
Moreover, the original obligation must have been proper (an amount was not
obligated in excess of the estimate to complete the
project authorized or before the project was ready to proceed), and the deobligation must have been for a valid reason complying
with 23 CFR 630.110(a).
- 55: Can the repurposed funds be
transferred to another agency or Federal Lands to carry out a project or
projects?
- Answer 55: Yes, based upon authorized transfer procedures as described in FHWA Order
4551.1.
- If funds are being
transferred to another agency, e.g., the Federal Transit Administration, the
repurpose transfer process should be followed first. The State should submit the repurpose
transfer request in the FMIS Fund Control module. Then, a request to transfer
the repurposed funding to Federal Lands or another agency should be submitted
following the normal process after the funds are repurposed.
- 56: Can the repurposed funds be
used to convert advance construction (AC)?
- Answer 56: Yes. As long as the project was properly identified
during the repurposing process, the funds may be used to convert AC.
- 57: Can toll credits be used with
the repurposed funds?
- Answer 57: If the earmark was previously eligible to use toll credits as non-Federal
share, then the repurposed funds may also use toll credits as the non-Federal
share.
- 58: Does PE or right-of-way
payback apply to the original earmark?
- Answer 58: If the earmark, as written, was specifically for PE (e.g., design activities)
or right-of-way acquisition, then consistent with FHWA Order 5020.1A, "Repayment
of Preliminary Engineering Costs", dated June 8, 2018,
the project is not subject to PE or right-of-way reimbursement to FHWA because
the earmark had a specific limited purpose. If the State did use part of earmarked
funds for PE or right-of-way activities that were intended to include
construction prior to repurposing and the amount obligated was less than 10% of
the earmark, the earmark may be repurposed, but the expended funds for PE or
right-of-way activities will be subject the applicable reimbursement
provisions. If the State spent 10% or more of the earmark intended for
construction for PE or right- of-way activities, the project cannot be
considered complete. If the State promptly pays back those activities, the
funds could be considered for repurposing.
Appendix 1 (to FY 2024 Earmark Repurposing Q&A): Response to Question 51
What are the various types of obligation limitation that could be affected by earmark repurposing?
Answer 51: Earmarks have various types of limitation. The State's funds and limitation balances on the FMIS W10A report may change category after repurposing of an earmark. The following are descriptions of the different limitation types:
1) Special limitation for specific earmarks at the program level.
a) All earmarks from the same program draw their limitation from the associated limitation pool. The limitation pool amounts may match the allocated funds at 100% or less. Examples of special limitation at the program level include: Transportation Improvements (program code LY30); TEA-21 High Priority Projects (program code Q920); and Projects of Regional and National Significance (program code LY40). To repurpose an earmark which has program level pool limitation:
(1) Determine the limitation type from the Program Code Crosswalk. See column "PC Type Description (limitation type)".
(2) Refresh the Business Objects report "Lim buckets by Demo ID" to get the total amount of contract authority contrasted to the total amount of limitation which is available for the program. See example below.

(3) If the total Available Limitation is equal to Total Unobligated Funds, then the total unobligated balance of the Demo ID would be repurposed to the program code shown on the crosswalk in column (-B-).
(4) If Available Limitation is less than the Total Unobligated Funds, then the State would repurpose the earmark fund balance using the program codes shown on the crosswalk in columns (-B-) and (-C-) depending upon the amount of available limitation the State determines to use for the repurposed earmark funds. However, the remaining total limitation balance for the program cannot exceed the remaining total unobligated balance of funds for all earmarks in the associated program.
2) Special limitation authorized only for a specific earmark within a program.
a) High Priority Projects authorized in SAFETEA-LU section 1602 #1-3676 have limitation assigned to each earmark (e.g., by Demo ID). The limitation type is Limited by Demo.
To repurpose one of the earmarks from this program:
(1) Look up the amount of available limitation for the
specific Demo ID from the FMIS Fund Control Limitation Balances screen. Filter
for your State and Limited by Demo. Then expand Details and open View Limit by
Demo ID.
(2) Lookup the available limitation for both program codes HY10 and LY10. These amounts must be repurposed to program code RPS7.
(3) The excess contract authority (funds which have no matching obligation authority) must be
repurposed to program code RPF7.
3) Earmarks which draw from annual limitation.
a) Refer to the Program Code Crosswalk and the Business Objects "Lim Buckets by Demo ID" report to identify by Demo ID or
program code which earmarks (or programs) draw from Charged to Limitation balances.

b) When earmarks with discretionary limitation are
repurposed from the State's existing allocated funds, the State may see a
change in their Charged to Limitation account balance. This limitation was
previously allocated to the State for these funds. When funds are repurposed to RPS5, then the applicable amount of limitation will be moved from the "FUNDS SUBJ TO ANNUAL OBLIG LIM" section
of the W10A "TOTAL ANNUAL OBLIG LIM" to the special limitation category "TOTAL SPECIAL LIM".
4) Exempt from limitation and non-Federal-aid limitation.
a) For program codes shown on the crosswalk as Exempt and Non-Federal-aid in the PC Type
column, use the program codes shown on the crosswalk – RPE7 and RN#7. The State's limitation balances will not
change.
b) The fund amounts on the W10A report will continue to be shown in the Exempt category and the Other
category, as appropriate.
RPF7 note: Funds repurposed to program code RPF7 will
draw from the State's formula limitation balance at the time that the funds are obligated. If the funds are not obligated and lapse, the limitation
will not be affected.
RPS7 note: Special limitation for funds repurposed to program code RPS7 will expire at the end of FY 2027.
All repurposed funds will show unobligated balances as "Possible Lapse Fiscal Year End" 2027 column
when visible on the W10A report (in FY 2025).