Rehabilitation of Jointed Portland Cement Concrete Pavements:
SPS-6, Initial Evaluation and Analysis
Chapter 8. SUMMARY, CONCLUSIONS, AND RECOMMENDATIONS
The SPS-6 experiment, Rehabilitation of Jointed Portland Cement
Concrete Pavements, is one of the key experiments in the LTPP
program. The main objective of this experiment is to determine the
effectiveness of different rehabilitation techniques and strategies
and their contributions to pavement performance and service life.
There are some concerns about the ability of the SPS-6 experiment
to meet expectations, given that several SPS-6 sites were not
constructed. In addition, some construction deviations and data
collection deficiencies exist for the SPS-6 sites that were
constructed.
This study presents the first comprehensive evaluation of the
SPS-6 experiment. First, this chapter summarizes the experiment
site factors, data availability, and data completeness for the
SPS-6 experiment. Next, this chapter provides a convenient summary
of the conclusions drawn from the early performance trends
identified in this report. This is followed by a brief summary of
some of the States' expectations for the SPS-6 experiment. Finally,
this chapter provides the research team's recommendations for
improving the SPS-6 experiment, its data availability, expectations
for the SPS-6 experiment, and future data collection and analysis
topics.
SUMMARY
A summary of experiment site factors and data availability and
completeness is provided below:
SPS-6 Experiment Site Factors Summary
Fourteen SPS-6 sites have been constructed throughout the United
States. Each SPS-6 site was selected to fulfill a portion of the
original SPS-6 design factorial. Once these sections were
constructed, a review of the climatic data resulted in several
sites being reclassified in the wet-freeze zone (as shown in table
81). This reclassification completes the wet-freeze design
factorial. This will allow a complete analysis of the wet-freeze
climatic areas, which encompass a large geographic region of the
United States. Unfortunately, many sites are now missing from the
wet-no freeze, dry-freeze, and dry-no freeze zones. Thus, there is
excellent coverage in the wet-freeze climatic zones for both JPCP
and JRCP, and excellent coverage for JPCP in wet-no freeze climatic
zones. Unfortunately, there is no coverage for either JPCP or JRCP
in dry climatic zones. Note that this will only be important if
increased precipitation significantly affects the performance of
rehabilitated JRCP and JPCP.
It is also important to consider the variations in the design
properties associated with each experiment section and variations
in the monitoring interval from that designated by the SPS-6
experimental plan. All of these deviations from the requirements of
the SPS-6 experimental plan must be considered during all future
analytical efforts.
Table 81. As-built sites as placed in original
experimental design factorial.
|
|
Wet |
Dry |
|
|
Freeze |
No Freeze |
Freeze |
No Freeze |
JPCP |
Fair |
MO(A),
SD,TN |
AL , * |
** |
* |
Poor |
AZ ,IN |
AR, CA |
** |
* |
JRCP |
Fair |
IA, MI,
OK, PA |
** |
* |
|
Poor |
IL, MO |
** |
* |
|
Notes:
- Each * indicates that an additional site is needed to complete
the original design matrix.
- Bolded sections were originally in another
cell of the design matrix.
- Italicized sections indicate that the site did not
meet the minimum traffic requirements.
- MO(A) is the second SPS-6 site constructed in Missouri; the
first site is designated as MO.
Data Availability and Completeness Summary
Data availability and completeness for the SPS-6 experiment are
good overall. A high percentage of the SPS-6 data are at level E;
however, a significant amount of data was not available at the time
of analysis, especially traffic, distress surveys, and key
materials testing data. These deficiencies need to be addressed
before serious analysis of the SPS-6 experiment can occur. This
includes:
- Data that were not available at the time of the study and are
required by the LTPP data collection guidelines (unavailable
data).
- Data elements that are important to future research, but are
not required by the LTPP data collection guidelines for SPS-6
(missing data elements).
Unavailable Data
This section summarizes the data that were unavailable at the
time of the study and are required by LTPP data collection
guidelines. It should be stressed that there are numerous reasons
why some important data may not be available from the publicly
released IMS database at the time of analysis. The following are
some possible examples:
- Data are yet to be collected or the laboratory tests have not
yet been performed.
- Data are under regional review.
- Data have failed one of the quality checks and are being
reviewed.
- Data have failed one of the quality checks and were identified
as anomalies.
- Data need to be quality checked.
As such, the unavailable data identified in this section do not
necessarily mean that the data were not collected or submitted by
the States. There are several instances where data may get held up
and not reach level E. Note that the results reported in this
section are based on level E data only. The LTPP program is
embarking on a systemwide effort to resolve all unavailable data so
that they will be available to future researchers. Some data have
already been located during the course of this study.
Table 82 summarizes data availability and completeness by some
of the key data types, while table 83 summarizes data availability
and completeness for the key data types that are to be monitored
over the long term. Note that any rating of "Fair" or "Poor" means
that these sites would not meet analytical needs and, therefore,
must be improved as soon as possible. The SPS-6 data deficiencies
are summarized below:
- Alabama and Missouri (A): Sites are newly constructed and data
processing is underway.
- Indiana: Design thicknesses are in the database in place of the
as-constructed thicknesses.
- Traffic data are deficient or there are negative ESAL values
for 6 of 14 sites (40 percent).
- All States (except Arizona) need to conduct some of the
materials testing.
- Some of the monitoring data from immediately before and after
construction were not collected or are not yet available in the
database.
- Most of the long-term monitoring data are at level E.
Table 82. Summary of SPS-6 data availability and
completeness for key datatypes.
Type of Data |
SPS-6 Core Sections (Total: 14 Sites,
112 Sections) |
SPS-6 Supplemental Sections (Total: 59
Sections) |
Number of Sites (Sections) |
% at Level E |
Comments |
w/Data |
Missing Data |
Site Information (Reports, location, and
significant dates data) |
10 to 14 sites |
AL, MO, MO(A), TN (Construction dates) |
100% |
Excellent |
Excellent (Same as the core sections) |
Pavement Structure (Subgrade layer, base, and
surface) |
10 to 14 sites |
AL, AR, IN*, MO(A) |
61-91% |
Good |
Good (Available for 50 to 59 sections) |
Climatic Data |
11sites |
AL, CA, MO(A) |
100% |
Good |
Good (Same as core sections) |
Traffic |
11 sites |
AL, AR, MO(A), TN |
40-100% |
Good |
Good (Same as core sections) |
Key AC and PCC Materials Testing |
11 sites |
All but AZ |
70-100% |
Good-Fair |
Not evaluated |
*For Indiana, design values were used as actual pavement layer
thicknesses.
Table 83. Summary of SPS-6 data availability and
completeness assessment for monitoring data.
Monitoring Data Types |
SPS-6 Sites and Core Sections (Total:
14 Sites, 112 Sections) |
Comments |
Initial Survey Immediately Before
Rehab. |
Initial Survey Immediately After
Rehab. |
Long Term Maximum < 3 years |
Yes |
No |
Yes |
No |
Yes |
No |
No Data |
% at Level E |
Longitudinal Profile |
11 |
AL, IL, IA |
12 |
AL, SD |
13 |
AL |
MO(A) |
95% |
Good |
Deflection |
9 |
AL, CA,IL, IN, TN |
10 |
AL, MI, PA, SD |
13 |
AL |
MO(A) |
94% |
Good |
Faulting |
|
|
|
|
13 |
AL, AR, TN |
MO(A) |
84% |
Fair |
Distress: Manual and PASCO |
8 |
CA, IA, OK, PA, SD, TN |
11 |
IL, MI, PA |
9 |
AL, AZ, AR, IA, TN |
MO(A) |
84-99% |
Fair |
Detailed data availability and completeness assessments are
provided in the following sections for traffic, materials, and
monitoring data.
Traffic Data
The SPS-6 experimental design calls for traffic data to be
collected using a combination of permanent and portable equipment
by the individual States. Table TRF_MONITOR_BASIC_INFO was examined
to identify SPS-6 records with annual ESAL estimates. As discussed
in this report, Alabama, Arkansas, Missouri (A), and Tennessee do
not have any traffic data in the IMS database. Because these
sections are relatively new to the program, they probably have
traffic information. However, as of August 1999, information had
not yet been entered into the database. The remaining sites have 1
to 9 years of traffic data available, depending on the age of the
site. In addition, Arizona and California have negative ESAL values
for most of the AC-overlaid sections and, therefore, have a
non-level E record status. Reportedly, these values have been
corrected since these data were originally extracted from the IMS
database.
Materials Testing Data
Data availability and completeness assessment results for the
key AC and PCC materials testing tables show that none of the
materials tests meets the required number of tests initially
established by the LTPP program. It is important to point out that,
even though all of the materials tests have not been conducted,
many States have conducted some of these tests. In addition, many
States are looking into and addressing their materials testing
deficiencies. As of the time of this report, very little materials
testing data were available for the sites in Alabama, Arkansas, and
Missouri (A) because of the relatively young ages of these sites.
In addition, California, Indiana, and South Dakota had very little
materials testing data available when this report was prepared. The
remaining eight sites have completed a significant portion of the
materials testing results. Arizona has the most complete set of
materials testing results in the IMS database based on the data
extracted from the IMS database for this report.
Monitoring Data
Seven types of monitoring data are included in the LTPP IMS: (1)
automated distress, (2) manual distress, (3) friction, (4)
longitudinal profile, (5) cross profile, (6) deflection, and (7)
dynamic load response. Using the minimum requirements for the
collection of monitoring data noted in these tables, an assessment
of data availability and completeness follows:
- Long-term monitoring data were not yet releasable at the time
of this data analysis for Alabama, Arkansas, Missouri (A), and
Tennessee.
- Longitudinal profile data are acceptable for most sites.
Long-term monitoring was typically conducted at an interval
averaging less than 3 years.
- Deflection data are complete, with a long-term monitoring
interval averaging 3 years or less.
- Faulting data are, on average, at an interval of 3 years or
less.
- Rutting data are, on average, at an interval of 2 years or
less.
- Combined distress data result in periodic surveys within an
average interval of 2 years, except for Arizona, which is at an
interval of 2.4 years.
- Friction testing was not available for nine sites. However,
sites with friction data have a relatively good monitoring period
that averages 3 years or less.
Missing Data Elements
The following data elements or information were not included in
the SPS-6 data collection plan; however, they will probably be
needed for future analyses of the data. These data elements or
activities are recommended for future data collection activities
for the SPS-6 experiment:
- Measure the dynamic modulus in uniaxial compression over a
temperature range for hot mix asphalt (HMA) mixtures.
- Measure the performance grade of the asphalt that was used in
the HMA layers and measure the aging that has occurred since
construction.
- Measure the indirect tensile strain at failure in accordance
with the method identified in National Cooperative Highway Research
Program (NCHRP) Report 338. This value can be easily measured
during the indirect tensile strength test.
CONCLUSIONS
Conclusions drawn from the early performance trends identified
in this report are provided below.
Early Performance Trends Summary
Note that these performance trends represent early findings and
that these results may be altered once all of the data have been
collected and a more thorough investigation has been conducted in
the future. This includes detailed analysis of every SPS-6 site.
Tables 84 through 87 show the preliminary performance trends for
each general type of rehabilitation treatment applied.
Table 84. Summary of roughness performance.
Section |
Rehabilitation Alternative |
Initial Roughness |
Change in IRI Over Time |
***601 |
Control |
High |
High |
***602 |
Minimum preparation (w/o diamond grinding) |
High |
High |
***605 |
Maximum preparation (w/diamond grinding) |
Low |
High |
***603 |
Minimum preparation with 102-mm (4-inch) AC overlay |
Low |
Moderate |
***604 |
Same as ***603 with sawed and sealed joints |
Low |
Moderate |
***606 |
Maximum preparation with 102-mm (4-inch) AC overlay |
Low |
Moderate |
***607 |
Crack and seat with 102-mm (4-inch)AC overlay |
Low |
Low to Moderate |
***608 |
Crack and seat with 203-mm (8-inch)AC overlay |
Low |
Low |
Table 85. Summary of distress performance trends for bare
PCC pavement.
Section |
Rehabilitation Alternative |
Transverse Cracking |
Faulting |
Initial Effect of Rehabilitation |
Change Over Time |
Initial Effect of Rehabilitation |
Change Over Time |
***601 |
Control |
Unchanged |
Least |
Unchanged |
Little change |
***602 |
Minimum preparation |
Reduced |
Similar to ***605 |
Reduced |
More |
***605 |
Maximum preparation |
Reduced |
Similar to ***602 |
Reduced |
More |
Table 86. Summary of reflection cracking performance for
ACoverlays on nonfractured PCC.
Section |
Rehabilitation Alternative |
Initial Effect of Rehabilitation |
Change Over Time |
***603 |
Minimum preparation with 102-mm (4-inch) AC overlay |
None |
Slightly more than ***606 |
***604 |
Same as ***603 with sawed and sealed joints |
N/A |
N/A |
***606 |
Maximum preparation with 102-mm (4-inch) AC overlay |
None |
Little change |
N/A: Surveys for section ***604 are not sufficient to identify
preliminary trends
Table 87. Summary of distress performance trends for AC
overlays on fractured PCC pavement.
Section |
Rehabilitation Alternative |
Transverse Cracking |
Faulting |
Initial Effect of Rehabilitation |
Change Over Time |
Initial Effect of Rehabilitation |
Change Over Time |
***607 |
Crack and seat with 102-mm (4-inch) AC overlay |
None |
Similar to ***608 |
None |
Similar to ***608 |
***608 |
Crack and seat with 203-mm (8-inch) AC overlay |
None |
Similar to ***607 |
None |
Similar to ***607 |
N/A: Surveys for section ***604 are not sufficient to identify
preliminary trends.
Bare PCC Pavements
Roughness
- Control sections (maintenance only) and minimum-preparation
sections (without diamond grinding) exhibit the roughest pavements.
Even those sections having the maximum preparation, but no diamond
grinding exhibited considerable roughness or IRI. Thus, if the
pre-rehabilitated section has significant roughness, diamond
grinding should be thoroughly considered or the section will retain
its roughness. By themselves, full-depth repairs did not remove
significant roughness from JRCP or JPCP.
- Maximum preparation with diamond grinding resulted in initially
smooth pavements (initial IRI about 1.0 m/km (63.36 inches/mi))
that were similar to AC overlays. The IRI of these sections did
increase over time (more so than for the AC overlays), probably
because of more joint and crack faulting in some sections.
Transverse Cracking
- Both minimum- and maximum-rehabilitation treatments reduce the
amount of transverse cracking immediately after rehabilitation
because of full-depth repairs and slab replacements.
- The rate of increase in transverse cracking is somewhat less
for the control section. The minimum-preparation section (***602)
has a higher rate of increase in transverse cracking, while the
maximum-preparation section (***605) has the highest rate. The
cause of these trends needs to be explored on a site-by-site
basis.
Faulting
- The control section had the least change in joint faulting over
time. This can be explained by the fact that all of the slabs
within this section have reached equilibrium and have reduced
movement.
- Maximum-preparation rehabilitation with diamond grinding
reduces the amount of faulting to zero immediately after
rehabilitation.
- Minimum- and maximum-preparation sections had a higher rate of
increase in faulting over time than the control section. This may
be partially caused by the fact that most of these sections were
diamond ground, giving a zero faulting, and then a more rapid
increase followed over time at both the regular joints and the
joints of the new full-depth repairs.
- Faulting of the maximum-preparation sections is projected to
equal that of the control sections after about 12 years, on
average.
- The major advantage of maximum preparation over minimum
preparation in the early analysis appears to be the smoothness
resulting from diamond grinding.
AC Overlay of Nonfractured PCC
Roughness
- AC overlay of nonfractured PCC reduces the roughness
immediately after rehabilitation, typically to a smooth level (1
m/km (63.36 inches/mi)).
- These sections are experiencing a faster increase in IRI over
time than the AC overlay of fractured PCC.
- These sections are experiencing a lower increase in IRI over
time than the maximum preparation PCC sections.
- The amount of preparation (minimum or maximum) did not yet
appear to have a significant effect on the IRI of AC nonfractured
JRCP or JPCP. This may change as the pavements age.
Reflection Cracking
- Neither the minimum- nor maximum-preparation sections with
102-mm (4-inch) AC overlays had any reflection cracking within the
first year after construction.
- Reflective cracking survey information for the
minimum-preparation sections with a 102-mm (4-inch) AC overlay with
sawed and sealed joints (***604) appears to be inconsistent from
survey date to survey date. It is recommended that these
inconsistencies be addressed before this rehabilitation alternative
is further evaluated.
- Maximum-preparation sections had very little change or increase
in reflection cracking, while minimum-preparation sections had a
slightly higher increase in reflection cracking over time.
AC Overlay of Fractured PCC
Roughness
- AC overlay of fractured PCC had a low IRI immediately after
rehabilitation (typically 1.0 m/km (63.36 inches/mi)).
- This rehabilitation had the lowest rate of increase in IRI
after rehabilitation than any of the other rehabilitation
alternatives.
Fatigue Cracking
- Both crack/break and seat rehabilitation techniques with 102-mm
(4-inch) and 203-mm (8- inch) AC overlay show low amounts of
fatigue cracking over time.
Transverse Cracking
- As these pavement sections continue to age, a direct comparison
should be made between the transverse (reflection) cracking
occurring for the nonfractured PCC rehabilitation and that found
for the fractured PCC rehabilitation. This should be done,
site-by-site, for each SPS-6 experiment to obtain the maximum
trends and findings for each rehabilitation alternative.
STATE EXPECTATIONS
One national workshop was held recently where input was received
from the States on the SPS-6 experiment. The meeting was held on
April 28, 2000, in Newport, RI. The research team made
presentations at the conference on the status of SPS-6 data
collection, data availability, near- and long-term LTPP products,
and the analysis of SPS-6 data. Several participating States made
presentations on the status and analyses of their SPS-6 projects
and their expectations for the SPS-6 experiment. There were many
discussions on future directions for the SPS-6 experiment and
analyses of the data.
In general, the States are satisfied with the SPS-6 experiment
and fully expect to get valuable information about the different
rehabilitation features included in the SPS-6 experiment. Many
States have been conducting and are planning their own analyses on
their SPS-6 projects. Some of these analyses have already yielded
useful results. The States would like to see a focus on
implementation of SPS-6 findings as they evolve over time.
First and foremost, what the States want from the SPS-6
experiment are the effects on pavement performance and the
cost-effectiveness of the experimental design factor features, such
as:
- Condition of existing pre-rehabilitated jointed plain
concrete.
- Pre-restoration effectiveness.
- Pre-overlay effectiveness.
- AC overlay thickness.
- Fractured versus nonfractured influence.
- Diamond grinding effectiveness.
- Edge drain effectiveness.
In addition to the structural design features, the States also
want to know which major site condition factors influence the
performance of rehabilitated concrete pavement, including:
- Climate.
- Traffic volume.
- Traffic loading.
Other specific expectations from the States include:
- Maximum years of service life for rehabilitated pavements.
- Next-best alternative.
- Dollar design.
- Standard solutions for a given pavement condition.
- Best rehabilitation methods for minimizing reflection
cracking.
- State-specific findings.
As for future analytical plans for the SPS-6 experiment, the
States believe that it is worthwhile to first fill in the missing
data (backcasting, if necessary, to obtain traffic and materials
data). It is believed that many fundamental studies can be
conducted to see how SPS-6 sections are responding to loading and
environmental stresses. It was also suggested that an integrated
analytical plan is needed for future research.
This evaluation has shown that several significant problems will
limit the results that can be obtained from the SPS-6 experiment.
Specifically, the SPS-6 projects have construction and
rehabilitation deviations. In addition, significant materials and
traffic data are missing from some sites or sections. The missing
traffic data and key materials data must be obtained or forecasted
before meaningful global analysis can be performed.
However, this does not mean that many important and useful
findings and results cannot be obtained from the SPS-6 experiment.
Some interesting and important early trends have already been
identified that will be useful for the rehabilitation of jointed
plain concrete, even though the sections are less than 10 years
old. As time and traffic loadings accumulate on the SPS-6 sites,
much more valuable performance data will be obtained.
Because of FHWA's intense ongoing effort to obtain missing data
(construction, materials, traffic, and monitoring), valuable
results can be obtained from the SPS-6 sites. It is further
believed that even more results can be obtained if a concerted
effort is made to perform proper analyses of the data.
RECOMMENDATIONS
Finally, this chapter provides the research team's
recommendations for improving the SPS-6 experiment, data
availability, expectations for the SPS-6 experiment, and future
data collection and analysis topics as follows.
Missing SPS-6 Experiments
It is recommended that the following sites be constructed:
- Construct additional sites in dry climatic regions (assuming
that States such as Arizona and California agree) so that the
findings can be extended to these regions. There are currently no
SPS-6 sites within a dry climatic region. Precipitation and
temperature are known to affect diamond-ground joints and may
affect HMA overlays over conventional and cracked and seated
pavements as well.
Missing SPS-6 Data
Significant efforts should be put forth to obtain the following
missing data:
- Materials: Extensive data are currently missing. It is
important that these data be obtained and moved to level E in the
database or the evaluation of various rehabilitation treatments
will be hampered.
- Traffic: Data at level E are limited or missing for a large
number of sites.
- Pavement structure data (primarily thickness): Data at level E
are limited or missing for about 25 percent of the sites.
- Monitoring: Data are very limited at four sites; joint faulting
is limited. Pre- and post-rehabilitation testing are missing for
most sections.
Expectations From SPS-6 Experiments
The overall objective is for SPS-6 performance results to
provide the SHAs with documented findings to help them improve
their management, design, construction, and materials procedures
for the rehabilitation of jointed concrete pavements. The following
specific expectations for the SPS-6experiments are recommended:
Effects of Specific Design, Climate, and
Traffic
- Effects of level of pre-restoration preparation for bare JPCP
and JRCP on performance (faulting, transverse cracking, joint
spalling, IRI).
- Effects of level of pre-HMA overlay preparation on performance
(rutting, reflection/transverse cracking, IRI).
- Effects of HMA-overlaid sawed and sealed joints on performance
(reflection/transverse cracking, IRI).
- Effects of cracking and seating of JRCP and JPCP prior to HMA
overlay on performance (rutting, reflection/transverse cracking,
IRI).
- Effects of HMA overlay thickness over cracked and seated JRCP
and JPCP on performance (rutting, reflection/transverse cracking,
fatigue, longitudinal cracking, IRI).
- Effects of climatic region on the performance of various
rehabilitation treatments (temperature, precipitation).
- Effects of traffic loading on the performance of various
rehabilitation treatments.
Data for Use in Calibration of Mechanistic-Empirical
Distress Models
- 2002 Design Guidedistress models:
- Data for use in empirical performance modeling (for pavement
management).
- Data for use in a variety of mechanistic modeling
(backcalculation, structural analysis, and reflection
cracking).
Data for Use in a Variety of Cost-Benefit
Analyses
Future Data Collection
The following are recommended:
- Routine current data collection:
- Weigh-in-motion (WIM) and automatic vehicle classification
(AVC) traffic monitoring: Ensure that LTPP guidelines are
followed.
- Resolve irregular distress measurements over time for each
SPS-6 section (wild swings of distress quantities over time) and
resolve saw and seal reflection/transverse cracking interpretation
problems.
- Collect new data:
Recommended Future Analyses for SPS-6
Experiment
As stated previously, the SPS-6 test sections are currently
developing initial performance trends. Currently, no long-term
performance trends have been identified and only a few sections
have been taken out of service. The real benefit from this
experiment will occur over the next 10 to 15 years as more and more
test sections exhibit higher levels of distress, magnifying the
effects of the experimental factors on performance.
This report focuses on the quality and completeness of the SPS-6
construction and monitoring data and on the adequacy of the
experiment to achieve the original expectations and objectives.
Detailed analysis of the effects of different rehabilitation
alternatives on performance was outside the scope of this study.
Thus, future studies using the SPS-6 experiment data should be
planned and prioritized so that they can be initiated as the SPS-6
projects exhibit higher levels of distress.
These future studies should be planned in two stages, focusing
on local and national expectations for the experiment. The first
stage is to conduct a detailed assessment or case study on each
experimental cell in the experiment to ensure data adequacy, assess
construction deficiencies, and support local interests and
expectations, while the second stage evaluates the effects of
different rehabilitation alternatives across the entire national
experiment. Both analytical stages are briefly discussed in the
following sections. A third analytical stage will ultimately be
needed after the sections are 10 to 15 years of age to fully reap
the benefits of the SPS-6 experiment.
Initial Stage: Analysis of Local Expectations or
Experimental Factorial Cells
Each major cell in the SPS-6 experiment consists of a duplicated
project. Each SPS-6 site constitutes a full factorial of design
factors and makes it possible to evaluate the performance results
for each experimental factor for those site conditions. A detailed
evaluation of the replicated projects within each major cell should
be completed as soon as possible to ensure that all of the required
data exist and to examine any construction anomalies. The
objectives of the case studies in the first stage are to:
- Resolve construction and monitoring data anomalies and
experimental cell differences for those projects that changed cell
locations from the original experimental design as they relate to
the specific cell in the experiment.
- Conduct comparative analyses of the individual test sections at
each site, including the supplemental test sections, to
identify the differences in pavement performance and response.
These comparative studies should include performance measures,
material properties, and as built conditions.
- Determine the effects of any construction difficulties,
problems, and material noncompliance issues with the SPS-6 project
specifications, if any, on pavement performance and response at
each site.
- Develop findings regarding comparisons made between the
companion projects and test sections and prepare a case study
report that will be useful for the SHAs involved (the report will
also be useful for the national studies).
This first analytical stage is considered absolutely essential
prior to initiation of the second analytical stage.
Second Stage: Analysis of National Expectations or
Experimental Findings
The second analytical stage should not be pursued until the
first analytical stage has been completed. It is expected that the
analyses performed at this stage will be coordinated with the
Strategic Plan for LTPP Data Analysis. The SPS-6 experiment can
contribute to the following specific analyses outlined in the
strategic plan:
- Relationships to enable interchangeable use of laboratory- and
field-derived material parameters (Strategic Plan No. 2B).
- Procedures for determining as-built material properties
(2C).
- Estimation of material design parameters from other materials
data (2E).
- Information as to the relationship between as-designed and
as-built material characteristics (2F).
- Recommendations for climatic data collection to adequately
predict pavement performance (3D).
- Models relating functional and structural performance
(4C).
- Calibrated relationships (transfer functions) between pavement
response and individual distress types (5C).
- Quantitative information on the performance of maintenance and
rehabilitation treatments, including the effect of pretreatment
conditions (6A).
- Guidance on the timing and selection of pavement maintenance
and rehabilitation options, and the expected performance life of
each (6B).
- Quantitative information on the impact of design features on
measured pavement responses (deflections, load transfer, strains,
etc.) (7A).
- Quantitative information on the impact of design features on
pavement distress (7B).
In summary, the following future analytical objectives are
recommended for the SPS-6 experiment. These analytical topics are
discussed in more detail in figures 22 through 26.
- Perform site-by-site analyses of SPS-6 projects to resolve data
problems and the impact of construction anomalies on the
performance of individual test sections (initial stage (figure
22)).
- Determine the effects of the SPS-6 experimental factors on the
performance of the rehabilitation of JPCP and JRCP (figure
23).
- Conduct cost-benefit analyses of SPS-6 site data to determine
the cost-effectiveness of various rehabilitation design features
(figure 24).
- Calibrate and validate relationships (transfer functions)
between pavement structural response and individual distress types
(figure 25).
- Determine the optimum rehabilitation techniques for jointed
concrete pavement design features for specific site conditions and
traffic loading (study of the SPS-6 experimental factors) (figure
26).
The full results from the SPS-6 experiment will require 10 to 15
years of monitoring for the majority of the sections. Additional
studies beyond those proposed will be required.
Figure 22. Recommended future analyses for SPS-6
experiment: Site-by-site analyses of SPS-6 projects to gain
understanding of the performance of individual test sections
(initial stage).
OBJECTIVE NO. 1
Perform site-by-site analyses of SPS-6 projects to gain
understanding of the performance of individual test sections and
the impact of construction anomalies (initial stage, expected
timeframe: 2001-2002). |
TOPIC AREA
Pavement design |
PROBABILITY OF SUCCESS
High |
LTPP STRATEGIC PLAN
7A, 7B, and 7C
(Study of the Experimental Factors) |
SUPPLEMENTAL EXPERIMENTS
General Pavement Studies (GPS)-7 |
END PRODUCT
- Performance review of each test section and identification of
those that perform well and poorly at each SPS-6 site, including
supplemental sections.
- Determination of the effect of any construction anomalies and
material noncompliance issues on pavement performance and
response.
|
POTENTIAL PRODUCT USE
Important knowledge for the SHAs regarding early findings on
rehabilitation and vital information for future analyses of SPS-6
experiments. |
GENERAL TASKS
- Resolve construction and monitoring data anomalies and
experimental cell differences for those projects that changed cell
locations from the original experimental design as they relate to
the specific cell in the experiment.
- Conduct comparative analyses of the individual test sections at
each site, including the supplemental test sections, to
identify the differences in pavement performance and response and
the potential causes.
- Determine the effects of any construction difficulties and
problems and material noncompliance issues with the SPS-6 project
specifications, if any, on pavement performance and response.
- Develop findings regarding comparisons made between the
duplicate projects and test sections and prepare a case study
report that will be useful for the SHAs involved and also for the
national studies.
|
Figure 23. Recommended future analyses for SPS-6
experiment: Study of the effects of experimental factors on the
performance of rehabilitated jointed concrete pavement.
OBJECTIVE NO. 2
Determine the effects of the SPS-6 experimental factors on the
performance of the rehabilitation of jointed concrete pavements
(expected timeframe: 2003 to 2005). |
TOPIC AREA
Pavement design |
PROBABILITY OF SUCCESS
High |
LTPP STRATEGIC PLAN
7A, 7B, and 7C |
SUPPLEMENTAL EXPERIMENTS
GPS-7 |
END PRODUCT
- Effects of site conditions (subgrade, climate, traffic) on the
performance of rehabilitation alternatives, including restoration
without overlay and rehabilitations such as various overlays.
- Effects of jointed concrete pavement design features on the
performance of rehabilitation alternatives, including restoration
without overlay and rehabilitations such as various overlays.
- Effects of minimum and maximum preparation on the performance
of restoration without overlay.
- Effects of minimum and maximum preparation on the performance
of overlays.
- Effects of overlay thickness on the performance of crack and
seat rehabilitations.
- Effects of sawing and sealing of overlays on performance.
- Comparative performance of key supplemental sections (e.g.,
rubblized PCC sections, other reflection crack treatments).
|
POTENTIAL PRODUCT USE
Rehabilitation of jointed concrete pavements in a cost-effective
and reliable manner. |
GENERAL TASKS
- Review results and findings from each SPS-6 site from Objective
No. 1.
- Conduct statistical analysis to determine significant factors
and interactions on performance.
- Conduct mechanistic-empirical analyses for slab cracking, joint
faulting, rutting of overlays, reflection cracking of overlays, and
IRI.
- Based on statistical and mechanistic analyses, determine the
effects of different experimental factors or design features and
their interaction on rehabilitated pavement performance and
response.
- Prepare practical presentations of the results, including
software, decision trees, etc., for use by practicing engineers,
which will aid them in using the knowledge gained from previous
tasks.
|
Figure 24. Recommended future analyses for SPS-6
experiment: Cost-benefit analyses of rehabilitated jointed concrete
pavement.
OBJECTIVE NO. 3
Conduct cost-benefit analyses of SPS-6 sites to gain knowledge of
the cost-effectiveness of design features in different site
conditions for rehabilitated jointed concrete pavements (expected
timeframe: 2005 to 2007). |
TOPIC AREA
Pavement design and construction |
PROBABILITY OF SUCCESS
Moderate to high |
LTPP STRATEGIC PLAN
7B and 7C |
SUPPLEMENTAL EXPERIMENTS
GPS-7 |
END PRODUCT
In-depth field-verified knowledge as to the cost-effectiveness of
key design features, including minimum and maximum preparation, AC
overlay thickness, and cracking and seating of the existing PCC
pavement plus other findings from supplemental sections. |
POTENTIAL PRODUCT USE
Knowledge gained from this experiment will be directly useful to
pavement designers in improving the cost effectiveness of their
designs. |
GENERAL TASKS
- Review all findings from Objective 1 and Objective 2
analyses.
- Establish a comprehensive input database that includes design,
construction, materials testing, traffic, climatic, existing
pavement condition, and monitoring data.
- Establish the typical costs of various rehabilitation
alternatives from the SHAs in the States where SPS-6 experiments
are located.
- Analyze the results and develop the findings and
recommendations as to the cost effectiveness of each rehabilitation
alternative in each of the main climatic zones covered by the SPS-6
experiment.
|
Figure 25. Recommended future analyses for SPS-6
experiment: Calibration and validation of the transfer functions of
rehabilitated jointed concrete pavement.
OBJECTIVE NO. 4
Calibrate and validate the relationships (transfer functions)
between pavement response and individual distress types for
rehabilitated jointed concrete pavements (expected timeframe: 2003
to 2005). |
TOPIC AREA
Pavement design |
PROBABILITY OF SUCCESS
High |
LTPP STRATEGIC PLAN
7A, 7B, and 7C |
SUPPLEMENTAL EXPERIMENTS
GPS-7 |
END PRODUCT
Calibrated and/or validated relationship between pavement
structural responses (stress) and individual distresses (perhaps
update mechanistic-empirical models from 2002 Design
Guide). |
POTENTIAL PRODUCT USE
Design new cost-effective and reliable jointed concrete pavement
rehabilitation alternatives. |
GENERAL TASKS
- Establish a comprehensive input database that includes design,
construction, materials testing, traffic, climatic, existing
pavement condition, and monitoring data for the response
model.
- Perform mechanistic analysis to determine the critical response
stress and cumulative fatigue damage for traffic loading applied
until the time of distress measurement.
- Establish the relationships between the cumulative fatigue
damage and the measured distress.
- Perform model assessment and develop calibration
coefficients.
|
Figure 26. Recommended future analyses for SPS-6
experiment: Study of the effects of experimental factors on the
performance of rehabilitated jointed concrete pavement.
OBJECTIVE NO. 5
Determine the optimum rehabilitation techniques for the design
features for specific site conditions and traffic loading for
rehabilitated jointed concrete pavements (expected timeframe: 2005
to 2007). |
TOPIC AREA
Pavement design |
PROBABILITY OF SUCCESS
High |
LTPP STRATEGIC PLAN
7A, 7B, and 7C
(Study of the Experimental Factors) |
SUPPLEMENTAL EXPERIMENTS
GPS-7 |
END PRODUCT
Guidelines, catalog, or software design tool for selecting optimum
combinations of rehabilitation design features for specific site
conditions and traffic level. |
POTENTIAL PRODUCT USE
Design cost-effective and reliable rehabilitation alternatives for
jointed concrete pavements. |
GENERAL TASKS
- Review results from each SPS-6 site (Objective 1) and from
Objectives 2 and 3.
- Conduct statistical analysis to determine significant factors
and interactions on up-to-date data.
- Conduct mechanistic-empirical analyses for transverse cracking,
joint faulting, rutting of overlays, reflection cracking of
overlays, and IRI.
- Obtain representative construction cost data for all needed
rehabilitation features of JPCP over selected regions that include
an SPS-6 experiment.
- Based on statistical and mechanistic analyses, identify the
optimum combination of pavement design features to be used for
various site conditions to provide costeffective and reliable
jointed concrete pavement rehabilitation.
- Prepare practical presentations of the results, including
software for use by practicing engineers, guidelines, catalogs,
etc., which will aid in determining the end products above.
|