Structural Factors of Jointed Plain Concrete Pavements: SPS-2—Initial Evaluation and AnalysisChapter 7. Summary, Conclusions, and Recommendations
The SPS-2 project, Strategic Study of Structural Factors for
Rigid Pavement of Jointed Plain Concrete Pavements, is one of
the key experiments in the LTPP program. The main objective is to
determine the relative influence and long-term effectiveness of the
JPC pavement strategic factors that affect its performance. There
are some concerns about the ability of the SPS-2 experiment to meet
those expectations, given that several SPS-2 sites were not
constructed. In addition, at the SPS-2 sites that were constructed,
some construction deviations and data collection deficiencies
exist.
This study provides the first comprehensive review and
evaluation of the SPS-2 experiment. Issues of experimental design,
construction quality, data availability and completeness, and early
performance trends are addressed in this report. The key findings
are summarized in this chapter. This chapter also presents the
research team's recommendations on improving the SPS-2 experiment
and its data availability, expectations of the SPS-2 experiment,
and future data collection and analysis topics.
SPS-2 Experimental Site Status
As of January 2000, 13 SPS-2 sites have been constructed
throughout the United States. An additional site in California has
been nominated and is currently under construction. The full
factorial of the original experimental design is not completely
satisfied by the constructed sites, leaving a portion (31 percent)
of the desired inference space (subgrade and climate) with no
experimental sites.
These 14 sites fill in 11 of the 16 SPS-2 experiment factorial
cells and provide good coverage of major areas of the United
States. Five sites (31 percent) are missing from the original
experiment design, as listed below:
- Two sites in a wet no-freeze climate (southeast United States)
with a coarse-grained subgrade. Data from each site will fill half
of the design factorial.
- One site in a dry freeze climate (northwest United States) with
a fine-grained subgrade. Data from each site will fill half of the
design factorial.
- Two sites in a dry no-freeze climate (southwest United States),
one on a fine-grained subgrade and the other on a coarse-grained
subgrade. Data from each site will fill half of the design
factorial.
Five additional SPS-2 sites (60 sections total) are needed to
complete the design factorial. While it is impossible to determine
the exact effects at this time, the lack of data from these missing
sites will limit the results obtainable from the SPS-2 experiment,
as summarized below:
- There will be no performance data and, thus, no performance
findings from the missing sites.
- The missing site corresponding to the site in Arizona
(dry/no-freeze and coarse subgrade) will make it impossible to
determine (without confounding factors) the main effects and
interactions for the dry/no-freeze climate.
- The missing section at the Nevada site will reduce the findings
for that site and corresponding cell (although the Washington site
appears to be a replicate).
- Adequate SPS-2 sites exist in wet-freeze climates, making a
full inference space of performance data available. All main
effects and interactions in this climate should be
ascertainable.
- The number of SPS-2 sites in no-freeze climates, both wet and
dry areas, is deficient. There will be difficulties in determining
the main effects and interactions in these climates.
Some of these deficiencies can be overcome through use of
mechanistic data analysis. However, there is no mechanistic
analysis method that considers all factors involved, and the
missing data cells will always limit in the verification and
calibration of any performance models.
In addition to the 12 core sections at each site required by the
SPS-2 experiment, SHAs have built a total of 40 supplemental
sections with SPS-2 projects. The main value of the supplemental
sections will be as a direct comparison to the core sections. For
example, one supplemental section in Washington did not have
dowels, and this will provide a direct comparison to a similar
design with dowel bars. Various other comparisons are possible,
including skewed joints, base types, subdrainage, slab thickness,
asphalt concrete pavement, jointed reinforced concrete, special
dowels, and variable slab thickness. These sections are valuable to
the States, and efforts should be made to ensure that their
construction and monitoring data are collected and stored.
Data Availability and
Completeness
The SPS-2 project is an extremely valuable source of performance
data for modern concrete pavements. The performance of these
sections will be of great interest to all highway agencies building
concrete pavements, and of course to the concrete industry as well.
This report will be the major reference document for all future
SPS-2 research studies, and will be the major reference document
for the 14 SHAs that have constructed SPS-2 project sites.
Data elements that were considered to be essential to the SPS-2
experiment analyses have been assessed. The data availability and
completeness for the SPS-2 sites are considered good overall. A
high percentage of the SPS-2 data is at level E-greater than 82
percent for all data types, and greater than 99 percent for
many.
However, a significant amount of data is still missing,
especially traffic, distress and faulting surveys, and key
materials testing data. These deficiencies need to be addressed
before serious analysis of the SPS-2 experiment can occur.
The SPS-2 data deficiencies are summarized below:
- Wisconsin-newly constructed, data processing under way and all
data expected to be complete.
- Arizona, Arkansas, and North Carolina-late initial survey for
most monitoring types. Backcasting of IRI and distress data will be
required.
- Colorado and North Dakota-late initial survey for one
monitoring collection activity, either longitudinal profile
measurements, deflection testing, faulting, or distress data.
- Kansas SPS-2-very deficient faulting data. Faulting
measurements currently under way.
- Traffic data are very deficient for 5 of 13 sites (40
percent).
- Joint faulting data are not being collected as required by
LTPP, and this will limit the analyses that can be conducted.
- Arkansas, Kansas, North Carolina, and Wisconsin are missing
significant PCC materials testing data.
Note that the LTPP program is embarking on a systemwide effort
to resolve all missing data. Some missing data have already been
obtained. This effort will greatly improve the data availability
for future analysis.
Experimental Design versus Actual
Construction
Required experimental design factors were compared with the
actual constructed values stored in the IMS database. This database
includes both the site condition factors and pavement design
features. Most SPS-2 sections follow the experiment design for the
large majority of the design factors. Most deviations from the
experiment design are found in the concrete slab thickness and
14-day flexural strength. A number of sections were more than 12 mm
too thick or too thin, or were more than 10 percent too high or too
low in flexural strength.
Out of the 13 SPS-2 project locations, only the recently
constructed Wisconsin site does not have enough data in the IMS
database to be evaluated. These data are currently in the pipeline.
Of course, data from the California site under construction also
are not in the database at this time.
Eight projects can be characterized as good to excellent when
comparing designed versus constructed values, while the remaining
four projects are considered poor to fair.
In addition to the comparison of the designed versus constructed
values from the IMS database, construction reports of from all 13
SPS-2 reports sites were reviewed to identify construction
deviations and difficulties. Four projects were found to have
experienced more than minor construction difficulties or
deviations.
The following summarizes significant deviations when comparing
the designed versus constructed factorial factors, and more than
minor construction deviations:
- Delaware-significant deviations in both slab thickness and
flexural strength. This project is also considered to have moderate
construction deviations.
- Iowa-significant deviations in flexural strength, slab
thickness, and lane width. The lane width deviation may be a data
entry error. This project is also considered to have moderate
construction deviations.
- Michigan-moderate construction deviations.
- Nevada-significant deviations in subgrade type, flexural
strength, and slab thickness. This project is also considered to
have moderate construction deviations. Extensive cracking occurred
early, and one section has been taken out of service.
- Washington-significant deviations in flexural strength and slab
thickness. The traffic level for 1997 appears to be erroneous.
Early Performance Trends
The SPS-2 sections are relatively young, and a large majority
show little distress. As of January 2000, only 43 of 155 sections
(28 percent) are showing any noticeable distresses. Ninety-five
percent of the SPS-2 sections have less than 1 mm of edge joint
faulting. Eighty-seven percent of the SPS-2 sections show zero
transverse cracking, and 78 percent of the sections have zero
longitudinal cracking.
Based on the initial statistical analyses and comparisons, the
following initial performance trends are noted (note that long-term
performance may be different from short-term performance):
- The initial IRI of SPS-2 sections after placement ranged from
0.76 to 2.19 m/km with a mean of 1.30 m/km.
- JPCP constructed on coarse-grained soil were smoother (lower
initial IRI) than those constructed on fine-grained soils.
- JPCP constructed on PATB were smoother than sections
constructed on LCB or untreated aggregate base.
- The IRI trend over time depends heavily on the initial IRI, the
traffic loadings, and the extent of joint faulting.
- Sections with PATB show the lowest total longitudinal cracking
levels, while the sections with LCB show the highest longitudinal
cracking.
- Thinner (203 mm) slabs show more longitudinal cracks. Sections
with a thinner slab and widened slab show the highest level of
longitudinal cracking.
- Sections with PATB show the lowest percentage of slabs cracked
transversely, while the sections with an LCB show the highest
transverse cracking.
- Thinner (203 mm) slabs show more transverse cracks than thicker
slabs. Sections with a thinner slab and a widened slab show the
highest level of transverse cracking.
- Sections with aggregate base show the highest joint faulting
level. Sections with LCB and PATB have the lowest joint
faulting.
- Widened slab sections show less faulting than conventional
width slabs.
States' Expectations from the States
for the SPS-2 Experiment
Two national workshops were held where input was received from
the States on the SPS-2 project. The meetings were held on November
2-3, 1999, in Columbus, OH, and on April 27, 2000, in Newport, RI.
The research team made presentations at both conferences about the
status of SPS-2 data collection, analysis, and availability, and
the near- and long-term LTPP products. Several participating States
made presentations on the status and analyses of their SPS-2
projects, as well as the States' expectations of the SPS-2
experiment. There were many discussions of the future directions of
the SPS-2 experiment and the analyses of the SPS-2 data at both
conferences. Those discussions are summarized below.
In general, the States are satisfied with the SPS-2 experiment
and fully expect to get valuable information about different design
features from the project. Many States have been conducting or
planning their own analyses of their SPS-2 projects. Some analyses
have already yielded useful results. The States would like to see a
focus on implementation of SPS-2 findings as they evolve over
time.
First and foremost, what the States want to know the effect on
pavement performance and cost-effectiveness of the SPS-2
experimental factors, such as:
- Drainage and base type.
- Widened lanes.
- Slab thickness.
- Concrete strength.
In addition to the structural design features, the States also
would like to know what major site condition factors influence
performance of concrete pavement, including:
- Climate.
- Traffic volume and loading.
- Subgrade type properties.
- Embankment.
Other specific expectations from the States include:
- Evaluation of existing performance prediction equations (i.e.,
AASHTO formulas).
- Validation of pavement analysis models.
- Mechanistic/empirical calibration of lab materials properties,
backcalculated materials properties, and WIM data.
- Effects of soil type, base type, drainage, and climate on
long-term subgrade moisture gradients.
- Cost-effectiveness of drainable bases, underdrains,
high-strength concrete, different base types, and other
features.
- Dynamic load response of the concrete pavements (response of
PCC to single, tandem, and tridem axles; effect of vehicle speed on
dynamic response of PCC).
- Using stiffness rather than density for subgrade
acceptance.
As to the future analysis of SPS-2 data, the States believe that
it is worthwhile to complete the missing data (backcast if
necessary) to obtain traffic and materials data. Participants
believed that many fundamental studies can be conducted to see how
SPS-2 sections are responding to load and environmental stresses.
It was also suggested that an integrated analysis plan is needed
for future research.
Can SPS-2 Meet Expectations?
The specific experiment expectation of the SPS-2 project was to
determine the main effects and interactions of the following key
design features:
- Slab thickness.
- Concrete strength (14 day).
- Base type including PATB, LCB, and untreated aggregate
base.
- Lane width.
These main effects and interactions were to be determined for
each of the following subgrade and climatic conditions:
- Fine-grained and coarse-grained subgrade soils.
- Wet freeze, wet no-freeze, dry freeze, and dry no-freeze
climates.
This evaluation has identified several significant problems that
will limit the results that can be obtained from the SPS-2.
Specifically, SPS-2 project sites are missing for certain
subgrade-climate combinations. Some SPS-2 sites had construction
deviations. Significant materials data and traffic data are missing
from some sites or sections. The missing traffic data and key
materials data must be obtained or forecasted before meaningful
global analysis can be performed. The Nevada site has excessive
early cracking that will limit its usefulness.
However, these problems do not mean that many important and
useful findings and results cannot be obtained from SPS-2
experiments. Some interesting and important early trends have
already been identified that will be useful in the design and
construction of JPCP, even though the sections are only a maximum
of 7.5 years old. As time and traffic loadings accumulate on the
SPS-2 sites, additional valuable performance data will be
obtained.
Because of FHWA's intense ongoing effort to obtain missing data
(construction, materials, traffic, and monitoring), valuable
results can be obtained from the SPS-2 sites. It is further
believed that even more results can be obtained if a concerted
effort is made to perform proper analyses of the data.
Recommendations for the SPS-2
Experiment
Missing SPS-2 Sites. To complete all the SPS-2
factorial cells, construction of the following sites is
recommended:
- Two sites are needed to complete the factorial in the dry
no-freeze climate: one site with a fine-grained subgrade, and the
other site with a coarse-grained subgrade (i.e., Arizona,
California in the southwest United States).
- Two sites are needed to complete the factorial and match sites
in the wet no-freeze climate with a coarse-grained subgrade
(southeast United States).
- One site is needed to complete the factorial and match a dry
freeze climate with a fine-grained subgrade (north central United
States).
Missing SPS-2 Data. Significant effort is
recommended to obtain the following missing data:
- Materials-PCC strength.
- Traffic-5 sites completely missing traffic data, 11 sites
missing continuous WIM data.
- Faulting-collect faulting data from several SPS-2 sites
immediately.
Expectations from SPS-2. The overall objective
is for the SPS-2 project's results to provide SHAs with documented
findings to help them improve their management, design,
construction, and materials procedures related to JPCP. The
following specific information is expected to be gained from the
SPS-2 project:
Specific design, subgrade, climate, and traffic
effects
- Effect of subdrainage on performance (faulting, transverse
cracking, longitudinal cracking, IRI).
- Effect of widened slab on performance (faulting, transverse
cracking, longitudinal cracking, IRI).
- Effect of base type (lean concrete, permeable asphalt, dense
aggregate) on performance (faulting, transverse cracking,
longitudinal cracking, IRI).
- Effect of concrete slab thickness on performance (faulting,
transverse cracking, longitudinal cracking, IRI).
- Effect of 14-day concrete strength on performance (faulting,
transverse cracking, longitudinal cracking, IRI).
- Effect of climatic region on performance (precipitation,
temperature).
- Effect of subgrade soil on performance (fine-grained,
coarse-grained).
- Interactive effect of subdrainage, widened slab, base type,
slab thickness, concrete strength, climatic region, and subgrade
soil on performance.
- Effect of traffic loading on performance of various design
treatments.
Data for use in calibration of mechanistic-empirical
distress models
- 2002 Design Guide distress models.
- Subsequent improvement in future versions of the guide over
time.
Data for use in empirical performance modeling (for
pavement management)
Data for use in a variety of mechanistic modeling
(backcalculation, structural analysis)
Data for use in a variety of cost/benefit
analyses
- SPS-2 performance data are ideally suited for use in cost and
benefit studies to determine the relative cost-effectiveness of
each design feature in various climates and subgrades.
Future Data Collection. It is recommended that
the following areas receive special emphasis in SPS-2 data
collection:
- Routine data collection.
- WIM and AVC traffic monitoring: ensure that LTPP guidelines are
followed.
- Joint faulting: follow LTPP guidelines closely.
- Resolve irregular distress measurements over time for each
SPS-2 section (variations of distress quantities over time).
- Thermal coefficient of expansion of concrete: ensure that all
SPS-2 sites are tested in 2000.
- Collect new data required for 2002 Design Guide
calibration.
- Slab curvature measurements: measure slab curvature when the
thermal gradients are zero. Measure this during two seasons of
year, wet and dry.
- Conduct video surveys of edge drains to ensure they are
working, and schedule maintenance if needed.
- Cores along the cracks in JPCP to determine the initiation of
the crack and the direction of its propagation. In other words,
where did the crack initiate: top-down or bottom-up?
Recommended Future Analyses for
SPS-2 Experiment
As stated previously, a very small percentage of the SPS-2 test
sections currently have significant levels of distress, and only a
few have been taken out service. The real benefit from this
experiment will occur over the next 15 years, as more and more test
sections exhibit higher levels of distress, magnifying the effect
of the experimental and other structural factors on
performance.
This report focuses on the quality and completeness of the SPS-2
construction and monitoring data and on the adequacy of the
experiment to achieve the original expectations and objectives.
Detailed analysis of the effect of different design factors on
performance was outside the scope of work for this study. Thus,
future studies using the SPS-2 experimental data should be planned
and prioritized so they can be initiated as the SPS-2 projects
exhibit higher levels of distress.
These future studies should be planned for in two stages that
focus on local and national expectations from the experiment. The
first stage is to conduct a detailed assessment or case study on
each experimental cell in the project (companion SPS-2 sites that
define a full factorial experiment) to ensure data adequacy, assess
construction deficiencies, and support local interests and
expectations. The second stage evaluates the effect of different
structural features across the entire national experiment. Both
analysis stages are briefly discussed in the following sections.
After the sections are 15 to 20 years of age, a third-stage
analysis will ultimately be needed to fully reap the benefits of
the SPS-2 experiment.
Initial Stage-Analysis of Individual Factorial Cells
Each major cell in the SPS-2 experiment consists of at least two
companion projects. One of these companion projects contains
experimental sections 1 through 12, and the other contains sections
13 through 24. These companion SPS-2 sites constitute a full
factorial of design factors and make it possible to evaluate the
main effects and interactions of each experimental factor for those
site conditions. A detailed evaluation of the companion projects
within each major cell should be completed as soon as possible to
ensure that all of the data exist and are acceptable. The purposes
of the case studies in the first stage are listed below:
- Resolve construction and monitoring data anomalies and
experimental cell differences for those projects that changed cell
locations from the original experiment design, as they relate to
the specific cell in the experiment.
- Conduct comparative analyses of the individual test sections at
each site, including the supplemental test sections, to
identify differences in pavement performance and response. These
comparative studies should include performance measures, material
properties, and as-built conditions.
- Determine the effect of any construction difficulties and
problems and material noncompliance issues with the SPS-2 project
specifications, if any, on pavement performance and response at
each site.
- Develop findings regarding comparisons made between the
companion projects and test sections and prepare a case study
report that will be useful for the SHAs involved. Such information
will also be useful for the national studies.
This first-stage analysis is considered absolutely essential
prior to initiation of the second-stage analyses.
Second Stage-Analysis of
Experimental Findings
The second-stage analyses should not be pursued until the
first-stage analysis has been completed. It is expected that the
analyses performed at this stage will be coordinated with the
Strategic Plan for LTPP Data Analysis. The SPS-2
experiment can contribute to the following specific analyses
outlined in the strategic plan:
- Develop relationships to enable interchangeable use of
laboratory- and field-derived material parameters (Strategic Plan
No. 2B).
- Establish procedures for determining as-built material
properties (2C).
- Identify quantitative information on the performance impact of
different levels of material variability and quality (2D).
- Estimate material design parameters from other materials data
(2E).
- Quantify information as to the relationship between as-designed
and as-built material characteristics (2F).
- Develop recommendations for climatic data collection to
adequately predict pavement performance (3D).
- Develop models relating functional and structural performance
(4C).
- Calibrate relationships (transfer functions) between pavement
response and individual distress types (5C).
- Identify quantitative information on the impact of design
features on measured pavement responses (deflections,
load-transfer, strains, etc.) (7A).
- Identify quantitative information on the impact of design
features on pavement distress (7B).
- Develop guidelines for the selection of pavement design
features (7C).
In summary, the following future analysis objectives are
recommended for the SPS-2 experiment. These analysis topics are
discussed in more detail in figures 25 through 31.
- Perform site-by-site analyses of SPS-2 projects to resolve data
problems and gain understanding of performance of individual test
sections (figure 25).
- Determine the effect of the SPS-2 experimental factors on the
performance of the jointed plain concrete pavements (figure
26).
- Determine the optimum JPCP design features for specific site
conditions and traffic loading (figure 27).
- Determine the effect of concrete slab thickness variations on
LTPP and initial ride quality (figure 28).
- Calibrate and validate relationships (transfer functions)
between pavement structural response and individual distress types
(figure 29).
- Conduct mechanistic analyses of SPS-2 sites (particularly Ohio
and North Carolina) to gain knowledge of critical stresses and
deflections to explain their performance in terms of joint faulting
and slab transverse and longitudinal cracking (figure 30).
- Conduct cost-benefit analyses of SPS-2 data to determine the
cost-effectiveness of various design features (figure 31).
The full results from the SPS-2 experiment will require 20 years
of monitoring for the majority of sections. Additional studies
beyond these proposed will be required.
Figure 25. Recommended future analyses for
SPS-2-Site-by-site analyses of SPS-2 projects to gain understanding
of performance of individual test sections (initial
stage).
Objective no. 1
Perform site-by-site analyses of SPS-2 projects to gain
understanding of performance of individual test sections. (Initial
stage, expected timeframe 2001 to 2002) |
TOPIC AREA Pavement design. |
PROBABILITY OF
SUCCESS High. |
LTPP STRATEGIC PLAN 7A, 7B, and
7C.
(Study of the Experimental Factors) |
SUPPLEMENTAL
XPERIMENTS None. |
END PRODUCT
- Identification of test sections that perform well and poorly at
each SPS-2 site, including supplementals.
- Determination of the effect of any construction difficulties
and material noncompliance issues on pavement performance and
response.
|
POTENTIAL PRODUCT
USE Design of new or reconstructed cost
effective and reliable jointed plain concrete pavements. |
GENERAL TASKS
- Conduct evaluation of permeable base and edge drains and
outlets to determine their proper construction performance, and
maintenance.
- Resolve construction and monitoring data anomalies and
experimental cell differences for those projects that changed cell
locations from the original experiment design, as they relate to
the specific cell in the experiment.
- Conduct comparative analyses of the individual test sections at
each site, including the supplemental test sections, to
identify differences in pavement performance and response.
- Determine the effect of any construction difficulties,
problems, and material noncompliance issues with the SPS-2 project
specifications, if any, on pavement performance and response.
- Develop findings regarding comparisons made between
the companion projects and test sections and prepare a case study
report that will be useful for the State highway agencies involved
and also will be useful for the national studies.
|
Figure 26. Recommended future analyses for SPS-2
experiment-study of the effect of the experimental factors on rigid
pavement performance.
Objective no. 2
Determine the effect of the SPS-2 experimental factors on the
performance of the jointed plain concrete pavements. (Expected
timeframe 2003 to 2006) |
TOPIC AREA Pavement design. |
PROBABILITY OF
SUCCESS High (assuming that subdrainage was
evaluated in Objective No. 1). |
LTPP STRATEGIC PLAN 7A, 7B, and
7C. |
SUPPLEMENTAL
EXPERIMENTS None. |
END PRODUCT
- Effect of a permeable base drainage system on the performance
of the jointed plain concrete pavements.
- Effect of different base types on the performance of the
jointed plain concrete pavements.
- Effect of widened lane on the performance of the jointed plain
concrete pavements.
- Identification of site conditions where thicker concrete slab
will and will not contribute to improved performance.
- Effect of thicker slabs on the performance of the jointed plain
concrete pavements.
- Effect of higher strength concrete on the performance of the
jointed plain concrete pavements.
- Identification of site conditions where these design features
will contribute to improved performance of the jointed plain
concrete pavements.
|
POTENTIAL PRODUCT
USE Design of new or reconstructed cost
effective and reliable jointed plain concrete pavements. |
GENERAL TASKS
- Review results and findings from each SPS-2 site.
- Conduct statistical analysis to determine significant factors
and interactions on performance.
- Conduct mechanistic-empirical analyses for cracking, joint
faulting, and IRI.
- Based on statistical and mechanistic analyses, determine the
effect of different experimental factors or design features and
interaction on pavement performance and response.
- Prepare practical presentations of the results, including
software, decision trees, etc., for use by practicing engineers,
that aid them in determining the end products above.
|
Figure 27. Recommended future analyses for SPS-2
experiment-determination of the optimum pavement design
features.
Objective no. 3
Determine the optimum design features for specific site conditions
and traffic loading for JPCP. (Expected timeframe 2003 to
2005) |
TOPIC AREA Pavement design. |
PROBABILITY OF
SUCCESS High. |
LTPP STRATEGIC PLAN 7A, 7B, and
7C.
(Study of the Experimental Factors) |
SUPPLEMENTAL
EXPERIMENTS GPS-3 and SPS-8. |
END PRODUCT A guideline,
catalog, or a design tool for selecting optimum combinations of
design features for specific site conditions and traffic
level. |
POTENTIAL PRODUCT
USE Design new cost effective and reliable
jointed plain concrete pavements. |
GENERAL TASKS
- Review results from each SPS-2 site.
- Conduct statistical analyses to determine significant factors
and interactions.
- Conduct mechanistic-empirical analyses for transverse cracking,
joint faulting, and IRI for JPCP.
- Obtain representative construction cost data for all needed
features of JPCP over selected regions that include an SPS-2
experiment.
- Based on statistical and mechanistic analyses, identify the
optimum combination of pavement design features to be used for
various site conditions to provide cost effective and reliable
JPCP.
- Prepare practical presentations of the results, including
software, guidelines, catalogs, and other tools that aids
practicing engineers in determining the end products above.
|
Figure 28. Recommended future analyses for SPS-2
experiment-quantify the relationships between as-designed and
as-built concrete slab thickness and strength.
Objective no. 4
Determine the effect of concrete slab thickness variations on
long-term pavement performance and initial ride quality. (Expected
timeframe 2005 to 2007) |
TOPIC AREA Pavement design and
construction. |
PROBABILITY OF
SUCCESS High. |
LTPP STRATEGIC PLAN 2C and
2F. |
SUPPLEMENTAL
EXPERIMENTS GPS-3 and SPS-8. |
END PRODUCT A relationship
between increased thickness variations and reduced pavement service
life or reduced initial ride quality. |
POTENTIAL PRODUCT
USE
Develop pay reduction factors based on concrete slab thickness
variation. |
GENERAL TASKS
- Review results from each SPS-2 site.
- Establish the variation in the concrete slab thickness for each
of the SPS-2 test sections.
- Conduct statistical analyses to determine the effect of the
slab thickness variation on pavement performance and response.
- Develop reductions in service life based on these increased
variations in concrete slab thickness.
|
Figure 29. Recommended future analyses for SPS-2
experiment-calibration and validation of the pavement transfer
functions.
Objective no. 5
Calibrate and validate relationships (transfer functions) between
pavement response and individual distress types. (Expected
timeframe 2005 to 2007) |
TOPIC AREA Pavement design. |
PROBABILITY OF
SUCCESS High. |
LTPP STRATEGIC PLAN 7A, 7B, and
7C. |
SUPPLEMENTAL
EXPERIMENTS
GPS-3 and SPS-8. |
END PRODUCT A calibrated and/or
validated relationship between pavement structural responses
(stress) and individual distresses. |
POTENTIAL PRODUCT
USE Design of new cost effective and reliable
jointed concrete pavements (would contribute to upgrading of
2002 Design Guide). |
GENERAL TASKS
- Establish a comprehensive input database that includes design,
construction, materials testing, traffic, climatic, and monitoring
data, for the response model.
- Perform mechanistic analysis to determine the critical response
stress and cumulative fatigue damage for the traffic loading
applied until the time of the distress measurement (utilize the
relationships in the 2002 Design Guide as well as
others).
- Establish the relationships between the cumulative fatigue
damage and the measured distress.
- Perform model assessment and develop calibration
coefficients.
|
Figure 30. Recommended future analyses for SPS-2
experiment-mechanistic analyses of JPCP.
Objective no. 6
Conduct mechanistic analyses of SPS-2 sites (particularly Ohio and
North Carolina) to gain knowledge of critical stresses and
deflections to explain their performance in terms of joint faulting
and slab transverse and longitudinal cracking. (Expected time frame
2005 to 2007) |
TOPIC AREA Pavement design and
construction. |
PROBABILITY OF
SUCCESS Moderate to high. |
LTPP STRATEGIC PLAN 2D and
7B. |
SUPPLEMENTAL
EXPERIMENTS None. |
END PRODUCT In-depth,
field-verified knowledge as to the effects of critical measured
structural responses and curling that will be useful in pavement
design, evaluation, and rehabilitation. |
POTENTIAL PRODUCT
USE Knowledge gained from this experiment will
be useful to researchers and others for improving design procedures
to make JPCP a more cost effective and reliable pavement (upgrade
2002 Design Guide). |
GENERAL TASKS
- Establish a comprehensive input database that includes design,
construction, materials testing, traffic, climatic, monitoring
data, and structural monitoring data (deflections, strains,
stresses, others).
- Analyze slab curling at all sites using longitudinal profile
data or other slab curling measurements available (Note: if
insufficient data are available, measure curling at several sites
in different climates).
- Perform mechanistic analysis to determine the critical response
stress and cumulative fatigue damage for the traffic loading and
slab curling.
- Analyze results and develop findings and recommendations as to
impacts of loading and curling on JPCP performance (cracking and
faulting).
|
Figure 31. Recommended future analyses for SPS-2
experiment-cost/benefit analyses of JPCP.
Objective no. 7
Conduct cost/benefit analyses of SPS-2 sites to gain knowledge of
the cost-effectiveness of design features in different site
conditions. (Expected timeframe 2005 to 2007) |
TOPIC AREA Pavement design and
construction. |
PROBABILITY OF
SUCCESS High. |
LTPP STRATEGIC PLAN 7B and
7C. |
SUPPLEMENTAL
EXPERIMENTS None |
END PRODUCT In-depth,
field-verified knowledge as to the cost-effectiveness of key design
features including slab thickness, widened slab, base type,
concrete strength, and a permeable base layer. |
POTENTIAL PRODUCT
USE Knowledge gained from this experiment will
be directly useful to pavement designers in improving the
cost-effectiveness of their designs. |
GENERAL TASKS
- Establish a comprehensive input database that includes design,
construction, materials testing, traffic, climatic, and monitoring
data.
- Establish typical costs of various design features from the
State highway agencies in the States where SPS-2 sites are
located.
- Analyze results and develop findings and recommendations as to
the cost-effectiveness of each design feature in each of the main
climatic zones covered by the SPS-2 experiment.
|
|