This memo is superseded by the Department of Labor Final Rule 12/20/2000
Supplemental Information Relative to Implementation of the Midway Decision
The following information is offered as supplemental guidance in response to questions and scenarios that have been brought to our attention from the various field offices since the Midway Decision was issued.
Questions:
- What is the effective date for implementation of policy changes arising from the Midway Decision?
May 17, 1991, the date of the court's decision, is the effective date, since all motions for rehearing were denied and the parties in question never petitioned to the Supreme Court.
- What projects may the Midway Decision affect?
The decision may affect Federal-aid construction projects that were authorized on or after May 17, 1991, as well as work that occurred on or after May 17 on projects authorized prior to that date.
The impact of Midway to existing and completed projects will depend upon the number of contractors who desire to make adjustments in payments made to truck drivers pursuant to the ruling and States' reactions to such requests. States with their own minimum wage legislation may find that such statutes preclude any adjustment.
- Does the Midway Decision have applicability to owner/operators?
No, there is no impact on owner/operator trucking agreements. Davis-Bacon wage rates do not apply to any type of owner/operator transaction, including trucking.
- Has the Midway Decision ruling affected the Department of Labor's (DOL's) policy involving hauling operations from the project site to a "non-dedicated" off-site facility?
Yes, the Court's decision held that DOL's regulation, 29 CFR Section 5.2(j), defining "construction" to include the hauling of materials to and from a construction site, is invalid because it conflicts with the language of the Davis-Bacon Act in that such hauling is not performed "directly on the site of the work." As a result, the Court concluded that truck drivers engaged in hauling materials and supplies to and from a construction site are not employed "on the site of the work" and, therefore, the DOL is without statutory authority to extend the prevailing rate requirement to such drivers. It is noted that this application is in reference to only those hauling operations to and from an "off-site" facility that has been determined to be "non-dedicated."
- In view of the Midway Decision, a number of inquiries have been made regarding applicability of Davis-Bacon wage rates under several scenarios of truck/hauler operations involving various "off-site facilities." To properly address each scenario, the "off-site facility" must be evaluated to assure it meets the criteria for "site of the work" as defined in DOL's regulations (29 CFR 5.2). The criteria is as follows:
An "off-site" facility that comes under the definition of "site of the work" must be considered "dedicated exclusively" to the performance of the contract, and be so located in proximity to the actual construction location that it would be reasonable to include it.
An evaluation of the "off-site" facility should address the following issues:
- Does the "off-site" facility exist because of the Federal-aid project? If the answer is yes, then it probably meets the "dedicated exclusively" criteria, which means all truckers hauling from this facility to the project site and from the project site to the facility, regardless of whom they are employed by, are covered by Davis-Bacon wage rates.
However, when it comes to certain "off-site" facilities, such as borrow or waste pits, one must also examine whether or not it has a "commercial nature". This can be done by answering the following questions:
- Was the "off-site" facility established by a commercial supplier or materialman prior to award of the project?
- Will the "off-site" facility be used for multiple purposes (by other projects, i.e., State or the private sector)?
If the answer is yes to either of these questions, then the "off-site" facility most likely cannot be considered "dedicated exclusively" and be included as part of the "site of the work", even when the operations for a period of time may appear dedicated exclusively, or nearly so, to the performance of the contract.
- If the "off site" facility being evaluated is determined to meet the "dedicated exclusively" portion of the criteria, it next must be tested to assure it also meets the "in proximity to" portion. To accomplish this, several factors should be examined. These include:
- the type/nature of the project, and
- the geographical elements involved (i.e., geological and whether the project is in an urban or rural location).
The key word in this test is "reasonable." The determination of reasonableness is very subjective and best left to be determined at the local or State level based on the factors involved. For this reason, no specified distance limitations have been developed as they may vary from State to State and region to region.
- Scenarios that involve major route/corridor type work that consists of multiple adjacent contracts/projects and/or different contractors represent a unique set of circumstances. As a general rule, if such a group of projects have "off-site" facilities that meet the test criteria noted above for being "dedicated exclusively" and "in proximity to" for the "group of projects" only, then such facilities can be considered to be included in the definition of "site of the work." This would include "shared" facilities from different contracts/projects by the same contractor, as well as, the possibility of "shared" facilities from different contracts/projects by different contractors.
- Does the "off-site" facility exist because of the Federal-aid project? If the answer is yes, then it probably meets the "dedicated exclusively" criteria, which means all truckers hauling from this facility to the project site and from the project site to the facility, regardless of whom they are employed by, are covered by Davis-Bacon wage rates.
- In light of the Midway Decision, how will determinations be made with regard to "split-trip" operations?
Due to the Midway Decision, contractors will need to establish payroll records that indicate the times that truck drivers are hauling under conditions that meet the criteria for Davis-Bacon coverage and the times when conditions do not meet the criteria. Since wage determinations are usually based on hourly increments, the wage rate that dominates for any given hour of the day will depend on the type of operation that dominates for that given hour of the day.
In cases where the legs of the trip are split (i.e., hauling from a commercial site to the project site in one leg of the trip, then hauling from the project site to a "dedicated exclusively" off-site facility in the other leg), DOL has in the past ruled the trip-leg that meets the criteria for Davis-Bacon wage rate coverage will dominate the wage coverage determination for that entire operation. It is noted that the impact of the Midway Decision on this "split-trip" issue is currently being examined in the Ames Construction Case. Until a decision is conclusively reached on this matter, DOL's current policy will stand with respect to the Midway Decision.
Application Scenarios:
Using the guidance provided above, the following scenarios furnished by the field offices are now examined to demonstrate the application of Davis-Bacon to truck drivers under Midway:
(Remember, whether or not the truck drivers are directly employed by the government contractor is no longer a relevant factor.)
Scenario 1: | A trucking firm is contracted to haul materials from a commercial production source. The contract may be with the supplier or the prime contractor. (The work is not covered under the Davis-Bacon Act.) |
Scenario 2: | The prime contractor hires drivers to operate trucks from a commercial production source. (The work is not covered under the Davis-Bacon Act.) |
Scenario 3: | A project involves milling a bituminous overlay from concrete pavement, rubblizing and hauling off old concrete pavement, re-compacting the subgrade, placing a lime treatment on the subgrade, placing a Portland cement treated base, followed by Portland Cement Concrete Pavement. A trucking firm is subcontracted to do the following:
|
Scenario 4: | The project involves hauling excavated earth from various locations on the project to other locations on the same project and from a borrow site established by the contractor at the same location as the commercial hot mix plant. The hot mix plant is located within a reasonable hauling distance to the project site. The prime contractor owns several trucks capable of hauling both dirt and bituminous material and does the following work:
|
Scenario 5: | The project involves grading and bituminous surfacing of an existing roadway for a distance of 16 km (10 miles) with limited right of way. The plans call for the roadway to be widened and the shoulders to be stabilized. Included in the plans is a requirement for the contractor to furnish embankment from a location approved by the State. The contractor locates an area approximately 3.2 km (2 miles) from the nearest point of the project. The haul road from the borrow area intersects the project midway through the project. The contractor is required to strip vegetation from the area and, by an agreement with the land owner, stockpile the top soil which will be replaced after use of the borrow pit is no longer needed. The contractor subcontracts a trucking firm to:
|
Scenario 6: | A contract is awarded to a company who has just completed a similar project during the later part of the preceding construction season. This project abuts one end of the project completed the preceding season and is of the same design. The contractor cannot locate an acceptable borrow pit site within reasonable hauling distance, however, there is a commercial quarry located within an acceptable distance from the project. An agreement is made with the quarry owner to allow the prime contractor to remove overburden from part of his quarry to be purchased and used for roadway embankment material. The owner of the quarry will take both original and final cross sections for measurement of the site of which borrow is purchased. The contractor moves in his own fleet of trucks to:
|
Scenario 7: | A contract is awarded to a company who has just completed a similar project during the later part of the preceding construction season. This project abuts one end of the project completed the preceding season and is of the same design. The contractor cannot locate an acceptable borrow pit site within reasonable hauling distance, however, there is a commercial quarry located within an acceptable distance from the project. An agreement is made with the quarry owner to allow the prime contractor to remove overburden from part of his quarry to be purchased and used for roadway embankment material. The owner of the quarry will take both original and final cross sections for measurement of the site of which borrow is purchased. The contractor moves in his own fleet of trucks to:
|