The following charts detail TFHRC research and identify the goals that this research supports. The charts also indicate which projects were completed in FY 2003 and which ones are still ongoing for 2004 and beyond. The comment column provides reasons behind changes or deviations from the unit plan and schedule. In addition, we’ve included new projects that were not identified at the time the FY 2002/2003 Performance Plan was published.
Project |
Technical Contact |
Projected Goal Impact |
Project Completion Status (Percent) |
On Schedule |
Target Completion Date |
Comments |
25 |
50 |
75 |
100 |
Pavements/Portland Cement Concrete (PCC)
|
Guidelines to Detect, Analyze, Treat, and/or Prevent Materials-Related Distress
|
Steve Forster
HRDI-04
202–493–3070 |
Mobility |
|
|
|
X |
Yes |
Complete |
Improved PCCP forensic analysis.
Reports printed. T2 package received.
Workshop being considered. The results should provide for more systematic forensic analysis of PCCP.
|
Guidelines to Select Curing Materials and Procedures
|
Steve Forster
HRDI-04
202–493–3070 |
Mobility |
|
|
|
X |
Yes |
Complete |
Guidelines for improved PCCP curing.
Draft final reports under review.
|
Guidelines to Develop Statistical Quality Assurance Specifications
|
Peter Kopac
HRDI-12
202–493–3051 |
Mobility |
|
|
X |
|
Yes |
Oct 2003 |
Enhanced quality and uniformity of State quality assurance specifications.
Project is 99 percent complete; final report is being prepared.
|
Freeze-Thaw Durability of Concrete Report
|
Marcia Simon
HRDI-12
202–493–3071 |
Mobility |
|
|
X |
|
No |
Dec 2003 |
Enhanced understanding of the freezethaw durability of concrete having “marginal” air contents.
Laboratory testing delayed by equipment problems. Final report writing has begun.
|
Guidelines on the Use of Recycled PCCP as Aggregate in New PCCP
|
Steve Forster
HRDI-04
202–493–3070 |
Mobility |
|
|
X |
|
No |
Dec 2003 |
Research designs that consider recycled aggregate.
Principal investigator is no longer with the contractor, which has delayed delivery of the final report.
|
Petrography Manual
|
Steve Forster
HRDI-04
202–493–3070 |
Mobility |
|
|
X |
|
No |
Dec 2003 |
State-of-the-art petrographic manual for PCC.
Adding new techniques, including scanning electron microscope analysis. Draft report has been reviewed.
|
Vibrating Slope Apparatus to Measure PCC Workability, Equipment, and Test Method
|
Marcia Simon
HRDI-12
202–493–3071 |
Mobility |
|
|
X |
|
Yes |
Dec 2003 |
More meaningful assessment of concrete paving mixtures workability.
Work being coordinated with the University of Texas.
|
HIPERPAV Software for Jointed Plain Concrete Pavement and CRCP Performance Behavior
|
Fred Faridazar
HRDI-12
202–493–3076 |
Mobility |
|
|
X |
|
Yes |
Jan 2004 |
Improved performance of PCCP.
Contract was revised to add software refinements and an expand product delivery effort (workshops and technical support). Work is 98 percent complete.
|
Project |
Technical Contact |
Projected Goal Impact |
Project Completion
Status (Percent) |
On Schedule |
Target Completion Date |
Comments |
25 |
50 |
75 |
100 |
Pavements/LTPP
|
DATAPAVE 3.0, CD-ROM Software Package
|
Aramis Lopez
HRDI-13
202–493–3145 |
Mobility |
|
|
|
X |
Yes |
Complete |
National software distribution to facilitate LTPP database usage.
National distribution was made during the TRB annual meeting, and the software was used during an FHWA professor training workshop.
|
Dynamic Test System Protocol
|
Aramis Lopez
HRDI-13
202–493–3145 |
Mobility |
|
|
|
X |
Yes |
Complete |
Develop a new procedure to evaluate close-loop equipment.
Report completed and awaiting publication. 508 conversion is underway.
|
Estimating Cumulative Traffic Loads Report
|
Larry Wiser
HRDI-13
202–493–3079 |
Mobility |
|
|
|
X |
Yes |
Complete |
Study of State DOTs using the new axle load spectra procedures.
Report completed and is under technical and editorial review. It will be published in April 2004.
|
Improved Specifications for Weigh-In-Motion (WIM)
|
Larry Wiser
HRDI-13
202–493–3079 |
Mobility |
|
|
|
X |
Yes |
Complete |
Improved WIM technology.
The WIM specifications and guideline are available on the LTPP Web page.
|
Joint and Crack Load Transfer in LTPP Test Sections Report
|
Aramis Lopez
HRDI-13
202–493–3145 |
Mobility |
|
|
|
X |
Yes |
Complete |
Improve the understanding of PCCP joint and crack load transfer.
Report completed and is in the final stages of publication.
|
LTPP Database, Data Releases
|
Aramis Lopez
HRDI-13
202–493–3145 |
Mobility |
|
|
|
X |
Yes |
Complete |
Make LTPP database available to the public. Two data releases completed during FY 2003 (January and July). The July 2003 data are available at the LTPP customer support office (LTPPInfo@fhwa.dot.gov)
|
Verification of LTPP Virtual Weather Stations Report
|
Aramis Lopez
HRDI-13
202–493–3145 |
Mobility |
|
|
|
X |
Yes |
Complete |
To determine accuracy and factors affecting virtual weather stations.
Report completed and awaiting publication and 508 conversion.
|
Project |
Technical Contact |
Projected Goal Impact |
Project Completion
Status (Percent) |
On Schedule |
Target Completion Date |
Comments |
25 |
50 |
75 |
100 |
Projects Not Reflected in 2002–2003 Plan
|
Abutment Scour Field Data
|
J. Sterling Jones
HRDI-07
202–493–3043 |
Mobility/Safety |
|
|
|
X |
Yes |
Complete |
Provide database with field data from South Carolina for comparison with predictions based on FHWA guidelines and new procedures being developed.
Data report will be published as a U.S. Geological Survey Open File Report. It will be provided to researchers for NCHRP Project 24-20, “Prediction of Abutment Scour.”
|
Air Pollution Models for Complex Site Geometries
|
Howard Jongedyk
HRDI-10
202–493–3077 |
Environment |
|
|
|
X |
Yes |
Complete |
Techniques to evaluate impacts of toxic spills.
Model for dispersion of exhaust gases and toxic gases from chemical spills or terrorist attacks; applicable to complex urban sites and tunnels. Report printed.
|
Cost Analysis for Innovative Bridge Coatings Methods
|
Bob Kogler
HRDI-06
202–493–3080 |
Mobility |
|
|
|
X |
Yes |
Complete |
Comparative cost information for bridge coating rehabilitation projects. |
COST Web Site and Report
|
Marcia Simon
HRDI-12
202–493–3071 |
Mobility |
|
|
|
X |
Yes |
Complete |
Web-based software to efficiently optimize concrete mix proportioning and achieve multiple performance criteria. Final report was submitted for printing.
Web site: http://ciks.cbt.nist.gov/cost/.
|
Diffusion of Airborne Highway Pollutants
|
Howard Jongedyk
HRDI-10
202–493–3077 |
Environment |
|
|
|
X |
Yes |
Complete |
Methodology to mitigate impacts of airborne pollutants. |
Full-Scale Accelerated Performance Testing for Superpave and Structural Validation: Phase I—Construction
|
Terry Mitchell
HRDI-11
202–493–3147 |
Mobility |
|
|
|
X |
Yes |
Complete |
National Superpave binder specification refinement to capture fully the benefit of modified binders. Pooled fund study TPF- 5(019) in partnership with the TRB Superpave Binder ETG. |
Fundamental Properties of Asphalt and Modified Asphalts
|
Ernie Bastian
HRDI-11
202–493–3075 |
Mobility |
|
|
|
X |
Yes |
Complete |
Expanded fundamental knowledge of asphalt and modified asphalts.
Congressionally directed research activity.
|
Management of Highway Runoff in Karst Areas
|
Howard Jongedyk
HRDI-10
202–493–3077 |
Environment |
|
|
|
X |
Yes |
Complete |
Techniques to prevent damage to sensitive geologies. |
Performance Measures on the Benefits of Infrastructure RD&T
|
Shiela Duwadi
HRDI-07
202–493–3106 |
Mobility |
|
|
|
X |
Yes |
Complete |
A new framework for measuring the benefits of research. |
Preliminary Laboratory Investigation of the Performance of Modified Asphalt Binders in Mixtures
|
Kevin Stuart
HRDI-11
202–493–3073 |
Mobility |
|
|
|
X |
Yes |
Complete |
National refinement of Superpave binder specifications to fully capture the benefit of modified binders. Validation of proposed changes to the Superpave binder specifications.
Funded by NCHRP and the TRB Superpave Mix/Aggregate and Binder Expert Task Group (ETG).
|
Risk-Based Countermeasure Selection for Scour Critical Bridges
|
J. Sterling Jones
HRDI-07
202–493–3043 |
Mobility |
|
|
|
X |
Yes |
Complete |
The HYRISK model has been posted on the FHWA bridge technology Web site at https://www.fhwa.dot.gov/engineering/hydraulics/.
HYRISK is keyed to the National Highway Institute (NHI) database and has been revised to prioritize bridges from information based on the 2001 coding guide. HYRISK has a component for a risk-based selection of countermeasures for bridges with limited service life that will be a starting point for NCHRP 24-25.
|
Asset Management Suite of Pavement Models
|
Bill Kenis
HRDI-10
202–493–3149 |
|
|
|
X |
|
Yes |
Nov 2003 |
Life-cycle costing analysis for pavements.
Suite of models being developed.
|
Studies to Better Understand the Performance of Bridges Subjected to Near-Source Ground Motions (NSGM)
|
Hamid Ghasemi
HRDI-07
202–493–3042 |
Mobility/Safety |
|
|
X |
|
Yes |
Nov 2003 |
Studied the characteristics of NSGM.
Analyzed the performance of Bolu Viaduct in Turkey, subjected to NSGM by generating synthetic records. A technical report will be generated.
|
Warp and Curl Analysis Software
|
Dennis Sixbey
HRDI-10
202–493–3078 |
Mobility |
|
|
X |
|
Yes |
Nov 2003 |
Improved analysis and design of PCC pavements.
Software analysis package being developed.
|
High-Energy Radiography for Structures
|
Glenn Washer
HRDI-10
202–493–3082 |
Mobility |
|
|
X |
|
Yes |
Jan 2004 |
Develop technology for detecting subsurface defects in concrete and steel bridges.
Ongoing field testing to evaluate capabilities of the method; guidelines for field application being developed.
|
Technical Expertise on Grout Issues
|
Glenn Washer
HRDI-10
202–493–3082 |
Mobility |
|
|
X |
|
Yes |
Jan 2004 |
Technical assistance for inspection of post-tensioned bridges.
Ongoing consultation and project development.
|
An Educational Guide to the History of Covered Bridges in the United States
|
Shiela Duwadi
HRDI-07
202–493–3106 |
Mobility |
|
|
X |
|
Yes |
Feb 2004 |
A guide designed to provide standards with a basic understanding of covered bridges. |
Covered Bridge Manual
|
Shiela Duwadi
HRDI-07
202–493–3106 |
Safety |
|
|
X |
|
Yes |
Feb 2004 |
A guide to rehabilitate, restore, preserve, and reconstruct historic covered bridges. |
Mixture-Specific Test Method for Alkali- Silica Reactivity
|
Marcia Simon
HRDI-12
202–493–3071 |
Mobility |
|
X |
|
|
No |
Apr 2004 |
Improve performance of PCCP.
Continued delay in testing due to equipment problems. Expected resolution by October 2003.
|
Evaluation of the Proposed Simple Performance Test
|
Kevin Stuart
HRDI-11
202–493–3073 |
Mobility |
|
X |
|
|
Yes |
Jun 2004 |
New tool to improve the quality and performance of asphalt pavements.
Funded by Revenue Aligned Budget Authority; requested by AASHTO.
|
Infrared Thermography for Infrastructure Inspection
|
Glenn Washer
HRDI-10
202–493–3082 |
Mobility |
|
|
X |
|
Yes |
Jun 2004 |
Technology for detecting delamination in bridge members.
System built; new software developed; field testing underway.
|
Guidelines for Achieving High Levels of Smoothness Without Sacrificing PCC Performance
|
Peter Kopac
HRDI-12
202–493–3151 |
Mobility |
|
|
X |
|
Yes |
Jul 2004 |
Guidance to assure high smoothness and performance levels.
Field testing and data collection underway.
|
Corrosion Control Design Guidance for Bridges
|
Bob Kogler
HRDI-06
202–493–3080 |
Mobility |
X |
|
|
|
Yes |
Sep 2004 |
Provide bridge engineers with knowledge and guidance to design more durable structures. |
Smoothness Specifications
|
Dennis Sixbey
HRDI-10
202–493–3078 |
|
|
|
X |
|
Yes |
Sep 2004 |
Improved pavement measurements made at highway speeds.
Phases I and II—Determination of accelerometer requirements for inertial profilers at speeds from 24–120 kilometers per hour complete.
Possible Phase III being considered.
|
Synthesis—Bridge Surveillance and Security Technologies
|
Shiela Duwadi
HRDI-07
202–493–3106 |
Security |
X |
|
|
|
Yes |
Oct 2004 |
Provide guidance on selection and implementation of bridge and tunnel security and surveillance systems. |
Compendium of Knowledge on Pavement Models
|
Bill Kenis
HRDI-10
202–493–3149 |
Mobility |
|
|
X |
|
Yes |
Dec 2004 |
Text being written on basic principles of pavement models and analysis. |
Feasibility of Bridge Design for Near-Fault Ground Motions
|
Hamid Ghasemi
HRDI-07
202–493–3042 |
Mobility/Safety |
X |
|
|
|
Yes |
Dec 2004 |
Develop simplified design procedures for bridges built close to an active fault. |
Evaluation of GSB-88 Emulsified Sealer
|
Kevin Stuart
HRDI-11
202–493–3073 |
Mobility |
|
X |
|
|
Yes |
Sep 2005 |
Product intended to increase pavement service life.
Congressionally directed research activity.
|
Design and Material Specifications for FRP/Glulam Bridges
|
Shiela Duwadi
HRDI-07
202–493–3106 |
Mobility/Safety |
|
|
X |
|
Yes |
Oct 2005 |
New specifications for adoption by AASHTO. |
Project |
Technical Contact |
Projected Goal Impact |
Project Completion
Status (Percent) |
On Schedule |
Target Completion Date |
Comments |
25 |
50 |
75 |
100 |
Intelligent Vehicle Initiative (IVI) and Human Centered Systems
|
Guidelines for In-Vehicle Display Icons
|
Tom Granda
HRDS-07
202–493–3365 |
Safety/Mobility |
|
|
|
X |
Yes |
Complete |
Diverse industry working group guided development. Original equipment manufacturer suppliers expressed interest in the product. |
Synthesis of Practices Addressing Consistency in Text-Based Messaging for Advanced Traveler Information Systems (ATIS)
|
Tom Granda
HRDS-07
202–493–3365 |
Safety/Mobility |
|
|
|
X |
Yes |
Complete |
Review of ATIS operator practices in selecting, filtering, and assembling dynamic message sign messages. Survey of the diverse text message delivery systems to understand the baseline system, the various types of messages being presented, and the decisionmaking processes for those messages. |
Specialty Vehicles Technologies Evaluation
|
Randy VanGorder
HRD0-03
202–493–3266 |
Safety/Mobility |
|
|
X |
|
No |
Nov 2003 |
Final review of evaluation report in progress. Minnesota DOT resubmitting final reports in HTML format for 508 compliance and Web posting. |
Enhanced Digital Mapping
|
Toni Wilbur
HRD0-01
202–493–3269 |
Safety |
|
|
X |
|
Yes |
Apr 2004 |
A cooperative partnership with industry to develop specifications and improve driver assistance systems. |
Intersection Collision and Roadway Crash Avoidance/Infrastructure Systems Concepts and Requirements
|
Bob Ferlis
HRDO-02
202–493–3268 |
Safety |
X |
|
|
|
Yes |
Jan 2005 |
Organized as a pooled fund project to develop functional requirements and demonstration systems for infrastructure-based intersection collision avoidance systems. |
Transportation Management Center (TMC) National Pooled Fund Study Results
|
Tom Granda
HRDS-07
202–493–3365 |
Safety/Mobility |
|
X |
|
|
Yes |
Sep 2006 |
Developed several references for TMC operations. For more information, see the pooled fund Web site at http://tmcpfs.ops.fhwa.dot.gov/index.cfm. |
Project |
Technical Contact |
Projected Goal Impact |
Project Completion
Status (Percent) |
On Schedule |
Target Completion Date |
Comments |
25 |
50 |
75 |
100 |
Traffic Control and Operations
|
ACS—Development
|
Deborah Curtis
HRDO-03
202–493–3267 |
Mobility |
|
|
|
X |
Yes |
Complete |
Weather and evacuation papers prepared; product handoff to Office of Operations done. Preparing one-page marketing tool. |
ACS—Field Test
|
Raj Ghaman
HRDO-03
202–493–3270 |
Mobility |
|
|
|
X |
Yes |
Complete |
|
Freeway Management Handbook
|
James Colyar
HRDO-03
202–493–3282
|
Mobility/ Productivity |
|
|
|
X |
Yes |
Complete |
Updated and revised handbook. Will be available for free download in December 2003. For more information, visit www.nawgits.com/icdn/fmoh.html. |
Traffic Control Systems Handbook
|
Raj Ghaman
HRDO-03
202–493–3270 |
Mobility |
|
|
X |
|
Yes |
Dec 2003 |
Update underway. |
ACS “Lite” Version Software
|
Gene McHale
HRDO-03
202–493–3275 |
Mobility |
|
X |
|
|
Yes |
Jan 2004 |
Software development expected to be complete in December 2003. Hardware interface under development; expected late 2003. Lab testing expected June 2004. Field testing expected July 2005. Final report and evaluation expected October 2005. |
Traffic Detector Handbook
|
Dave Gibson
HRDO-04
202–493–3271 |
Safety/ Mobility/ Environment |
|
|
X |
|
Yes |
Jul 2004 |
An update to the handbook describes design requirements, installation, and maintenance procedures for transportation sensors. Update complete; currently making report 508 compliant. |
Winter Weather Maintenance Decision Support Systems
|
Randy VanGorder
HRDO-03
202–493–3266
Rudy Persaud
HRDO-04
202–493–3391
|
Safety/ Mobility/ Productivity/ Environment |
|
|
X |
|
Yes |
Oct 2004 |
The demonstration has been extended through FY 2004 to take the evaluations and lessons learned from the first demonstration to enhance and better refine the system. |
Support to Office of Operations on Devices—Manual on Uniform Traffic Control Devices (MUTCD) Signing Issues
|
Tom Granda
HRDS-07
202–493–3365 |
Safety/Mobility |
|
X |
|
|
Yes |
Nov 2004 |
Role of FHWA regarding in-vehicle information.
Phase II to begin in FY 2004.
|
Ramp Metering 2000 Software
|
Deborah Curtis
HRDO-03
202–493–3267 |
Mobility |
|
|
|
X |
Yes |
Dec 2004 |
Working with Office of Operations to determine next steps for product. Contract issues were resolved. Software development completed May 2003. Currently performing simulation evaluation. Field test planned for summer 2004. |
DynaMIT—Field Test in Los Angeles, CA
|
Henry Lieu
HRDO-03
202–493–3273 |
Mobility |
X |
|
|
|
Yes |
Feb 2006 |
This project integrates CLAIRE, DynaMIT and Advanced Incident Detection Algorithm in Los Angeles, CA for real-time traffic management on arterials. The project started in September 2003. |
DynaSMART-X—Field Test in Houston, TX
|
Henry Lieu
HRDO-03
202–493–3273 |
Mobility |
X |
|
|
|
Yes |
Mar 2006 |
This project integrates CLAIRE, DynaSMART-X and RHODES in Houston, TX. FHWA will provide Texas DOT with the three software packages for field test. The project is scheduled to start by late 2003. |
Project |
Technical Contact |
Projected Goal Impact |
Project Completion
Status (Percent) |
On Schedule |
Target Completion Date |
Comments |
25 |
50 |
75 |
100 |
Traffic Simulation Modeling
|
DynaSMART-P—Release and Technical Support
|
Henry Lieu
HRDO-03
202–493–3273 |
Mobility |
|
|
|
X |
Yes |
Jan 2004 |
DynaSMART-P will be released to the public in early 2004. |
QuickZone Work Zone Delay Estimation Tool
|
Deborah Curtis
HRDO-03
202–493–3267 |
Mobility/ Productivity |
|
|
X |
|
|
Jan 2004 |
Working on cost-estimate tool. QuickZone 2.0 to be released January 2004. |
Strategic Work Zone Analysis Tools (SWAT)
|
Deborah Curtis
HRDO-03
202–493–3267 |
Mobility/ Productivity |
|
X |
|
|
Yes |
Dec 2004 |
Working on impact-analysis tools. |
GPS Surface Observation System Installation for Integrated Precipitable Water Vapor (IPWV)
|
Jim Arnold
HRDO-04
202–493–3265
Rudy Persaud
HRDO-04
202–493–3391
|
Safety/ Mobility/ Productivity/ Environment/ Security |
|
X |
|
|
Yes |
Dec 2005 |
Install GPS surface observation system packages at NDGPS sites to calculate the IPWV from the accurate measurements of the GPS signal delay caused by atmospheric water vapor. |
NDGPS Base Stations
|
Jim Arnold
HRDO-04
202–493–3265 |
Safety/ Mobility/ Productivity/ Environment/ Security |
|
X |
|
|
Yes |
Dec 2005 |
|
NDGPS Coverage Verification Test Jig
|
Jim Arnold
HRDO-04
202–493–3265 |
Safety/ Mobility/ Productivity/ Environment/ Security |
X |
|
|
|
Yes |
Dec 2005 |
|
DynaMIT-P—Field Test in Hampton Roads, VA
|
Henry Lieu
HRDO-03
202–493–3273 |
Mobility |
X |
|
|
|
Yes |
Jan 2006 |
The project began in May 2003. |
Next Generation Simulation Modeling
|
Gene McHale
HRDO-03
202–493–3275 |
Mobility |
X |
|
|
|
Yes |
Dec 2007 |
|
Project |
Technical Contact |
Projected Goal Impact |
Project Completion
Status (Percent) |
On Schedule |
Target Completion Date |
Comments |
25 |
50 |
75 |
100 |
Run-Off-the-Road Prevention: Design
|
IHSDM—2003 Public Release |
Ray Krammes
HRDS-05
202–493–3312 |
Safety |
|
|
|
|
Yes |
Complete |
This suite of safety evaluation software modules incorporates available knowledge about roadway safety and geometric design into a more useful format for highway planners and designers. |
Night Driving and Lighting Requirements for the Older Driver |
Kenneth Opiela
HRDS-05
202–493–3371 |
Safety |
|
|
|
X |
Yes |
Complete |
Final report completed and in print. |
Updated Minimum Levels for Pavement Marking Retroreflectivity |
Kenneth Opiela
HRDS-05
202–493–3371 |
Safety |
|
|
X |
|
No |
Rescheduled Jan 2004 |
Progress has been made in verifying and validating past efforts, but the need to revise the sign retroreflectivity values has delayed completion of this effort; 9-month extension is anticipated for this project. |
Minimum Fluorescent Requirements for Traffic Signs |
Carl Andersen
HRDS-05
202–493–3366 |
Safety |
X |
|
|
|
No |
Mar 2004 |
Delayed due to difficulty in finding specifically configured fluorescent material. |
Guidelines for Assuring Systemwide Adequacy of Traffic Sign Visibility at Night |
Kenneth Opiela
HRDS-05
202–493–3371 |
Safety |
X |
|
|
|
Yes |
Jun 2004 |
Tables of minimum requirements for traffic sign retroreflectivity have been completed, IDIQ with TTI initiated. |
Enhanced Night Visibility Project Followup Study Results |
Carl Andersen
HRDS-05
202–493–3366 |
Safety |
|
X |
|
|
Yes |
Dec 2004 |
Initial project extended through May 31, 2004. |
IHSDM—Driver/Vehicle Module Beta Test |
Ray Krammes
HRDS-05
202–493–3312 |
Safety |
|
|
|
|
No |
Sep 2005 |
This module needs additional work, which we are deferring to FY 2003/2004. It will not be part of the 2003 release of IHSDM. |
Requirements for Light-Emitting Diode (LED) Traffic Signals |
Carl Andersen
HRDS-05
202–493–3366 |
Safety |
|
|
|
|
Yes |
June 2006 |
Not started. Exploring cooperative agreement with NIST. |