The following activities require coordination between FHWA and MoDOT in order to attain reviews/approvals within the agreed timeframes. In this agreement, all reference to days denotes calendar days, unless otherwise noted. FHWA and MoDOT agree to work as true partners to ensure the success of the Environmental Program.
The following table identifies the various approval/review activities.
Activities | MoDOT/FHWA Responsibilities | |||
---|---|---|---|---|
Approval Action | Reference Document | Approving Agency, Review Timeframe | MoDOT | FHWA |
Programmatic Categorical Exclusion (PCE) |
23 CFR 771 Programmatic Agreement for CEs |
FHWA, 3 business days |
|
Verifies use of the Programmatic CE when requested Reviews quarterly submittal for risk- based stewardship and oversight purposes |
Documented Categorical Exclusion (CE2) or revisions based on FHWA comments |
23 CFR 771 |
FHWA, 2 weeks |
Provides a completed CE2 and related source documents (such as surveys, studies, PI material, etc.) to FHWA prior to needed action |
Requests additional information, provides comments or approval to MoDOT |
Environmental Assessment (EA) | 40 CFR 1500 23 CFR 771 TA 6640.8A |
FHWA, 4 weeks |
Provides a complete submittal to FHWA prior to needed action | Requests additional information, provides comments or approval to MoDOT |
Finding of No Significant Impacts | 40 CFR 1500 23 CFR 771 TA 6640.8A |
FHWA, 4 weeks |
Provides a complete submittal to FHWA prior to needed action | Requests additional information, provides comments or approval to MoDOT |
NEPA Coordination Plan |
SAFETEA- LU Section 6002 FAST Act Section 1304 |
FHWA, 2 weeks |
Provides a complete submittal to FHWA prior to needed action | Requests additional information and provides comments to MoDOT |
Classes of Action | 23 CFR 771 | FHWA, 2 weeks |
Provides a complete submittal to FHWA prior to needed action |
Requests additional information and provides comments to MoDOT |
Purpose and Need | 40 CFR 1500 23CFR 771 TA 6640.8A |
FHWA, 4 weeks |
Provides a complete submittal to FHWA prior to needed action | Requests additional information and provides comments to MoDOT |
Environmental Impact Statement (EIS) and FEIS/ROD combined |
40 CFR 1500 23 CFR 771 TA 6640.8A |
FHWA, 8 weeks |
Provides a complete submittal to FHWA prior to needed action | Requests additional information, provides comments or approval to MoDOT |
Record of Decision | 40 CFR 1500 23 CFR 771 TA 6640.8A |
FHWA, 4 weeks |
Provides a complete submittal to FHWA prior to needed action | Requests additional information, provides comments or approval to MoDOT |
EA, EIS, 4(f) revised to address FHWA comments |
40 CFR 1500 23 CFR 771 23 CFR 774 TA 6640.8A |
MoDOT, 3 weeks* FHWA, 4 weeks |
Provides revised copies that clearly indicate the changes that were requested from receipt of complete information from districts |
Provides comments or approval to MoDOT including legal sufficiency review when appropriate |
CE and EA/EIS Reevaluations | 23 CFR 771 | FHWA, 2 & 4 weeks, respectively |
Provides a complete submittal to the FHWA prior to needed action | Requests additional information, provides comments or approval to MoDOT |
Section 106 Compliance | 36 CFR 800 |
FHWA, 4 weeks |
Provides a complete submittal to the FHWA prior to needed action | Provides documentation to the Advisory Council on Historic Preservation and other consulting parties (tribes, historic organizations, etc.) requesting consultation determination and reviews and approves MOAs. |
Section 4(f) de minimis | 23 CFR 774 |
FHWA, 2 weeks |
Provides a complete submittal to the FHWA prior to needed action | Requests additional information, provides comments or approval to MoDOT |
Programmatic Section 4(f) | 23 CFR 774 |
FHWA, 4 weeks |
Provides a complete submittal to FHWA prior to needed action | Requests additional information; provides comments or approval to MoDOT |
Individual Section 4(f) Evaluation | 23 CFR 774 |
FHWA, 6 weeks |
Provides a complete submittal to FHWA prior to needed action | Requests additional information, provides comments or approval to MoDOT |
Biological Assessment (BA) under ESA for LAA | ESA |
FHWA, 2 weeks |
Provides complete submittal to FHWA prior to needed action | Requests additional information, provides comments to MoDOT for revision and submits to US FWS |
PEL Coordination Review Points |
23 CFR 450 23 USC 168 PEL Questionnaire |
FHWA, 2 weeks |
Provides complete submittal to FHWA prior to needed action | Requests additional information, provides comments or approval to MoDOT |
Final PEL Documentation | 23 CFR 450 23 USC 168 PEL Questionnaire |
FHWA, 4 weeks |
Provides a complete submittal to the FHWA prior to needed action | Requests additional information, provides comments or approval to MoDOT |
NEPA document public involvement material for EA/EISs |
EPG 129 | Concurrent with MoDOT review and determined by current schedule |
Include FHWA on all correspondence outlined in the EPG | Provide comments or approval to MoDOT |
*from receipt of complete information from districts
This agreement will be reviewed and updated, as needed, on an annual basis.
IN WITNESS WHEREOF, the parties have entered into this Agreement on the date last written below.
FHWA:
[DIGITALLY SIGNED]
Date: 2025.01.15 10:53:34 -06'00'
Rebecca Rost
FHWA-MO Division Environmental Specialist
(573) 638-2623
MISSOURI DEPARTMENT OF TRANSPORTATION:
[DIGITALLY SIGNED]
Date: 2025.01.15 08:44:20 -06'00'
Melissa Scheperle
MoDOT Environmental and Historic Preservation Manager
(573) 526-6684