Structural Factors of Jointed Plain Concrete Pavements: SPS-2—Initial Evaluation and AnalysisChapter 3. Assessment of Data Availability and Completeness
The second step in the SPS-2 review and evaluation study is to
assess the key data availability and completeness. LTPP data
availability and quality control (QC) checks are discussed first.
Then, key data elements are assessed for their quality level and
completeness. The data reviews are divided into the following
categories:
- General site information.
- Pavement structure data.
- Construction data.
- Material testing data.
- Traffic data.
- Climate data.
- Monitoring data.
- Dynamic load-response data.
IMS data release 9.8, obtained on August 10, 1999, was used for
the majority of the study; however, the distress, profile, and
materials testing data are from IMS release 10.1, obtained on
February 1, 2000.
LTPP Data Availability and Quality
Control Checks
The quality of the data is the most important factor in any type
of analysis. From the outset of the LTPP program, data quality has
been considered of paramount importance. Procedures for collecting
and processing data were defined (and are modified as necessary) to
ensure consistency across various reporting contractors,
laboratories, equipment operators, and so forth. Although these
procedures formed the foundation of quality control/quality
assurance (QC/QA) and data integrity, many more components of a
QC/QA plan were necessary to ensure that the data sent to
researchers were as error-free as practical.
LTPP has developed and implemented an extensive QC program that
classifies each of the data elements into categories depending upon
the location of the data in this QC process. Several components or
steps comprise the overall QC/QA plan used on LTPP data, as are
discussed in the following paragraphs.
- Collect Data: Procedures for collecting data are documented for
each module in the IMS. These procedures are intended to ensure
that data are collected in similar format, amounts, conditions,
etc. Documentation references include the Data Collection Guide
for Long-Term Pavement Performance Studies(2) and
various module-specific guides.
- Review Data: Regional engineers review essentially all data
input into regional IMS (RIMS) to check for possible errors related
to keystroke input, field operations, procedures, equipment
operations, and other variables. The regional review is intended to
catch obvious data collection errors. In addition, some data are
preprocessed before they are entered into the IMS. For example,
PROFCAL™ software is used on SHRP profilometers to provide a system
check by comparing measurements taken at different speeds.
PROFSCAN™ is a field QA tool that allows an operator to identify
invalid data while still in the field, thus avoiding costly
revisits to the site.
- Load Data in IMS: Some checks are programmed into the IMS to
identify errors as data are entered. The IMS contains mandatory
logic, range, data verification, and other miscellaneous checks
that are invoked during input.
- QC/QA: Once data are input into the IMS and reviewed by
regional engineers, formal QC/QA software programs are run on the
data.
- Level A-Random checks of data are performed to ensure correct
RIMS to IMS data transfer.
- Level B-A set of dependency checks is performed to ensure that
essential section information has been recorded in the IMS. In
addition, experiment types are verified based on inventory data.
These checks are currently being incorporated into the level E
checks for all modules.
- Level C-A minimum data search is performed for critical
elements. For example, inventory data should contain the
coordinates of the section, friction data should contain the skid
number, and rehabilitation data should have a code entered to
identify each work type activity.
- Level D-Expanded range checks are applied to certain fields to
identify data element values that fall outside an expected range.
These checks are more stringent than the input range checks
reviewed by the regional engineers.
- Level E-Intramodular checks are employed to verify the
consistency of data within a data module. For example, if an
overlay is identified in the inventory layer structure, the data of
the overlay should be recorded in the inventory table that includes
major improvements to the pavement structure.
Once the QC/QA programs are completed, the regional engineers
review the output and resolve any data errors whenever possible.
Often the data entered are accurate and legitimate, but do not pass
a QC/QA check. When this occurs, the regional engineer can document
that the data have been confirmed using a comments table in the IMS
and manually upgrade the record to Level E.
Figure 3 is a flowchart that shows the movement of data elements
and quality checks completed on the data prior to release to the
public. Only a fraction of the data fields are checked. A value of
"A" is automatically assigned to a record on entry in the database.
A value of "B" indicates that the QC process was executed and a
level C check was failed. Any record for which correct section
information is stored in the database is available after the QC is
completed. A record of the QC processing is included with the
record. Since the checks are run in sequence from A to E, the last
successful check is identified on the record as the record status
variable. A value of B or C does not necessarily indicate that
higher level QC was unsuccessful, merely that a necessary data
element was not available when the QC was done.
Figure 3. LTPP data collection and data
movement flowchart.
There are numerous reasons why some important data may not be
available from publicly released IMS database at the time of
analysis. The following are some possible examples:
- Data are yet to be collected or the laboratory tests have not
been performed yet.
- Data are under regional review.
- Data have failed one of the quality checks and are to be
reviewed.
- Data have failed one of the quality checks and were identified
as anomalies.
- Data are yet to be quality checked.
As such, the unavailable data identified in this report do not
necessarily mean that the data were not collected or submitted by
the States. There are several places where data may get held up and
not reach level E. Note that the results reported in this report
are based upon level E data only.
The LTPP program is embarking on a systemwide effort to resolve
all unavailable data so that information will be available to
future researchers. Some data have already been located during the
course of this study.
General Site Information
General site-related information availability for SPS-2 projects
is discussed in this section. This includes site identification and
location, key equipment installed, report availability, and
important dates associated with each SPS-2 site. The information
was obtained from the site construction reports and deviation
reports, or from the following IMS tables:
- EXPERIMENT_SECTION
- SPS_ID
The EXPERIMENT_SECTION table contains records for all the SPS-2
sites and sections. All the site-level records (0200) for the 13
constructed SPS-2 projects are at level E. The section-level
records are at level E except for the 12 sections at the newly
constructed Wisconsin SPS-2 site. The SPS_ID tables contain records
for all 13 SPS-2 sites, and the site data are all at level E.
Since this site-level information is fundamental to the SPS-2
sites and is very important for an overall understanding of the
sites, actual key data are presented, in addition to the data
availability assessment. General State identification, equipment
installation, and report availability information about the SPS-2
sites are provided in table 7. The construction reports were
prepared and submitted by LTPP regional coordination office
contractors (RCOCs) for all SPS-2 projects.
The site location and functional class information are provided
in table 8. Table 9 presents the significant dates such as the
approximate construction complete date, traffic opening date, and
the LTPP assign and deassign dates. The oldest SPS-2 site is 7.5
years old. As indicated in both tables, all the important
site-level information is available for the 13 SPS-2 sites. The
only exception is that the approximate construction completion date
for the North Dakota site was not available at the time of analysis
in the SPS_ID table.
Table 7. SPS-2 site general information and report
availability.
State Information |
Equipment Installed |
Report Availability |
Abbr. |
Code |
Name |
SHRP Region |
AWS |
WIM |
AVC |
Construction |
Deviation |
AZ |
04 |
Arizona |
W |
|
|
|
|
- |
AR |
05 |
Arkansas |
S |
|
|
- |
|
|
CO |
08 |
Colorado |
W |
|
|
|
|
- |
DE |
10 |
Delaware |
NA |
|
|
|
|
|
IA |
19 |
Iowa |
NC |
|
|
|
|
|
KS |
20 |
Kansas |
NC |
|
|
|
|
|
MI |
26 |
Michigan |
NC |
|
|
|
|
|
NV |
32 |
Nevada |
W |
|
|
|
|
- |
NC |
37 |
North Carolina |
NA |
|
|
|
|
- |
ND |
38 |
North Dakota |
NC |
|
|
|
|
|
OH |
39 |
Ohio |
NC |
|
|
|
|
|
WA |
53 |
Washington |
W |
|
|
|
|
- |
WI |
55 |
Wisconsin |
NC |
|
|
|
|
|
Notes: NA = North Atlantic
Region
NC = North Central Region
S = Southern Region
W = Western Region
Table 8. SPS-2 site location information.
State |
County |
Route No. |
Functional Class |
Lanes |
AZ |
Maricopa |
Interstate 10 |
Rural principal arterial-interstate |
2 |
AR |
Hot Springs |
Interstate 30 |
Rural principal arterial |
2 |
CO |
Adams |
Interstate 76 |
Rural principal arterial |
2 |
DE |
Sussex |
US 113 |
Rural principal arterial-other |
2 |
IA |
Polk |
US 65 |
Urban principal arterial-other freeways or expressways |
2 |
KS |
Dickinson |
Interstate 70 |
Rural principal arterial-interstate |
2 |
MI |
Monroe |
US 23 |
Rural principal arterial-other |
2 |
NV |
Lander |
Interstate 80 |
Rural principal arterial |
2 |
NC |
Davidson |
US 52 |
Rural principal arterial-other |
2 |
ND |
Cass |
Interstate 94 |
Rural principal arterial-interstate |
2 |
OH |
Delaware |
US 23 |
Rural principal arterial-other |
2 |
WA |
Adams |
State 395 |
Urban principal arterial-other freeways or expressways |
2 |
WI |
Marathon |
State 29 |
Rural other principal arterial |
2 |
Table 9. SPS-2 sites significant dates and age as of
August 1999.
State Abbr |
Age as of August 1999 (years) |
Significant Dates |
Date Completed |
Data Open to Traffic |
Assign Date |
Deassign Date |
AZ |
5.8 |
10/01/93 |
10/01/93 |
01/01/93 |
- |
AR |
3.8 |
10/01/95 |
11/01/95 |
09/01/93 |
- |
CO |
5.8 |
10/01/93 |
11/01/93 |
01/01/93 |
- |
DE |
3.3 |
05/01/96 |
05/01/96 |
01/01/92 |
- |
IA |
5.0 |
08/01/94 |
12/01/94 |
01/01/92 |
- |
KS |
7.1 |
07/01/92 |
08/01/92 |
01/01/92 |
- |
MI |
5.8 |
11/01/93 |
11/01/93 |
01/01/93 |
- |
NV |
4.0 |
08/01/95 |
09/01/95 |
01/01/93 |
09/18/97 (0202, 0206) |
NC |
5.1 |
07/01/94 |
07/01/94 |
07/15/92 |
- |
ND |
4.8 |
11/01/94 |
11/01/94 |
01/01/94 |
- |
OH |
2.9 |
09/01/96 |
10/01/96 |
01/01/94 |
- |
WA |
3.8 |
11/01/95 |
11/01/95 |
01/01/93 |
- |
WI |
1.8 |
10/01/97 |
11/01/97 |
01/01/97 |
- |
Pavement Structure Data
Pavement structure data are further divided into two categories:
pavement layer data and pavement design features.
Pavement Layer Data
Pavement layer data for SPS-2 sections are available from two
sources: rod and level measurements (IMS table SPS2_Layer) and core
measurements (IMS table TST_L05B). Both tables were examined for
the following pavement structure layers:
- PCC slab thickness.
- Base type and thickness.
- Subgrade type.
The data availability and QC levels for these data elements are
summarized in table 10.
The TST_L05B table contains records with all layer data for 143
core sections at 12 SPS-2 sites. Layer information from the
Wisconsin SPS-2 site is not available from the database at the time
of analysis.
The SPS2_LAYER table contains all layer data for all 155
sections from all 13 SPS-2 sites, and 143 sections are at QC level
E. The remaining 12 records, all from the same site in Wisconsin,
are at level A.
Table 10. Data availability and QC levels for key pavement
layer data.
Data Availability |
TST_L05B |
SPS2_layer |
|
Slab Thickness |
Base Layer |
Subgrade |
Slab Thickness |
Base Layer |
Subgrade |
Core Sections (Total 155 sections) |
At all levels (A to
E) |
143 |
143 |
143 |
155 |
155 |
155 |
At level E only |
127 |
108 |
126 |
143 |
143 |
143 |
Percent data at level
E |
89 |
82 |
88 |
92 |
92 |
92 |
Core sections missing
data at all levels |
12 |
12 |
12 |
0 |
0 |
0 |
Sites with missing
data at all levels |
WI |
WI |
WI |
- |
- |
- |
Supplemental Sections (Total 40
Sections) |
Supplemental sections
with data |
30 |
26 |
30 |
34 |
33 |
28 |
Supplemental sections
missing data |
10 |
14 |
10 |
6 |
7 |
12 |
Key Design Feature Data
Important general design features, such as drainage, lane width,
and shoulder type data, are included in table SPS_GENERAL. The data
availability assessment for these data elements is provided in
table 11.
Table 11. Data availability for lane width, drainage, and
shoulder data for SPS-2 sections.
Data Availability Number |
Lane Width Data |
Drainage and Shoulder Type Data |
Core Sections (Total 155 sections) |
At all levels (A to
E) |
131 |
131 |
At level E only |
131 |
131 |
Percent data at level
E |
100 |
100 |
Core sections missing data
at all levels |
24 |
24 |
Sites with missing data at
all levels |
KS, WI |
KS, WI |
Supplemental Sections (Total 40
Sections) |
Supplemental sections with
data |
29 |
27 |
Supplemental sections
missing data |
11 |
13 |
As indicated in table 11, information is available for 133 SPS-2
sections, and the data are all at level E. The key design feature
data for 24 SPS-2 core sections in Kansas and Wisconsin were not
available at the time of analysis.
Construction Data
SPS-2 construction data include information pertaining to the
pavement layers constructed according to the requirements
stipulated for the experiment. The following key SPS-2 construction
tables were evaluated for the data completeness and QC levels:
- SPS2_PCC_JOINT_DATA-PCC layers: Joint data (sheets 15,
16).
- SPS2_PCC_MIXTURE_DATA-PCC layers: Mixture data (sheets 18,
19).
- SPS2_PCC_PLACEMENT_DATA-PCC layers: Placement data. (sheets 20,
21).
- SPS2_PROJECT_STATIONS-Test section information (sheet 3).
- SPS2_SUBGRADE_PREP-Subgrade preparation (sheet 6).
- SPS2_UNBOUND_AGG_BASE -Unbound aggregate base material
placement data (Sheet 9).
Data availability assessment and QC levels summary for these
tables are provided in tables 12 and 13.
Table 12. Data availability assessment and QC levels for
SPS-2 key construction data.
Data Availability Number |
SPS2_PCC_
JOINT_DATA |
SPS2_PCC_
MIXTURE_DATA |
SPS2_PCC_
PLACEMENT_DATA |
Core Sections (Total 155 sections) |
At all levels (A to E) |
151 sections (157 records) |
139 sections (175 records) |
155 sections (194 records) |
At level E only |
136 sections (142 records) |
133 sections (169 records) |
142 sections (181 records) |
Percent data at level E |
90 |
97 |
93 |
Core sections missing data at all
levels |
4 |
16 |
0 |
Sites with missing data at all
levels |
WA |
AZ, OH |
- |
Supplemental Sections (Total 40
Sections) |
Supplemental sections with
data |
35 |
21 |
35 |
Supplemental sections
missing data |
5 |
19 |
5 |
Table 13. Data availability assessment and QC levels for
other SPS-2 construction data.
Data Availability Number |
SPS2_PROJECT_
STATIONS |
SPS2_Subgrade_
PREP |
SPS2_UNBOUND_
Agg_base |
Core Sections (Total 155 sections) |
At all levels (A to E) |
143 sections |
153 sections |
92 sections (194 records) |
At level E only |
143 sections |
141 sections |
92 sections (181 records) |
Percent data at level E |
100 |
92 |
100 |
Core sections missing data
at all levels |
12 |
12 |
12 (only 8 sections at each site) |
Sites with missing data at
all levels |
WI |
WI |
WI |
Supplemental Sections (Total 40
Sections) |
Supplemental sections with
data |
32 |
34 |
20 |
Supplemental sections
missing data |
8 |
6 |
20 |
Over 90 percent of the existing pavement structure data are at
level E, but some data for several SPS-2 core sections were not
available at the time of analysis. However, the supplemental
sections were missing a lot of data at the time of analysis, as
shown in these tables. The Wisconsin SPS-2 site represents most of
the missing data, as it was a new site at the time of analysis.
Material Testing Data
Field and laboratory tests are conducted to establish material
properties and characteristics for LTPP sections. Characterization
of material properties and the variations in these properties
between and within the test sections is required to evaluate causes
of performance differences between test sections. The materials
characterization includes parameters used in current pavement
design and mechanical analysis models.
Material sampling and testing requirements are documented in the
SPS-2 Material Sampling and Testing Requirements
report.(3) This report includes the development of SPS-2
sampling and testing plans, field material sampling and testing
requirements, and laboratory material testing requirements for each
SPS-2 site. The SPS-2 material sampling and testing plans for
subgrade and bases are provided in table 14, while the material
sampling and testing plans for PCC surface are presented in table
15.
The sampling and testing plan specified methods for material
sampling and testing at the site level for similar material and
structure layers. Therefore, the evaluation of the material testing
data should also be conducted at the SPS-2 site level.
Since there is a comprehensive LTPP material data review study
underway, only the key data elements for the PCC surface from the
SPS-2 sampling and testing plan were evaluated in this study.
Table 14. SPS-2 materials sampling and testing plan for
subgrade and bases.
Material Type and Properties |
LTPP Designation |
LTPP Protocol |
Minimum No. of Tests per Layer |
SUBGRADE OR EMBANKMENT
Sieve analysis
Hydrometer to 0.001 mm
Atterberg limits
Classification
(visual manual only on thin-wall tubes)
Moisture-density relations
Resilient modulus
(if thin-wall tube is not available)
Unit weight (if thin-wall tube is not available, test is not
conducted)
Natural moisture content
Unconfined comp. strength
(if thin-wall tube is not available, test is not conducted)
Permeability
Permeability |
SS01
SS02
SS03
SS04
SS05
SS07
SS08
SS09
SS10
SS11
UG09 |
P51
P42
P43
P52
P55
P46
P56
P49
P54
P57
P48 |
6
6
6
6
18
6
6
6
6
6
6
3
6 |
UNBOUND GRANULAR BASE
Particle size analysis
Sieve analysis (washed)
Atterberg limits
Moisture-density relations
Resilient modulus
Classification
Permeability
Natural moisture content |
UG01
UG02
UG04
UG05
UG07
UG08
UG09
UG10 |
P41
P41
P43
P44
P46
P47
P48
P49 |
3
3
3
3
3
3
3
3 |
PERMEABLE-TREATED ASPHALT BASE
Asphalt content (extraction)
Extracted aggregate:
Gradation of aggregate |
AC04
AC04 |
P04
P14 |
3
3 |
LEAN CONCRETE BASE
Compressive strength
7 day
28 day
1 year
Core examination and thickness |
PC01
PC06 |
P61
(beams, cores)
P66 |
14 (6, 8)
14 (6, 8)
14 (6, 8)
24 (all cores) |
Table 15. SPS-2 materials sampling and testing plan for
the PCC surface.
PCC Properties |
LTPP Designation |
LTPP Protocol |
Minimum No. of Tests per Layer |
Compressive strength
14 day 3.8 MPa
14 day 6.2 MPa
28 day 3.8 MPa
28 day 6.2 MPa
1 year 3.8 MPa
1 year 6.2 MPa |
PC01 |
P61
(beam, cores) |
9 (3, 6)
9 (3, 6)
9 (3, 6)
9 (3, 6)
9 (3, 6)
9 (3, 6) |
Splitting tensile strength
14 day 3.8 MPa
14 day 6.2 MPa
28 day 3.8 MPa
28 day 6.2 MPa
1 year 3.8 MPa
1 year 6.2 MPa |
PC02 |
P62
(beam, cores) |
9 (3, 6)
9 (3, 6)
9 (3, 6)
9 (3, 6)
9 (3, 6)
9 (3, 6) |
Coefficient of thermal expansion |
PC03 |
P63 |
2 |
Static modulus of elasticity
28 day 3.8 MPa
28 day 6.2 MPa
1 year 3.8 MPa
1 year 6.2 MPa |
PC04 |
P64 |
6
6
6
6 |
PCC unit weight |
PC05 |
P65 |
12 |
Core examination thickness |
PC06 |
P66 |
98 (all cores) |
Air content, 28 day |
PC08 |
P68 |
2 |
Flexural strength
14 day 3.8 MPa
14 day 6.2 MPa
28 day 3.8 MPa
28 day 6.2 MPa
1 year 3.8 MPa
1 year 6.2 MPa |
PC09 |
P69 |
3
3
3
3
3
3 |
For the SPS-2 experiment, the following materials testing tables
were evaluated for data availability and completeness:
- TST_PC01-Compressive strength of in-place concrete test results
for PCC layers.
- TST_PC02-Split tensile strength test results for PCC
layers.
- TST_PC09-Flexural strength.
- TST_PC06-Core examination and thickness.
There are currently no data available on coefficient of thermal
expansion for SPS-2 sections; such data are an essential variable
for any mechanistic analysis.
The data availability and completeness assessment results for
these key PCC materials testing tables are presented in table 16.
As shown, 9 of 13 projects have good to excellent data availability
for these tables, ranging from 81 to 100 percent tests completed.
Three sites-Arkansas, Kansas, and Wisconsin-have a fair amount of
PCC testing data available, ranging from 66 to 71 percent. The
North Carolina SPS-2 project is missing much PCC testing data at
the time of analysis, with only 33 percent available.
Traffic Data
Traffic data provide estimates of annual vehicle counts by
vehicle classification, and distributions of axle weights by axle
type. Annual traffic summary statistics are stored in the IMS
traffic module. Data are provided for each year since the road was
opened to traffic. With few exceptions (such as annual average
daily traffic (AADT)-based values), the information applies only to
the lane being studied. Traffic data are collected by the
individual States/Provinces using a combination of permanent and
portable equipment.
For the SPS-2 experiment, traffic data are generally obtained at
the site level. In places where an intersection is located within
the test site (thus resulting in different traffic levels on the
test sections), measurements of the traffic level on the different
groups of sections on each side of the intersection should be
obtained. For simplicity and consistency, a traffic data
availability assessment is conducted on a section-by-section
basis.
The SPS-2 experiment design calls for continuous weigh-in-motion
(WIM) monitoring, as permitted by WIM scale operating conditions.
Table TRF_MONITOR_BASIC_INFO was examined to identify SPS-2 records
containing WIM records, automatic vehicle classifier (AVC) data,
and annual ESAL estimates. The WIM and AVC data were further
classified into "at least 1 day" and "continuous" monitoring
frequency categories. Continuous AVC monitoring was defined as over
300 AVC monitoring days in a given year. Continuous WIM monitoring
was defined as over 210 WIM monitoring days in a given year.
Table 17 summarizes the data availability and completeness for
SPS-2 traffic data. As shown, very few sections have continuous WIM
or AVC monitoring data stored in the IMS database. Non-zero
computed annual ESALs were found for 84 core SPS-2 sections at 8
sites with 83 records at level E status. A total of 71 core
sections (nearly half of the core sections) have neither WIM
monitoring data nor annual ESAL estimates data in the table
TRF_MONITOR_BASIC_INFO. Additional annual ESAL estimates were
available for 15 supplemental sections located in 6 different
States.
Table 16. Data availability assessment for key PCC
material testing tables.
Tables |
TST_PC01 Comp. Strength |
TST_PC02 Split Tensile |
TST_PC09 Flex. Strength |
TST_PC06 Core Exam. |
All |
Min. Req'd* |
Total 27 |
27 |
9 |
98 |
224 |
Core Section Summary |
702 records (96%
at level E) |
613 records (87%
at level E) |
282 records (88%
at level E) |
1121 (100% at E) |
Avg. % Tests
Conducted (% range) |
States Cells |
3.8 MPa |
6.2 MPa |
3.8 MPa |
6.2 MPa |
3.8 MPa |
6.2 MPa |
All |
AZ |
28 (>100%) |
26 (96%) |
26 (96%) |
28 (>100%) |
9 (100%) |
18 (>100%) |
114 (>100%) |
99% (96 -
>100%) |
AR |
19 (70%) |
18 (67%) |
10 (37%) |
10 (37%) |
15 (>100%) |
6
(67%) |
120 (>100%) |
68% (37 -
>100%) |
CO |
72 (>100%) |
86 (>100%) |
53 (>100%) |
53 (>100%) |
25 (>100%) |
27 (>100%) |
57 (58%) |
94% (58 -
>100%) |
DE |
21 (78%) |
31 (>100%) |
21 (78%) |
26 (96%) |
9 (100%) |
9
(100%) |
82 (84%) |
91% (78 -
>100%) |
IA |
26 (96%) |
25 (93%) |
27 (100%) |
27 (100%) |
9 (100%) |
9 (100%) |
121 (>100%) |
98% (93 -
>100%) |
KS |
19 (70%) |
17 (63%) |
17 (63%) |
17 (63%) |
21 (>100%) |
17 (>100%) |
0 |
66% (0 -
>100%) |
MI |
24 (89%) |
18 (67%) |
23 (85%) |
17 (63%) |
9 (100%) |
7 (78%) |
88 (90%) |
82% (63 -
100%) |
NV |
27 (100%) |
24 (89%) |
27 (100%) |
24 (89%) |
9 100%) |
9 100%) |
116 (>100%) |
97% (89 -
>100%) |
NC |
7 (26%) |
24 (89%) |
12 44%) |
12 44%) |
2 (22%) |
3 (33%) |
0 |
37% (0 - 89
%) |
ND |
27 (100%) |
24 (89%) |
14 (52%) |
13 (48%) |
8 (89%) |
8 (89%) |
98 (100%) |
81% (48 -
100%) |
OH |
26 (96%) |
25 (93%) |
28 (>100%) |
23 (85%) |
9 (100%) |
9 100%) |
125 (>100%) |
96% (93 -
>100%) |
WA |
29 (>100%) |
27 (100%) |
30 (>100%) |
27 (100%) |
12 (>100%) |
9 (100%) |
122 (>100%) |
100% |
WI |
18 (67%) |
20 (74%) |
18 (67%) |
20 (74%) |
6 (67%) |
8 (89%) |
62 (63%) |
71% (67 -
89%) |
*Note: Min. req'd refers to the
minimum number of tests required for the PCC layer.
Table 17. Traffic monitoring data availability assessment
for SPS-2 experiment.
Data Availability |
AVC |
WIM |
With at Least1-Year Annual ESAL
Computed |
At least 1 day |
Continuous |
At least 1 day |
Continuous |
Core Sections (Total 155 Sections) |
At all levels (A to E) |
96 |
37 |
84 |
23 |
84 |
At level E only |
83 |
12 |
83 |
10 |
83 |
Percent data at level E |
86 |
32 |
99 |
43 |
99 |
Core sections missing data
at all levels |
59 |
118 |
71 |
132 |
71 |
Sites with NO data at all
levels |
4 |
9 |
5 |
11 |
5 |
Supplemental Sections (Total 40
Sections) |
Supplemental sections with
data |
15 |
4 |
15 |
2 |
15 |
Supplemental sections
missing data |
25 |
36 |
25 |
38 |
25 |
Climate Data
There are three types of climatic information: general
environmental, automated weather station (AWS), and seasonal
monitoring. General environmental and AWS data for the SPS-2
project are obtained at a project or site level.
The general environmental information includes actual
measurements from at least one nearby weather station for each LTPP
site. In addition, a site-specific statistical estimate based on as
many as five nearby weather stations is available. The estimates
are called virtual weather stations. The IMS contains
monthly and annual summary statistics. Daily data for both the
virtual weather stations and actual weather stations are kept
offline. General environmental data available in the IMS are
derived from weather data originally collected from the National
Climatic Data Center and the Canadian Climatic Center.
AWSs have been installed at nearly all of the SPS-2 project
sites. The equipment provides site-specific information for the
same parameters as the general environmental tables. AWS tables are
available with monthly, daily, or hourly statistics.
The availability of both types of climatic data is shown in
table 18. As noted, historic climatic data are available for all
SPS-2 sites except Wisconsin. AWS data are available for 10 of 13
SPS-2 sites; Arkansas, Delaware, and Wisconsin have no data. The
time periods covered by the AWS data at these sites range from 3 to
6 years.
Table 18. SPS-2 climate information
availability.
State |
Age as of August1999 |
General Environment Information, Number
of Years with Data |
AWS, Number of Years with Data |
Temperature |
Precipitation |
Temperature |
Precipitation |
At All Levels |
At Level E |
At All Levels |
At Level E |
At All Levels |
At Level E |
AZ |
5.8 |
17 |
15 |
17 |
17 |
6 |
6 |
AR |
3.8 |
17 |
17 |
17 |
17 |
0 |
- |
CO |
5.8 |
17 |
17 |
17 |
17 |
5 |
5 |
DE |
3.3 |
17 |
17 |
17 |
17 |
0 |
- |
IA |
5.0 |
17 |
17 |
17 |
17 |
3 |
3 |
KS |
7.1 |
17 |
17 |
17 |
17 |
4 |
4 |
MI |
5.8 |
17 |
17 |
17 |
17 |
3 |
3 |
NV |
4.0 |
17 |
17 |
17 |
17 |
5 |
5 |
NC |
5.1 |
17 |
17 |
17 |
17 |
5 |
5 |
ND |
4.8 |
17 |
17 |
17 |
17 |
5 |
5 |
OH |
2.9 |
17 |
17 |
17 |
17 |
6 |
6 |
WA |
3.8 |
17 |
17 |
17 |
17 |
5 |
5 |
WI |
1.8 |
0 |
0 |
0 |
0 |
0 |
0 |
Monitoring Data
Seven types of monitoring data are included in the LTPP IMS:
automated distress, manual distress, friction, longitudinal
profile, cross profile, deflection, and dynamic load response. The
monitoring data reviewed for the SPS-2 project are broken into the
following categories for discussion:
- Longitudinal profile data.
- Deflection data.
- Manual and photographic distress data.
- Friction data.
In this section, the monitoring frequency requirement is
discussed first, followed by the data availability and completeness
assessment of all the categories.
Monitoring Frequency
During the life of these pavement sections, multiple directives
have been issued regarding the testing frequency for each type of
monitoring data collected. Some of these directives have slightly
adjusted the testing intervals during the life of the program. The
following is a list of the key documents and directives that affect
the monitoring frequency requirement for the SPS-2 project:
1. Data Collection Guide for Long-Term Pavement Performance
Studies.(2)
2. LTPP Directive D-02: Quality Assurance of PASCO
Products.(4)
3. LTPP Directive D-05: Measurement Frequency and Priorities
of Manual Distress Surveys.(5)
4. LTPP Directive FWD-03: Deflection Monitoring Frequency
Priorities and Use of FWDs Owned by Other
Agencies.(6)
5. LTPP Directive FWD-10: Deflection Monitoring Frequencies
and Priorities.(7)
6. LTPP Directive P-02: Profile Monitoring Frequencies and
Priorities.(8)
7. LTPP Directive GO-20: Revised Friction Measurement
Requirements.(9)
8. LTPP Directive GO-21: LTPP Test Section Monitoring
Adjustments.(10)
These directives were used to identify all previous testing
frequencies for each type of monitoring data collected, and are
summarized in table 19. For supplemental sections, the monitoring
frequencies are every 3 years for manual distress and joint
faulting monitoring, every 2 years and responsive for photographic
survey, and every 5 years and responsive for falling-weight
deflectometer (FWD) testing.
Table 19. Testing frequencies for SPS-2 monitoring data
collection.
Data Collection Type |
Postconstruction Monitoring |
Long-Term Monitoring Frequency |
In Effect Before October 1,
1999 |
In Effect After October 1, 1999 |
Longitudinal profile |
< 6 months is permitted |
Biennially, but may be postponed up to 1
year |
Annually |
Deflection (for nonfractured PCC) |
< 6 months is permitted |
Biennially and responsive |
Biennially and responsive |
Manual distress and faulting |
< 3 months |
Biennially, but may be postponed up to 1
year |
Annually |
Photographic |
Not specified |
- |
Biennially |
Friction |
<12 months |
Biennially |
Not specified |
In addition, close-out monitoring consisting of FWD, profile,
and manual distress surveys should be conducted on each section.
According to LTPP Directive GO-21, this monitoring is performed
"when it is determined that the test section will be taken
out-of-study (due to a construction event or at the option of the
highway agency) or at the end of the field monitoring portion of
the LTPP program, whichever comes first." (10)
The testing frequency requirements specified in LTPP Directive
GO-21 are also listed in the table. This requirement has been in
effect since October 1, 1999.
Monitoring Data
Assessment
The following IMS monitoring tables are used in evaluating the
data availability and completeness for SPS-2 monitoring:
- MON_PROFILE_MASTER-Monitoring profilometer master record.
- MON_DEFL_DROP_DATA-Peak and other drop-specific data values for
Dynatest FWD.
- MON_DIS_JPCP_FAULT_SECT-Section faulting statistics for
transverse joints and cracks.
- MON_DIS_JPCP_REV-Distress identification for jointed PCC
surfaces.
- MON_DIS_PADIAS_JPCP-Distress identification for JPCP
surfaces.
- MON_DIS_PADIAS42_JPCP-Distress identification for jointed PCC
surfaces.
- MON_FRICTION-Friction-resistance measurements.
Tables 20 to 24 show summaries of the data availability
assessment for longitudinal profile, deflection, faulting, manual,
and photographic distress surveys, and friction-monitoring data for
SPS-2. Using the minimum monitoring data collection requirement
noted in these tables, an assessment of this data availability and
completeness follows:
- Longitudinal profile data are acceptable for most sites, but
some are seriously deficient (such as Arkansas and North Dakota)
with very late initial longitudinal profile measurement.
- Deflection data are very complete. The only exception is the
late initial survey at the Arkansas site.
- Faulting data are very deficient at the Kansas site. Data from
Arizona, Arkansas, Colorado, and North Carolina are late. The other
eight sites have adequate faulting data.
- Combined distress data satisfies the minimum requirement,
except for the initial surveys of Arizona, Arkansas, and North
Dakota.
- Friction monitoring data are deficient, with very few test
visits, too-long survey intervals, and far too long to initial
friction measurement.
Table 20. Summary of the number of the surveys for
longitudinal profile data collection.
SPS-2 Project in State |
Age as of Aug. 1999 |
No. of Test Visits |
Long-Term Interval, year |
Initial Survey Age, month |
Meet Minimum Requirement? * |
Core Sections |
Suppl. Sections |
Avg (min-max) |
% At E |
Avg (min-max) |
Avg (min-max) |
AZ |
6.3 |
4.9 (4-5) |
100 |
5.0 (5-5) |
1.3 (1-2) |
3.8 (4-4) |
|
AR |
4.3 |
1.0 (1-1) |
100 |
N/A |
N/A |
16.2 (16-16) |
Not the initial survey |
CO |
6.3 |
3.0 (3-3) |
100 |
3.0 (3-3) |
2.2 (2-2) |
6.4 (6-6) |
|
DE |
3.7 |
6.0 (6-6) |
100 |
6.0 (6-6) |
0.3 (0-0) |
7.2 (7-7) |
|
IA |
5.4 |
4.9 (4-5) |
100 |
5.0 (5-5) |
1.1 (1-1) |
6.5 (7-7) |
|
KS |
7.5 |
7.9 (7-8) |
100 |
7.0 (7-7) |
0.9 (1-1) |
2.0 (1-8) |
|
MI |
6.2 |
8.6 (7-9) |
99 |
9.0 (9-9) |
0.6 (1-1) |
10.2 (10-10) |
|
NV |
4.4 |
3.6 (2-4) |
100 |
4.0 (4-4) |
0.7 (1-1) |
10.9 (11-11) |
|
NC |
5.5 |
7.9 (7-8) |
100 |
7.5 (7-8) |
0.7 (1-1) |
<0 (-3-3) |
|
ND |
5.3 |
2.0 (2-2) |
100 |
2.0 (2-2) |
2.0 (2-2) |
31.0 (31-31) |
Not the initial survey |
OH |
3.3 |
4.0 (4-4) |
100 |
3.4 (3-4) |
0.7 (1-1) |
<0 (-1-1) |
|
WA |
4.2 |
4.0 (4-4) |
100 |
4.0 (4-4) |
1.2 (1-1) |
0.6 (1-1) |
|
WI |
2.3 |
3.0 (3-3) |
100 |
3.0 (3-3) |
0.7 (1-1) |
2.0 (2-2) |
|
Note: * Minimum longitudinal profile
data collection requirement: Within 12 months for the initial
survey, and less than 3 years for all long-term monitoring
intervals (i.e., biannually, but may be postponed up to 1
year).
Table 21. Summary of the number of the surveys for
deflection data collection.
SPS-2 Project in State |
Age as of Aug. 1999 |
No. of Test Visits |
Long-Term Interval, year |
Initial Survey Age, month |
Meet Minimum Requirement? * |
Core Sections |
Suppl. Sections |
Avg (min-max) |
% At E |
Avg (min-max) |
Avg (min-max) |
AZ |
6.3 |
6.1 (5-7) |
100 |
2.3 (1-5) |
1.1 (1-1) |
<0 (-2-2) |
|
AR |
4.3 |
1.5 (1-2) |
100 |
N/A |
0.0 (0-0) |
13.5 (13-14) |
Not the initial survey |
CO |
6.3 |
4.2 (3-5) |
100 |
3.0 (3-3) |
1.6 (1-2) |
0.5 (-2-6) |
|
DE |
3.7 |
2.2 (2-3) |
100 |
2.0 (2-2) |
1.2 (1-1) |
0.2 (0-0) |
|
IA |
5.4 |
1.4 (1-2) |
100 |
1.0 (1-1) |
2.6 (3-3) |
5.3 (3-35) |
OK except for 0219 |
KS |
7.5 |
5.3 (5-7) |
100 |
2.0 (2-2) |
1.1 (1-1) |
1.1 (1-1) |
|
MI |
6.2 |
4.2 (3-5) |
100 |
4.0 (4-4) |
1.4 (1-2) |
0.5 (0-1) |
|
NV |
4.4 |
4.0 (2-6) |
100 |
2.0 (2-2) |
0.7 (0-1) |
<0 (-2-1) |
|
NC |
5.5 |
2.4 (2-5) |
100 |
2.0 (2-2) |
1.9 (1-2) |
<0 (-2-2) |
|
ND |
5.3 |
1.3 (1-2) |
100 |
1.3 (1-2) |
0.8 (1-1) |
1.1 (1-1) |
|
OH |
3.3 |
3.9 (3-5) |
100 |
3.3 (2-4) |
0.6 (0-1) |
<0 (-14--12) |
|
WA |
4.2 |
4.7 (4-5) |
100 |
4.0 (4-4) |
0.9 (1-1) |
<0 (-4-4) |
|
WI |
2.3 |
1.0 (1-1) |
0 |
0.9 (0-1) |
N/A |
6.8 (7-7) |
|
Note: * Minimum deflection data
collection requirement: Within 12 months for the initial survey,
and less than 3 years for all long-term monitoring intervals (i.e.,
biannually, but may be postponed up to 1 year).
Table 22. Summary of the number of the surveys for
faulting data collection.
SPS-2 Project in State |
Age as of Aug. 1999 |
No. of Test Visits |
Long-Term Interval, year |
Initial Survey Age, month |
Meet Minimum Requirement? * |
Core Sections |
Suppl. Sections |
Avg (min-max) |
% At E |
Avg (min-max) |
Avg(min-max) |
AZ |
6.3 |
2.6 (2-3) |
100 |
2.3 (0-3) |
1.7 (1-2) |
29 (17-49) |
Not the initial survey |
AR |
4.3 |
1.0 (1-1) |
100 |
N/A |
N/A |
14 (13-14) |
Not the initial survey |
CO |
6.3 |
3.0 (3-3) |
100 |
3.0 (3-3) |
1.7 (2-2) |
30.8 (31-31) |
Not the initial survey |
DE |
3.7 |
3.2 (3-4) |
100 |
3.0 (3-3) |
1.5 (1-2) |
0.2 (0-0) |
|
IA |
5.4 |
2.8 (2-3) |
100 |
2.0 (2-2) |
2.9 (2-5) |
2.6 (3-3) |
|
KS |
7.5 |
1.9 (1-2) |
100 |
1.0 (1-1) |
4.1 (4-4) |
13.4 (9-59) |
No |
MI |
6.2 |
4.8 (3-6) |
100 |
4.0 (4-4) |
1.4 (1-1) |
0.5 (0-1) |
|
NV |
4.4 |
2.2 (2-3) |
100 |
2.0 (2-2) |
2.1 (1-3) |
7.9 (8-8) |
|
NC |
5.5 |
2.4 (1-6) |
100 |
2.0 (2-2) |
2.6 (1-3) |
2.6 (0-33) |
Not the initial survey for 0204, 0208,
0212 |
ND |
5.3 |
2.1 (1-3) |
100 |
1.7 (1-2) |
3.9 (2-5) |
0.8 (1-1) |
|
OH |
3.3 |
2.0 (2-2) |
100 |
2.0 (2-2) |
2.7 (3-3) |
3.4 (3-3) |
|
WA |
4.2 |
3.0 (3-3) |
100 |
3.0 (3-3) |
1.5 (1-1) |
0.0 (0-0) |
|
WI |
2.3 |
1.1 (1-2) |
0 |
0.9 (0-1) |
N/A |
6.8 (7-7) |
|
Note: * Minimum faulting data
collection requirement: Within 12 months for the initial survey,
and less than 3 years for all long-term monitoring intervals (i.e.,
biannually, but may be postponed up to 1 year).
Table 23. Summary of the number of the surveys for manual
and photographic distress data collection.
SPS-2 Project in State |
Age as of Aug. 1999 |
No. of Test Visits |
Long-Term Interval, year |
Initial Survey Age, month |
Meet Minimum Requirement? * |
Core Sections |
Suppl. Sections |
Avg (min-max) |
% At E |
Avg (min-max) |
Avg (min-max) |
AZ |
6.3 |
3.6 (3-4) |
100 |
3.1 (0-4) |
1.5 (1-2) |
17.2 (17-18) |
Not the initial survey |
AR |
4.3 |
1.0 (1-1) |
100 |
N/A |
N/A |
13.5 (13-14) |
Not the initial survey |
CO |
6.3 |
5.1 (5-6) |
100 |
5.0 (5-5) |
1.3 (1-1) |
9.4 (9-9) |
|
DE |
3.7 |
3.2 (3-4) |
100 |
3.0 (3-3) |
1.5 (1-2) |
0.2 (0-0) |
|
IA |
5.4 |
3.8 (3-5) |
100 |
3.0 (3-3) |
1.7 (1-2) |
2.6 (3-3) |
|
KS |
7.5 |
3.8 (3-4) |
100 |
4.0 (4-4) |
1.5 (1-2) |
9.2 (9-9) |
|
MI |
6.2 |
5.8 (4-7) |
100 |
6.0 (6-6) |
1.1 (1-1) |
0.5 (0-1) |
|
NV |
4.4 |
3.2 (3-4) |
100 |
3.0 (3-3) |
1.1 (1-1) |
7.9 (8-8) |
|
NC |
5.5 |
2.5 (2-6) |
100 |
2.0 (2-2) |
1.0 (1-1) |
19.0 (17-19) |
Not the initial survey |
ND |
5.3 |
3.3 (3-4) |
100 |
3.0 (3-3) |
2.1 (2-2) |
0.8 (1-1) |
|
OH |
3.3 |
3.0 (3-3) |
100 |
2.6 (2-3) |
1.5 (2-2) |
<0 (0-0) |
|
WA |
4.2 |
3.0 (3-3) |
100 |
3.0 (3-3) |
1.5 (1-1) |
<0 (0-0) |
|
WI |
2.3 |
1.0 (1-1) |
0 |
0.9 (0-1) |
N/A |
6.8 (7-7) |
|
Note:* Minimum manual and photographic
data collection requirement: Within 12 months for the initial
survey, and less than 3 years for all long-term monitoring
intervals (i.e., biannually, but may be postponed up to 1
year).
Table 24. Summary of the number of the surveys for
friction data collection.
SPS-2 Project in State |
Age as of Aug. 1999 |
No. of Test Visits |
Long-Term Interval, year |
Initial Survey Age, month |
Meet Minimum Requirement? * |
Core Sections |
Suppl. Sections |
Avg (min-max) |
% At E |
Avg (min-max) |
Avg (min-max) |
AZ |
6.3 |
0 |
- |
- |
- |
- |
No Data |
AR |
4.3 |
0 |
- |
- |
- |
- |
No Data |
CO |
6.3 |
1.0 (1-1) |
100 |
1.0 (1-1) |
- |
7.0 (7-7) |
No |
DE |
3.7 |
0 |
- |
0.0 (0-0) |
- |
- |
No Data |
IA |
5.4 |
3.0 (3-3) |
100 |
3.0 (3-3) |
1.0 (1-1) |
13.0 (13-13) |
No |
KS |
7.5 |
2.0 (2-2) |
100 |
2.0 (2-2) |
1.1 (1-1) |
46.0 (46-46) |
No |
MI |
6.2 |
0.5 (0-1) |
100 |
1.0 (1-1) |
- |
46.8 (47-47) |
No |
NV |
4.4 |
0 |
- |
0.0 (0-0) |
- |
- |
No Data |
NC |
5.5 |
0 |
- |
0.0 (0-0) |
- |
- |
No Data |
ND |
5.3 |
0 |
- |
0.0 (0-0) |
- |
- |
No Data |
OH |
3.3 |
0 |
- |
0.0 (0-0) |
- |
- |
No Data |
WA |
4.2 |
2.0 (2-2) |
100 |
2.0 (2-2) |
0.5 (0-1) |
10.5 (6-11) |
|
WI |
2.3 |
0 |
- |
- |
- |
- |
No Data |
Note:* Minimum friction data
collection requirement: Within 12 months for the initial survey,
and less than 3 years for all long-term monitoring intervals (i.e.,
biannually, but may be postponed up to 1 year).
Dynamic Load-Response Data
Various PCC pavement sections of the SPS-2 project were selected
for measuring pavement response under controlled loading
conditions. Both deflections and strains at defined positions
within the slab were recorded under loading by known vehicles.
Deflections of the PCC surface were measured at six locations
(corner, midslab edge, and midslab out wheel path) within two
adjacent slabs. The pavement surface strains were measured using
surface-mounted strain gauges located at midslab within the wheel
path and midslab along the slab edge. Data from a total of 30
traces were obtained from each pass of the loaded vehicle, with
multiple repetitions at multiple speeds collected at various times
of the day. During the early life of the pavement, dynamic
load-response data were collected on a quarterly basis. Data
collection was terminated after 2 years.
The dynamic load-response data for PCC sections are stored in
the DLR_* module in the following seven IMS tables:
- DLR_LVDT_CONFIG_PCC-LVDT gauge device, settings, and location
information.
- DLR_LVDT_TRACE_SUM_PCC-LVDT trace summary information.
- DLR_MASTER-Dynamic load response site and instrumentation
summary information.
- DLR_STRAIN_CONFIG_PCC-Sensor gauge device, settings, and
location information.
- DLR_STRAIN_TRACE_SUM_PCC-Data load response strain trace
summary information.
- DLR_TEST_MATRIX-Data load response test matrix summary
information.
- DLR_TRUCK_GEOMETRY-Data load response truck geometry summary
information.
The only dynamic load response data in the IMS database are from
the North Carolina and Ohio SPS-2 sites. The data availability
assessment of these tables is provided in table 25. All records in
these tables are at level E. As shown in the table, significant
amounts of stress and strain data are available on the instrumented
sections. These data should be very useful for the analysis of the
pavement dynamic load responses.
Table 25. Data availability assessment for SPS-2 dynamic
load response data.
Table Name |
Total Records (All at E) |
State |
Records for Each Section |
|
|
|
|
DLR_LVDT_PCC |
880 |
37 |
112 |
112 |
112 |
112 |
39 |
96 |
112 |
112 |
112 |
DLR_LVDT_TRACE_SUM_PCC |
39,421 |
37 |
9,089 |
9,106 |
8,146 |
9,954 |
39 |
760 |
809 |
810 |
747 |
DLR_MASTER_PCC |
59 |
37 |
8 |
8 |
8 |
8 |
39 |
6 |
7 |
7 |
7 |
DLR_STRAIN_CONFIG_PCC |
1,051 |
37 |
128 |
128 |
128 |
127 |
39 |
120 |
140 |
140 |
140 |
DLR_STRAIN_TRACE_SUM_PCC |
31,659 |
37 |
7,658 |
8,128 |
6,348 |
8,674 |
39 |
199 |
136 |
240 |
276 |
DLR_TEST_MATRIX |
3,350 |
37 |
556 |
681 |
804 |
803 |
39 |
108 |
133 |
134 |
131 |
DLR_TRUCK_GEOMETRY |
3 |
37 |
2 Truck load/types |
39 |
1 Truck ID/type |
Summary of SPS-2 Data Availability
and Completeness Assessment
Table 26 summarizes the data availability and completeness by
key data types that are not subject to long-term monitoring, while
table 27 summarizes the data availability and completeness for the
key data types subject to long-term monitoring. Note that any
rating of "fair" or "poor" means that these sites would not meet
analysis needs and therefore must be improved as soon as possible.
The SPS-2 data deficiencies are summarized below:
- Wisconsin-newly constructed, data processing underway.
- Arizona, Arkansas, and North Carolina-late initial survey for
most monitoring types.
- Colorado and North Dakota-late initial survey for one
monitoring collection activity, either longitudinal profile
measurements, deflection testing, faulting, or distress data.
- Kansas SPS-2-very deficient faulting data.
- Traffic data are very deficient for 5 of 13 sites (40
percent).
- Joint faulting data are not being collected at the frequency
specified by LTPP data collection guidelines, and this will limit
the analyses that can be conducted.
- Friction data are completely deficient for most projects (11
out of 13).
- Arkansas, Kansas, North Carolina, and Wisconsin are missing
significant PCC material testing data at the time of analysis.
A very good percentage of the SPS-2 data are at level E. More
than 82 percent of the records are at level E for all data types,
with many greater than 99 percent. The availability and
completeness of data for the SPS-2 experiment is good overall.
However, a significant amount of data was not available at the time
of analysis, especially traffic, distress and faulting surveys, and
key materials testing data. These deficiencies need to be addressed
before serious data analysis can be undertaken. There is an active
plan in place to address the deficient materials testing and
traffic data.
Table 26. Summary of the SPS-2 data availability and
completeness for key data types.
Type of Data |
SPS-2 Core Sections-Total 13 Sites, 155
Sections |
SPS-2 Supplemental Sections-Total 40
Sections |
No. Sites
(Sections) |
% At Level E |
Comments |
W/ Data |
Missing Data |
Site information (reports, location, and
significant dates data) |
13 sites
(155) |
ND-Construction date |
100 |
Excellent |
Excellent-Same as the core sections |
Key design features (drainage and lane
width) |
11 sites
(131) |
KS, WI (all 24 sections) |
100 |
Good |
Good-Available for 27 to 29 sections |
Pavement structure (subgrade layer, base,
surface) |
12 sites
(143) |
WI |
82-89 |
Good |
Good-Available for 26 to 30 sections |
SPS-2 construction type data |
11 to 13
(92-155) |
AZ, OH, WA, WI (2 to 16
sections) |
90-100 |
Good |
Good-Available for 20 to 34 sections |
Key PCC material testing |
9 sites |
AR, KS, NC, and WI |
87-100 |
Fair to good |
Not evaluated |
Table 27. Summary of the SPS-2 data availability and
completeness assessment for traffic, climate, and monitoring data
types.
Monitoring Data Types |
SPS-2 Sites and Core Sections-Total 13
Sites, 155 Sections |
Comments |
Initial Survey <12
month |
Long-Term Max. <3
years |
No Data |
% at Level E |
Yes |
No |
Yes |
No |
Longitudinal profile |
11 |
AR, ND |
13 |
0 |
- |
99.9 |
Good |
Deflection |
11 |
AR,
IA (0219) |
13 |
0 |
- |
86 |
Good |
Faulting |
9 |
AZ, AR, CO, NC (0204, 0208,
0212) |
12 |
KS |
- |
99 |
Fair |
Distress-manual and PASCO |
10 |
AZ, AR, NC |
13 |
0 |
- |
100 |
Fair |
Friction |
2 |
11 sites |
2 |
11 |
8 sites |
92 |
Poor |
Traffic and Climatic
Data |
Sites with
Data |
No Data |
% At Level E |
Comments |
Traffic |
Eight sites have at least 1 day of
WIM data at 1 year. |
5 sites |
83 |
Poor |
Climate |
Twelve sites have 17 years of
general climatic data. Ten sites have 3 to 6 years of AWS
data. |
WI |
>99 |
Excellent |
|