U.S. DEPARTMENT OF TRANSPORTATION FEDERAL HIGHWAY ADMINISTRATION FISCAL MANAGEMENT INFORMATION SYSTEM
Report: FMISF71A-2
Florida

SUMMARY PROJECT LEVEL DATA PURSUANT TO 23 U.S.C. 104(g)(3)(B) WITH AN ESTIMATED TOTAL COST OF $25,000,000 OR MORE
AS OF SEPTEMBER 30, 2023
RECIPIENT
PROJECT
NUMBER
PROJECT TITLE
TOTAL
OBLIGATIONS
ESTIMATED
TOTAL
COST
Florida
0041228
I-4 MANAGED LANES FROM KIRKMAN TO SR 434; ADD LANES & RECONSTRUCT; PRELIMINARY ENGINEERING & CONSTRUCTION; DB
$903,901,412.00
$4,544,744,671.00
Florida
0105152
I-10 (SR 8) / SR 200 (US 301) INTERCHANGE OPERATIONAL IMPROVEMENTS;INTERCHANGE IMPROVEMENT;CONSTRUCTION
$108,271,456.00
$154,434,764.00
Florida
0751185
I-75 FROM SR 470 TO SR91(FLORIDA TURNPIKE);ADD LANES & RECONSTRUCT;CONSTRUCTION;DB
$14,603,840.00
$51,940,645.00
Florida
0754175
SR-93/I-75 ML SYSTEM FR S OF MIRAMAR PKWY INTG TO S OF SHERIDAN ST;ADD SPECIAL USE LANE;CONSTRUCTION;DB
$1,481,215.00
$97,963,937.00
Florida
0755096
I-75 AT SR 884 (COLONIAL BLVD) INTERCHANGE;INTERCHANGE IMPROVEMENT;PRELIMINARY ENGINEER
$55,570,320.00
$63,001,573.00
Florida
0757443
I-75 AT SR 64; INTERCHANGE IMPROVEMENT;CONSTRUCTION
$44,945,202.00
$51,692,830.00
Florida
0951671
SR-9/I-95 FR S. OF SR-842/BROWARD BLVD TO N. OF SR-870/COMMERCIAL BLVD; ADD SPECIAL USE LANE;CONSTRUCTION;DB
$77,743,312.00
$201,691,265.00
Florida
0951685
SR 9A/I-95 FROM NW 8 STREET TO NW 29 STREET;RIGID PAVEMENT RECONSTRUCTION;PRELIMINARY ENGINEER;DB
$36,161,715.00
$41,329,087.00
Florida
0951691
SR-9/I-95 FROM SW 10TH STREET TO BROWARD/PALM BEACH COUNTY LINE;ADD SPECIAL USE LANE;CONSTRUCTION;DB
$32,590,171.00
$119,190,177.00
Florida
0951694
SR-9/I-95 FROM BROW/PALM BCH CO LINE TO SOUTH OF GLADES RD.;ADD SPECIAL USE LANE;CONSTRUCTION;DB
$50,146,814.00
$58,340,989.00
Florida
0951695
SR-9/I-95 FROM SOUTH OF GLADES RD. TO SOUTH OF LINTON BLVD.;ADD SPECIAL USE LANE;CONSTRUCTION;DB
$31,238,492.00
$52,006,744.00
Florida
0953112
I-95 FROM SR 406 TO 0.5 MILE N OF SR 44;ADD LANES & REHABILITATE PVMN;CONSTRUCTION
$122,876,465.00
$136,937,342.00
Florida
0953133
I-95 INT @ ELLIS RD /ST JOHNS HERITAGE PKWY;INTERCHANGE (NEW);CONSTRUCTION
$46,184,911.00
$52,201,689.00
Florida
0955313
I-95 (SR 9) AT NORTH I-295 INTERCHANGE  ;INTERCHANGE RAMP (NEW);CONSTRUCTION;DB
$90,221,293.00
$240,801,338.00
Florida
0955314
I-95 (SR 9) AT I-10 INTERCHANGE OPERATIONAL IMPROVEMENT;INTERCHANGE - ADD LANES;CONSTRUCTION;DB
$4,544,596.00
$161,948,558.00
Florida
1002062
SR-80/SOUTHERN BLVD BRIDGES 930097 & 930098;BRIDGE REPLACEMENT;CONSTRUCTION
$48,901,530.00
$120,115,888.00
Florida
1171052
SR 77 FROM NORTH OF CR 279 TO N SUNNY HILLS ENTRANCE;ADD LANES & RECONSTRUCT;CONSTRUCTION;DB
$59,508,228.00
$89,488,062.00
Florida
1316003
GATEWAY EXPRESSWAY FM SR690 @ US19 & SR686 EXT @ CR611 TO W OF I-275;NEW ROAD CONSTRUCTION;PRELIMINARY ENGINEER;DB
$257,661,996.00
$2,602,743,816.00
Florida
1600003
SR 95 (US 29) FROM SR 8 (I-10) TO N OF SR 10 (US 90A) 9 MILE ROAD;ADD LANES & RECONSTRUCT;CONSTRUCTION
$59,369,586.00
$66,855,611.00
Florida
1852019
US 19 (SR 55) FROM W JUMP COURT TO W FORT ISLAND TRAIL;ADD LANES & RECONSTRUCT;CONSTRUCTION
$24,514,946.00
$139,930,183.00
Florida
2757410
I-275 (SR 93) FROM S OF GANDY BLVD TO N OF 4TH ST N;ADD LANES & RECONSTRUCT;ADMINISTRATION;DB
$138,725,731.00
$238,109,099.00
Florida
2955310
I-295 (SR 9A) FROM BUCKMAN BRIDGE TO I-95 AUX-LANES;ADD LANES & RECONSTRUCT;PRELIMINARY ENGINEER;DB-E2S01
$91,742,836.00
$94,732,580.00
Florida
2955314
I-295 (SR 9A) FROM SR202 JTB BLVD TO SR 9B  (MANAGED LANES);ADD LANES & RECONSTRUCT;CONSTRUCTION;DB
$152,830,539.00
$228,349,963.00
Florida
3115028
SR201 FROM S OF BALDWIN TO N OF BALDWIN (BYPASS);NEW ROAD CONSTRUCTION;CONSTRUCTION
$69,658,674.00
$77,051,104.00
Florida
3141036
SR429/46(WEKIVA PKW) FROM W OF OLD MCDONALD RD TO E OF WEKIVA RIVER RD;NEW ROAD CONSTRUCTION;CONSTRUCTION;DB
$30,502,118.00
$292,692,595.00
Florida
3141042
SR429/46(WEKIVA PKWY)FROM E OF WEKIVA RIVER RD TO ORANGE BOULEVARD;NEW ROAD CONSTRUCTION;CONSTRUCTION
$58,146,688.00
$246,171,141.00
Florida
3951501
SR 836/I-395 FROM WEST OF I-95 TO MACARTHUR CSWY BRIDGE;BRIDGE-REPLACE AND ADD LANES;CONSTRUCTION;DB
$181,135,675.00
$760,197,855.00
Florida
4002027
SR20 FROM SW 56TH AVENUE TO CR315 IN INTERLACHEN;ADD LANES & RECONSTRUCT; UTILITY WORK IN PREP FOR CONSTRUCTION.
$30,601,324.00
$36,384,171.00
Florida
4031035
SR 997/KROME AVENUE FROM SW 232 STREET TO S OF SW 184TH ST/EUREKA DR.;ADD LANES & RECONSTRUCT;CONSTRUCTION SUPPORT
$25,351,580.00
$41,415,639.00
Florida
4047203
CR 580/SAM ALLEN RD FM W OF SR39/BUCHMAN HWY TO E OF PARK RD;ADD LANES & RECONSTRUCT;CONSTRUCTION
$23,695,830.00
$30,578,736.00
Florida
4221091
SR 30 (US 98) PENSACOLA BAY BRIDGE NO. 480035;BRIDGE REPLACEMENT;CONSTRUCTION;DB
$18,344,966.00
$488,514,412.00
Florida
4222081
SR 30 (US 98) FROM EMERALD BAY DRIVE TO TANG-O-MAR DRIVE;ADD LANES & RECONSTRUCT;CONSTRUCTION
$53,954,461.00
$58,640,090.00
Florida
4751163
SR-7/US-441 FROM N. OF FILLMORE TO S OF STIRLING RD;ADD LANES & RECONSTRUCT;CONSTRUCTION;DB
$4,527,165.00
$45,203,759.00
Florida
4881064
SR 200 (A1A) FROM WEST OF RUBIN RD TO EAST OF CR 107/SCOTT RD;ADD LANES & RECONSTRUCT;CONSTRUCTION
$58,985,735.00
$81,465,943.00
Florida
5951553
I-595/SR-862/ P3 FROM E. OF I-75 TO W. OF I-95;ADD LANES & RECONSTRUCT;CONSTRUCTION
$665,711,369.00
$2,573,569,549.00
Florida
5951556
I595/P3/RESURFACING FROM E OF I-75 TO W. OF I-95;RESURFACING  
$80,952,434.00
Florida
5951557
I595/P3/RESURFACING FROM E OF I-75 TO W. OF I-95;RESURFACING  
$124,950,849.00
Florida
5951560
I-595/SR-862/ P3 FROM E. OF I-75 TO W. OF I-95;ADD LANES & RECONSTRUCT;CONSTRUCTION;DB - AVAILABILITY PAYMENTS & OPERATIONS UNDER CRRSSA
$160,390,282.00
$160,390,282.00
Florida
6107003
SR 847/NW 47 AVENUE FROM SR 860/NW 183 STREET TO N. OF NW 199 STREET;ADD LANES & RECONSTRUCT;CONSTRUCTION
$20,730,369.00
$29,539,605.00
Florida
6268021
SR 826 FROM FLAGLER ST TO NW 154 ST. & I-75 FROM SR 826 TO NW 170 ST.;ADD SPECIAL USE LANE;CONSTRUCTION;DB
$219,899,167.00
$319,198,240.00
Florida
7079006
SR-713/KINGS HWY FR 800' S OF SR-70 TO N OF PICOS ROAD;ADD LANES & RECONSTRUCT;CONSTRUCTION
$11,923,352.00
$36,958,568.00
Florida
7810035
SR 54 FROM CR 577/CURLEY RD TO CR 579/MORRIS BRIDGE RD;ADD LANES & REHABILITATE PVMNT;CONSTRUCTION
$35,007,182.00
$53,833,330.00
Florida
8886496
CR 4050 ORANGE AVE BR#794003 VETERANS MEMORIAL BRIDGE;BRIDGE REPLACEMENT;CONSTRUCTION;LAP
$43,321,726.00
$50,241,167.00
Florida
8886535
CROSSTOWN PARKWAY FROM MANTH LANE TO SR-5/US-1;NEW BRIDGE CONSTRUCTION;CONSTRUCTION;LAP
$46,175,530.00
$107,650,061.00
Florida
8886777
W. MIDWAY RD/CR-712 FROM S. 25TH STREET/SR-615 TO SR-5/US-1;ADD LANES & RECONSTRUCT;CONSTRUCTION
$31,294,239.00
$39,562,104.00
Florida
8886919
SR 46 / US 441 FROM W OF US 441 TO E OF VISTA VIEW LANE;ADD LANES & RECONSTRUCT;CONSTRUCTION; WEKIVA SECTIONS 3A AND 3B
$8,051,024.00
$65,869,341.00
Florida
ARR1134
SR 826/SR 836 FROM N OF SW 8 ST TO S OF NW 25 ST & FM NW 87 TO 57 AVE';INTERCHANGE (MODIFY);CONSTRUCTION;DB
$309,200,121.00
$567,489,632.00
Florida
ARR1279
I-4/SELMON EXPRESSWY FROM S OF SELMON EXPRSSW TO I-4;INTERCHANGE (NEW);CONSTRUCTION
$220,736,422.00
$226,120,955.00
Florida
D117027
I-75 FROM S OF N JONES LOOP TO N OF US 17    ;ADD LANES & RECONSTRUCT;CONSTRUCTION
$29,974,357.00
$36,266,388.00
Florida
D117115
I-75 AT SR 70 INTERCHANGE;INTERCHANGE - ADD LANES;CONSTRUCTION
$90,186,644.00
$120,046,639.00
Florida
D118021
US 41 - VENICE BYPASS FROM CENTER RD TO GULF COAST BLVD;ADD LANES & RECONSTRUCT;CONSTRUCTION
$14,153,429.00
$26,754,935.00
Florida
D118039
US 41 (SR 45) FROM WINKLER AVENUE TO SR 82   ;RESURFACING;CONSTRUCTION
$6,843,283.00
$31,508,035.00
Florida
D118043
I-4 AT SR 557 ;INTERCHANGE IMPROVEMENT;ENVIRONMENTAL;DB
$82,643,756.00
$91,583,064.00
Florida
D118127
I-75 (SR 93) AT US 301 INTERCHANGE ;INTERCHANGE - ADD LANES;CONSTRUCTION;DB
$152,050,689.00
$167,262,842.00
Florida
D119037
US 27 AT SR 60;INTERCHANGE - ADD LANES;CONSTRUCTION
$51,037,209.00
$58,529,274.00
Florida
D119075
SR 542 FROM BUCKEYE LOOP ROAD TO US 27;ADD LANES & RECONSTRUCT;CONSTRUCTION
$43,890,987.00
$53,785,491.00
Florida
D120030
I-75 (SR 93) AT SR 72 (CLARK ROAD) INTERCHANGE;INTERCHANGE - ADD LANES;CONSTRUCTION
$57,544,169.00
$64,179,810.00
Florida
D120059
I-4 (SR 400) AT CSX RAILROAD;BRIDGE REPLACEMENT;CONSTRUCTION
$14,834,051.00
$38,468,962.00
Florida
D121032
SR 70 FROM PEACE RIVER TO SE BAKER STREET;FLEXIBLE PAVEMENT RECONSTRUCT.;CONSTRUCTION
$19,165,583.00
$37,425,594.00
Florida
D122025
SR 683 (US 301) FROM S OF 25TH CT E TO S OF 13TH AVE E;RESURFACING;CONSTRUCTION
$6,871,635.00
$28,678,990.00
Florida
D122041
SR 25 (US 27) FROM N OF SR 540 TO N OF KOKOMO RD;RESURFACING;CONSTRUCTION;DB
$12,059,231.00
$25,064,677.00
Florida
D122068
SR 70 FROM LORRAINE ROAD TO BOURNSIDE BLVD   ;ADD LANES & RECONSTRUCT;CONSTRUCTION;DB
$392,862.00
$50,081,155.00
Florida
D217011
FCX SOUTH OF US17 TO NORTH OF SR16; NEW ROAD CONSTRUCTION;CONSTRUCTION
$100,563,020.00
$913,741,145.00
Florida
D217069
SR200(US301) FROM: BRADFORD C/L TO: NORTH OF CR218;MISCELLANEOUS CONSTRUCTION;CONSTRUCTION; CONCRETE PROJECT WITH STATE MATERIALS
$19,585,019.00
$37,786,847.00
Florida
D217080
SR15(US17) FROM: W. OF DUNNS CREEK TO: HORSE LANDING RD;ADD LANES & RECONSTRUCT;CONSTRUCTION
$42,153,656.00
$50,993,035.00
Florida
D217103
I-295(SR9A) ARTERIAL TRAFFIC MGMT (BUCKMAN BRG)SR13 TO US17(SR15);ATMS - ARTERIAL TRAFFIC MGMT;CONSTRUCTION
$15,873,078.00
$26,610,098.00
Florida
D217128
I-10 FROM I-295 TO I-95;ADD MANAGED LANES;PRELIMINARY ENGINEER;DB
$172,851,749.00
$270,900,377.00
Florida
D218017
SR23 FROM NORTH OF SR16 TO NORTH OF SR21(BLANDING BLVD);NEW ROAD CONSTRUCTION;CONSTRUCTION
$113,044,129.00
$282,609,610.00
Florida
D218123
SR23(FIRST COAST XWAY) FROM EAST OF CR16A (SPUR) TO EAST OF CR209     ;NEW ROAD CONSTRUCTION;CONSTRUCTION;DB  
$673,670,612.00
Florida
D219037
I-95(SR9) FROM: FLAGLER C/L TO: SR207;RESURFACING;CONSTRUCTION
$24,494,496.00
$26,805,330.00
Florida
D219120
URBAN CORE RIVERFRONT REVITALIZATION & COMPLETE STREETS;MISCELLANEOUS CONSTRUCTION;PRELIMINARY ENGINEER;LAP
$12,636,580.00
$51,182,261.00
Florida
D219130
I-95(SR9) FROM SR207 TO INTL GOLF PARKWAY;RESURFACING;CONSTRUCTION
$17,511,380.00
$26,414,490.00
Florida
D220122
I-95(SR9) FROM SOUTH OF SR126(EMERSON ST) TO ATLANTIC BLVD;ADD LANES & RECONSTRUCT;CONSTRUCTION;DB
$132,586.00
$286,918,845.00
Florida
D221010
SR116(WONDERWOOD) FROM: JANE STREET TO SAND CASTLE LANE;RESURFACING;CONSTRUCTION
$23,165,452.00
$36,893,498.00
Florida
D221018
I-295(SR9A) @ US17 TO SOUTH OF WELLS ROAD;INTERCHANGE - ADD LANES;CONSTRUCTION
$24,409,190.00
$27,558,445.00
Florida
D221062
SR115 FROM SOUTHSIDE BLVD TO MATHEWS BRIDGE;RESURFACING;CONSTRUCTION
$7,709,582.00
$27,396,026.00
Florida
D222030
I-95(SR9) @ SR115(US1)/ML KING/20TH STREET   ;INTERCHANGE - ADD LANES;CONSTRUCTION
$53,049,618.00
$91,301,910.00
Florida
D222084
I-295(SR9A) FROM MORSE AVE TO US90           ;RESURFACING;CONSTRUCTION
$22,491,686.00
$30,810,812.00
Florida
D317016
SR 30 (US 98) ELEVATED ROADWAY E TO W OF TYNDALL AFB ENTRANCE;INTERCHANGE - ADD LANES;CONSTRUCTION;DB
$25,859,887.00
$43,726,605.00
Florida
D317035
SR 388 WEST BAY PARKWAY FROM SR 79 TO E OF NWF BEACHES INTL AIRPORT;ADD LANES & RECONSTRUCT;CONSTRUCTION
$65,449,406.00
$97,456,770.00
Florida
D318058
SR 30 (US 98) GREGORY ST & BAYFRONT PKWY @ 17TH AVE INTERCHANGE;MISCELLANEOUS CONSTRUCTION;CONSTRUCTION;DB
$11,277,006.00
$29,671,630.00
Florida
D319003
SR 390 ST ANDREWS FROM SR 368 23RD ST TO E OF CR 2312 BALDWIN ROAD;ADD LANES & RECONSTRUCT;CONSTRUCTION
$41,030,700.00
$53,159,240.00
Florida
D319075
SR 77 FROM BAY COUNTY LINE TO NORTH OF CR 279;ADD LANES & RECONSTRUCT;CONSTRUCTION
$29,224,156.00
$46,196,080.00
Florida
D319079
SR 30 (US 98) FROM BAYSHORE ROAD TO PORTSIDE DRIVE;ADD LANES & RECONSTRUCT;PRELIMINARY ENGINEER;DB
$74,959,706.00
$86,708,676.00
Florida
D319080
SR 369 (US 319) FROM EAST IVAN ROAD TO NORTH OF SR 267;ADD LANES & RECONSTRUCT;CONSTRUCTION
$24,480,478.00
$32,334,416.00
Florida
D320013
SR 8 (I-10) INTERCHANGE WEST OF CRESTVIEW;INTERCHANGE (NEW);CONSTRUCTION SUPPORT;DB
$9,565,369.00
$96,859,782.00
Florida
D320016
SR 263 CAPITAL CIRCLE FROM CR 2203 SPRINGHILL RD TO SR 371 ORANGE AVE;ADD LANES & RECONSTRUCT;CONSTRUCTION
$30,569,186.00
$79,866,987.00
Florida
D320021
SR 10 (US 90) OVER SIMPSON RIVER BRIDGE NO. 580056 & 580108;BRIDGE REPLACEMENT;CONSTRUCTION
$8,451,501.00
$29,194,674.00
Florida
D322007
SR 77 FROM NORTH OF ROGERS ROAD TO SOUTH OF CANE MILL ROAD;ADD LANES & RECONSTRUCT;CONSTRUCTION  
$65,508,453.00
Florida
D322015
SR 8 (I-10) @ SR 95 (US 29) INTERCHANGE      ;INTERCHANGE - ADD LANES;CONSTRUCTION  
$249,419,876.00
Florida
D322082
SR 30A (US 98) PC BEACH PKWY FROM MANDY LANE TO EAST OF NAUTILUS ST;ADD LANES & RECONSTRUCT;CONSTRUCTION  
$57,615,300.00
Florida
D322083
SR 30A (US98) PC BCH PKWY FROM E OF NAUTILUS ST TO E OF R JACKSON BLVD;ADD LANES & RECONSTRUCT;CONSTRUCTION  
$74,463,882.00
Florida
D323054
SR 30 (US 98) OVER ST ANDREWS BAY ICWW BRIDGE NO. 460019;BRIDGE REPLACEMENT;CONSTRUCTION;DB
$48,305,698.00
$148,933,678.00
Florida
D323055
SR 8 (I-10) OVER SR 10 (US 90A) NINE MILE RD BR NO. 480061 & 480066;BRIDGE REPLACEMENT;CONSTRUCTION
$27,678,980.00
$70,291,426.00
Florida
D417080
SR-80 FROM W OF LION COUNTRY SAFARI RD TO FOREST HILL/CRESTWOOD BLVD.;ADD LANES & REHABILITATE PVMNT;CONSTRUCTION
$33,595,658.00
$47,199,656.00
Florida
D418011
SR-9/I-95 @ SR-808/GLADES ROAD;INTERCHANGE - ADD LANES;CONSTRUCTION;DB
$27,560,982.00
$29,571,843.00
Florida
D419098
SR-9/I-95 @COPANS RD FR S OF NB EXIT RAMP TO N OF SB TO WB EXIT RAMP;INTERCHANGE JUSTIFICA/MODIFICA;CONSTRUCTION
$28,094,527.00
$29,351,564.00
Florida
D420011
LOXAHATCHEE RD. FROM ARTHUR MARSHALL LOXAHATCHEE REFUGE TO SR-7/US-441;ROAD RECONSTRUCTION - 2 LANE;CONSTRUCTION
$15,790,125.00
$38,037,895.00
Florida
D420092
SR-A1A NORTH BRIDGE OVER ICWW BRIDGE #940045 ;BRIDGE REPLACEMENT;CONSTRUCTION
$13,107,403.00
$136,235,123.00
Florida
D421056
SR-5/US-1 FEDERAL HIGHWAY FROM CR-A1A TO BEACH ROAD;BRIDGE REPLACEMENT;CONSTRUCTION SUPPORT
$3,828,311.00
$136,545,913.00
Florida
D421077
SR-710/BEELINE HWY FROM NORTHLAKE BLVD TO SR-708/BLUE HERON BLVD;ADD LANES & RECONSTRUCT;CONSTRUCTION
$7,468,985.00
$170,054,234.00
Florida
D422005
SR-869/SW 10TH STREET CONNECTOR TSM&O SMART WORK ZONE;ITS COMMUNICATION SYSTEM;CONSTRUCTION;DB
$2,791,899.00
$29,360,054.00
Florida
D422059
SR-9/I-95 @ 6TH AVENUE SOUTH;INTERCHANGE - ADD LANES;CONSTRUCTION  
$26,220,410.00
Florida
D422077
SR-9/I-95 FROM SOUTH OF SW 10TH STREET TO NORTH OF HILLSBORO BLVD.;INTERCHANGE - ADD LANES;CONSTRUCTION;DB  
$846,113,531.00
Florida
D422093
SR-9/I-95 @ OSLO ROAD INTERCHANGE;INTERCHANGE (NEW);CONSTRUCTION
$3,596,419.00
$67,285,488.00
Florida
D423002
OSLO ROAD FROM SW 82ND AVE TO 58TH AVENUE;ADD LANES & RECONSTRUCT;CONSTRUCTION SUPPORT
$2,880,874.00
$48,251,135.00
Florida
D517015
SR 429 (WEKIVA PKWY) FROM ORANGE BOULEVARD TO W OF I-4 (SR 400);NEW ROAD CONSTRUCTION;CONSTRUCTION;DB
$134,317,170.00
$340,751,641.00
Florida
D518022
SR 46 (WEKIVA PKWY) FROM ORANGE BLVD TO N. OREGON ST/WAYSIDE DR; ADD LANES & RECONSTRUCT; CONSTRUCTION
$15,044,749.00
$26,079,015.00
Florida
D519013
SR 500 (US 441) FROM LAKE ELLA RD TO AVENIDA CENTRAL; ADD LANES & RECONSTRUCT; CONSTRUCTION
$42,870,936.00
$52,557,246.00
Florida
D520035
I-4 (SR 400) AT DARYL CARTER PARKWAY INTERCHANGE;INTERCHANGE (NEW);CONSTRUCTION
$21,731,972.00
$85,257,966.00
Florida
D520075
SR 93 (I-75) FROM SUMTER COUNTY TO SR 200; RESURFACING; CONSTRUCTION
$28,742,179.00
$31,573,246.00
Florida
D521023
I-4 @ SAND LAKE RD INTERCHANGE FROM E OF SR 528 TO W OF SR 435;INTERCHANGE IMPROVEMENT;CONSTRUCTION
$206,262,754.00
$234,171,755.00
Florida
D521049
SR 464 FROM SR 500 (US 27/301) TO SR 35; RESURFACING; CONSTRUCTION
$14,432,051.00
$25,279,655.00
Florida
D521092
SPACE COMMERCE WAY;ADD LANES & REHABILITATE PVMNT;CONSTRUCTION
$16,500,000.00
$29,722,571.00
Florida
D522091
NEPTUNE ROAD FROM SOUTH OF KINGS CREST RD TO SR 500 / US 192;WIDEN/RESURFACE EXIST LANES;CONSTRUCTION;LAP
$4,393,714.00
$51,314,503.00
Florida
D523009
I-75 (SR 93) REST AREA MARION COUNTY FROM N OF SR 484 TO S OF SR 200;REST AREA;CONSTRUCTION
$6,453,801.00
$38,067,726.00
Florida
D523042
NEPTUNE RD FROM PARTIN SETTLEMENT RD TO S OF KINGS CREST ROAD;WIDEN/RESURFACE EXIST LANES;CONSTRUCTION;LAP
$1,320,585.00
$25,906,667.00
Florida
D617044
SR 968/SW 1ST STREET AT MIAMI RIVER (BRIDGE #870660);BRIDGE REPLACEMENT;CONSTRUCTION
$64,999,715.00
$88,768,005.00
Florida
D619048
SR 826/PALMETTO EXPY - SR 826 EASTBOUND RAMP TO SR 9A/I-95 NORTHBOUND;INTERCHANGE RAMP (NEW);CONSTRUCTION
$14,706,111.00
$92,050,159.00
Florida
D620056
SR 25/OKEECHOBEE RD FROM E. OF NW 107 AVE TO E. OF NW 116 WAY(CNCRETE);ADD LANES & REHABILITATE PVMNT;CONSTRUCTION
$62,378,658.00
$126,031,294.00
Florida
D621008
SR 25/OKEECHOBEE RD FROM BROWARD COUNTY LINE TO WEST OF HEFT;ADD LANES & RECONSTRUCT;CONSTRUCTION
$49,547,094.00
$54,710,096.00
Florida
D622074
SR 7 AND SR 9/GOLDEN GLADES INTERCHANGE VARIOUS RAMP IMPROVEMENTS;INTERCHANGE RAMP (NEW);CONSTRUCTION
$47,531,861.00
$93,799,931.00
Florida
D622075
SR 826 CONNECTOR AT GOLDEN GLADES INTERCHG AND VARIOUS RAMPS;ADD LANES & RECONSTRUCT;CONSTRUCTION
$86,534,505.00
$86,534,505.00
Florida
D717065
I75/SR 56 INTERCHANGE FM E OF CR 54 TO W OF CYPRESS RIDGE BL(PHASE I);INTERCHANGE - ADD LANES;CONSTRUCTION
$42,211,254.00
$49,395,195.00
Florida
D718036
SR 52 (SCHRADER HWY) FROM W OF SUNCOAST PKWY TO E OF US 41 (SR 45);ADD LANES & RECONSTRUCT;CONSTRUCTION
$34,218,196.00
$59,861,589.00
Florida
D718055
I-275 (HOWARD FRKL) FROM N OF SR687(4TH ST N) TO N OF HOWARD FRANKLAND;BRIDGE-REPLACE AND ADD LANES;PRELIMINARY ENGINEER;DB
$230,619,874.00
$706,960,914.00
Florida
D718056
I-275 (HOWARD FRKL) FM N OF HOWARD FRANKLAND TO S OF SR 60;BRIDGE-REPLACE AND ADD LANES;PRELIMINARY ENGINEER;DB
$33,377,721.00
$51,682,122.00
Florida
D718067
SR 50 FM WINDMERE RD/BRONSON BL TO US 98/MCKETHAN RD;ADD LANES & REHABILITATE PVMNT;CONSTRUCTION
$37,756,362.00
$43,900,810.00
Florida
D719008
SR 50 FROM US 98/MCKETHAN RD TO US 301;ADD LANES & REHABILITATE PVMNT;CONSTRUCTION
$21,032,174.00
$25,399,595.00
Florida
D720029
US 41/SR 45 FROM N OF 15TH AVE TO S OF BULLFROG CREEK;RESURFACING;CONSTRUCTION
$23,790,391.00
$29,681,359.00
Florida
D720031
I-75 (SR 93A) FM S OF CSX/BROADWAY AVE TO EB/WB I-4 EXIT RAMP;INTERCHANGE - ADD LANES;CONSTRUCTION;DB
$97,259,199.00
$105,261,264.00
Florida
D721012
I-275 (SR 93) FROM N OF MLK TO N OF HILLSBOROUGH AVE;ADD LANES & RECONSTRUCT;CONSTRUCTION
$40,506,860.00
$46,884,409.00
Florida
D721013
I-275/SR 93 FROM N OF I-4 TO N OF MLK;ADD LANES & RECONSTRUCT;CONSTRUCTION
$52,839,257.00
$59,132,214.00
Florida
D721023
US 19 (SR 55) FROM N OF SR 580 (MAIN ST) TO NORTHSIDE DR;ADD LANES & RECONSTRUCT;CONSTRUCTION
$103,765,660.00
$123,557,404.00
Florida
D721027
I-4/SR 400 FROM DOWNTOWN TAMPA TO POLK COUNTY LINE;ITS COMMUNICATION SYSTEM;CONSTRUCTION
$11,541,288.00
$27,780,963.00
Florida
D721035
US 19 (SR 55) FROM NORTHSIDE DR TO NORTH OF CR 95;ADD LANES & RECONSTRUCT;CONSTRUCTION
$131,474,428.00
$147,783,516.00
Florida
D722039
US 19/SR55/34TH ST FROM SR 682/54TH AVE S TO 22ND AVE N;RESURFACING;CONSTRUCTION
$14,166,520.00
$26,131,707.00
Florida
D722064
I-4/SR 400 FROM E OF MCINTOSH RD TO E OF COUNTY LINE RD;RESURFACING;CONSTRUCTION SUPPORT
$35,130,965.00
$42,877,932.00
Florida
D723023
I-75/SR 93A FROM S OF PROGRESS BLVD TO N OF WOODBERRY RD;RIGID PAVEMENT REHABILITATION;CONSTRUCTION  
$28,921,149.00
Florida
E221002
HURRICANE IAN SANIBEL ISLAND ACCESS - EMERGENCY ROAD REPAIRS; EMERGENCY OPERATIONS; SANIBEL CSWY/SEXTANT - DB - IN12002E  
$70,758,737.00
Florida
E221006
HURRICANE IAN PINE ISLAND ROADWAY PERMANENT REPAIRS; EMERGENCY OPERATIONS; PINE ISLAND BRIDGE APPROACH - IN12006P
$41,243,579.00
$50,340,028.00
Florida
NASA002
NASA CAUSEWAY BRIDGE; BRIDGE REPLACEMENT; CONSTRUCTION
$86,988,000.00
$93,773,517.00
Florida
PMT1001
PORT OF MIAMI TUNNEL FROM PORT OF MIAMI TO SR 836/I-395;NEW ROAD CONSTRUCTION;CONSTRUCTION;DB
$214,270,573.00
$2,365,899,035.00
Florida
SR20001
SR20 FROM ALACHUA C/L TO SW 56TH AVENUE;ADD LANES & RECONSTRUCT;CONSTRUCTION
$45,637,697.00
$73,076,726.00
Florida
TAMI002
SR-90/US HWY-41/TAMIAMI TRAIL FROM STRUCTURE S-333 TO STRUCTURE S-334;FLEXIBLE PAVEMENT RECONSTRUCT.;CONSTRUCTION;DB
$65,772,857.00
$74,140,362.00
Florida
TGER002
FIU UNIVERSITY CITY PROSPERITY PROJ. ALONG SW 109 AVE & SR 90/SW 8 ST; PEDESTRIAN OVERPASS; DESIGN & CONSTRUCTION MANAGED BY FDOT
$25,015,326.00
$33,441,740.00
Florida
TGER004
BIG BEND ROAD/CR 672 @ I-75/SR93A FROM W OF COVINGTON TO E OF SIMMONS;INTERCHANGE - ADD LANES;CONSTRUCTION;DB
$25,000,000.00
$104,015,237.00
Florida
TPEX275
I275/SR93 FM N OF HFB TO N OF LOIS,SR60 FM KENNEDY TO N OF SPRUCE/TIA;ADD LANES & RECONSTRUCT;PRELIMINARY ENGINEER;DB
$467,677,830.00
$1,541,965,168.00