RECIPIENT |
PROJECT NUMBER |
PROJECT TITLE |
TOTAL OBLIGATIONS |
ESTIMATED TOTAL COST |
---|---|---|---|---|
Nevada | I15 / CC215 BELTWAY INTERCHANGE: PE/ROW | $116,584,912.60 |
$136,768,336.00 |
|
Nevada | LAUGHLIN TO BULLHEAD CITY BRIDGE, CLARK CO., FROM MOHAVE VALLEY HWY TO NEEDLES HWY. OFF SYSTEM | $18,190,998.67 |
$51,787,335.00 |
|
Nevada | LAS VEGAS, GRAND TETON DRIVE BETWEEN TEE PEE LANE AND EL CAPITAN WAY (OFF SYSTEM) | $20,413,317.00 |
$47,324,811.00 |
|
Nevada | LV SO BELTWAY (I-215) FM STEPHANIE TO I-515, PE, ROWA utilities/acquisition, construction. Construct system interchange & roadway. | $90,686,811.67 |
$131,470,387.37 |
|
Nevada | US 50, LYON TO CHURCHILL COUNTY, VIRGINIA ST. TO LEETEVILLE JUNCTION; MP LY 29.69 TO MP LY 35.40, MP CH 0.00 TO MP CH 11.24 | $51,841,349.58 |
$80,294,755.00 |
|
Nevada | I 11, I 515, I 215, CLARK COUNTY, HENDERSON INTERCHANGE FROM HORIZON DR TO GALLERIA DR AND FROM VAN WAGENEN ST TO VALLE VERDE DR | $14,161,451.68 |
$452,160,000.00 |
|
Nevada | I15 NORTH OF US95/I515 TO CRAIG ROAD WIDEN FM 6 TO 10 LANES FROM US 95/I515 TO LAKE MEAD BLVD: WIDEN 8 TO 10 FM LAKE MEAD TO CRAIG | $77,981,027.00 |
$259,704,838.00 |
|
Nevada | I 15 CACTUS AVE IN LAS VEGAS NEVADA. CONSTRUCT NEW INTERCHANGE. PE/ROW/CONSTRUCTION | $59,402,861.98 |
$63,081,090.29 |
|
Nevada | I 15 AT STARR AVENUE / PE AND RW FOR NEW INTERCHANGE. | $12,755,741.45 |
$60,043,179.31 |
|
Nevada | I 15/ US 95 NEON DESIGN BUILD, SAHARA AVE. TO US 95 INTERCHANGE | $122,697,437.87 |
$667,221,824.00 |
|
Nevada | I 15, CLARK COUNTY, GARNET INTERCHANGE @ US 93 MP CL 64.29 US 93 FROM MP CL 52.00 TO MP CL 57.00 | $70,255,946.00 |
$81,134,198.00 |
|
Nevada | I 15, LAS VEGAS, AT TROPICANA AVE INTERCHANGE; I 15 AT HARMON AVE OVERPASS; WARM SPRINGS RD TO HARMON AVE | $127,818,026.00 |
$363,408,500.00 |
|
Nevada | I 15 NORTH, CLARK COUNTY, FROM SPEEDWAY TO APEX (PHASE 3) MP CL 53.61 TO MP CL 58.38 | $39,386,961.00 |
$41,834,957.00 |
|
Nevada | I 15 NORTH, CLARK COUNTY, FROM APEX TO GARNET (PHASE 3) MP CL 58.38 TO MP CL 64.28 | $41,083,512.00 |
$43,245,800.00 |
|
Nevada | I 15 S, CLARK COUNTY, PH 2, FROM SLOAN RD TO JUST NORTH OF WARM SPRINGS, MP CL 25.52 TO MP CL 34.4 | $75,305,744.00 |
$88,397,583.00 |
|
Nevada | I 15, CL CO, 0.207 MI S OF BONANZA GRD SEP, TO 0.245 MI S OF CRAIG INT, MP 42.97 TO 48.17; SR 147, CL CO, 0.068 MI E OF LOSEE TO YALE, MP 0.07 TO 0.40 | $24,681,009.00 |
$25,986,310.00 |
|
Nevada | I 15, CLARK COUNTY, IN MESQUITE FROM 1.677 MI NORTH OF THE LOGANDALE/OVERTON INTERCHANGE TO 0.370 MI NORTH OF LOWER FLAT TOP DR; SB MP CL 95.559 TO MP | $37,706,635.00 |
$39,721,193.00 |
|
Nevada | SR 159, CHARLESTON BLVD FROM HONOLULU ST TO SACRAMENTO DR, MP CL 29.45 TO MP CL 29.80; I 515, FROM WYOMING AVE TO EASTERN AVE, MP CL 71.19 TO MP 73.37 | $44,386,918.17 |
$82,078,719.00 |
|
Nevada | US 395, NORTH OF RENO, FROM MCCARRAN TO GOLDEN VALLEY STRUCTURE, MP WA 27.064 TO MP WA 31.107 | $91,102,585.32 |
$174,738,781.65 |
|
Nevada | SR 376, NYE COUNTY, FROM 0.275 MILES NORTH OF CARVER'S ROADSIDE REST PARK TO US 50; MP NY 53.943 TO MP LA 18.065 | $30,016,136.00 |
$32,580,759.00 |
|
Nevada | SR 445, PYRAMID HIGHWAY, FROM QUEEN WAY TO GOLDEN VIEW DRIVE; MP WA 2.00 TO MP WA 4.50 | $38,000,000.00 |
$69,034,419.00 |
|
Nevada | US 50, LYON COUNTY, FROM ROY'S ROAD TO THE JUNCTION WITH US 95A. MP LY 19.90 TO LY 29.44 | $57,595,639.46 |
$60,917,455.00 |
|
Nevada | I 80, WASHOE COUNTY, FROM THE CA/NV STATELINE TO MCCARRAN INTERCHANGE. WA MP 0.00 TO WA MP 10.682; PACKAGE 2 | $26,266,689.00 |
$27,924,147.00 |
|
Nevada | I 80, PERSHING COUNTY, FROM 2.28 MILES EAST OF COAL CANYON INTERCHANGE TO 1.69 MILES EAST OF HUMBOLDT INTERCHANGE. MP PE 26.15 TO MP PE 51.30 | $26,925,231.00 |
$28,342,349.00 |
|
Nevada | I 80, LA CO, BEGIN OF ASPHALT 0.424 W OF ROSNY CK GRD SEP TO EU CO BEGIN OF PCCP 2.877 E OF LA/EU CO LINE; MP LA 15.889 TO 26.970; MP EU 0 TO 2.877 | $27,364,643.00 |
$28,804,889.00 |
|
Nevada | IR80W/IR80E, HUMBOLDT COUNTY, 0.94 MILES WEST OF GOLCONDA SUMMIT INTERCHANGE TO 2.36 MILES EAST, HU 32.500 TO HU 38.800 | $52,751,696.00 |
$60,797,832.00 |
|
Nevada | I 80, EUREKA COUNTY, AT EMIGRANT PASS | $24,332,245.00 |
$28,343,063.00 |
|
Nevada | I 80, ELKO COUNTY, FROM 0.932 MILES WEST OF OSINO INTERCHANGE TO 0.611 MILES EAST OF GRAYS CREEK; MP EL 31.980 TO MP EL 61.966 | $27,590,461.00 |
$29,042,590.00 |
|
Nevada | I80 1.04 MI E OF MOOR INTRCHG TO 1.87 MI E OF OASIS INTRCHG. PE/ROW | $37,297,334.88 |
$39,293,353.00 |
|
Nevada | I 80, ELKO COUNTY, FROM 3.161 MILES WEST OF PILOT PEAK INTERCHANGE TO THE NV/UT STATE LINE; MP EL 117.594 TO MP EL 132.726 | $42,629,173.00 |
||
Nevada | US93 From the Hoover Dam Interchange Bridge to 1 MS of the Junction of US95/ US93. Hoover Dam Bypass - Boulder Extension. | $253,024,309.52 |
$292,945,128.15 |
|
Nevada | US 93 BOULDER CITY BYPASS PART 1, PACKAGE 3 FROM SILVERLINE TO FOOTHILL ROAD. CL 16.35 TO CL 14.72 | $82,745,184.00 |
$128,678,039.00 |
|
Nevada | US95 AT RAINBOW CURVE (PHASES 2C & 2D). CONSTRUCTION | $44,561,874.41 |
$47,835,106.00 |
|
Nevada | US 95 FM MARTIN LUTHER KING TO VALLEY VIEW BLVD. CONSTRUCTION | $64,943,610.66 |
$68,551,694.71 |
|
Nevada | US 95 from East of Valley View to Rainbow Interchange (Phase 4B/5). Construction | $95,112,193.73 |
$106,034,709.00 |
|
Nevada | US 95, LAS VEGAS, FROM ANN ROAD TO KYLE CANYON ROAD MP CL 86.75 TO MP CL 92.70 PACKAGE 2B/5 | $42,356,460.00 |
$77,979,339.00 |
|
Nevada | US 95 NW CORRIDOR PHASE 3C AT MP 88 AND CC 215 FROM GRAND MONTECITO TO TENAYA WAY. MP 88 AND CC 215 37-39. | $18,391,964.00 |
$80,030,703.00 |
|
Nevada | US 95 NW PHASE 3D, MP 88 AND CC215 FROM GRAND MONTECITO TO TENAYA, MP CL 37-39 AND US 95 AT LONE MOUNTAIN MP CL 85.6 | $88,634,108.00 |
$162,793,795.00 |
|
Nevada | US 95, NYE COUNTY, 1.301 MILES SOUTH OF AMARGOSA VALLEY JUNCTION TO 1.742 MILES SOUTH OF THE AMARGOSA RIVER, MP NY 28.817 TO MP NY 56.234 | $24,828,488.00 |
$26,135,250.00 |
|
Nevada | US 95 FROM 12.16 MILES NORTH OF BEATTY TO 3.67 MILES SOUTH OF THE NY/ES COUNTY LINE. NY 72.036 TO NY 103.552 | $16,890,072.18 |
$36,721,092.00 |
|
Nevada | SR 160, BLUE DIAMOND ROAD, CLARK CO. FROM THE WEST EDGE OF MOUNTAIN SPRINGS COMMUNITY TO THE BEGINNING OF MOUNTAINOUS AREA MP CL 16.51 TO MP CL 22.20 | $39,197,146.00 |
$46,971,122.00 |
|
Nevada | SR 160 BLUE DIAMOND RD, CLARK COUNTY, FROM 1.03 MILES NORTH OF MOUNTAIN SPRINGS SUMMIT TO CL/NY CO. LINE (EASTBOUND ONLY) MP CL 21.960 TO MP NY 0.950 | $21,317,123.00 |
$25,262,492.00 |
|
Nevada | US 395 FM US 50 EAST TO LAKEVIEW INTERCHANGE PHASE 1B Construct a 4 lane controlled access freeway. Construction. | $86,183,570.00 |
$103,271,106.00 |
|
Nevada | US 395, CARSON FREEWAY PHASE 2A: CONSTRUCTION. | $54,758,708.87 |
$58,317,204.81 |
|
Nevada | US395 Carson City Fwy fm So Carson St to Fairview Dr. Pkg 2B-3. Construction. | $52,974,150.00 |
$55,881,653.00 |
|
Nevada | I 515/US 95, LAS VEGAS, FROM EASTERN AVENUE TO LAS VEGAS SPAGHETTI BOWL, MP CL 73.35 TO MP CL 75.66 | $32,556,338.00 |
$34,269,830.00 |
|
Nevada | I 515, CLARK COUNTY, FROM SUNSET RD. INTERCHANGE TO WYOMING AVE; MP CL 63.38 TO MP CL 71.18 | $54,221,181.00 |
$57,074,925.00 |
|
Nevada | I580 FM WINTERS RANCH TO NR MOUNT ROSE HWY structures at Corey Canyon, Browns Creek, St.James Parkway and Galena Creek. | $63,573,324.63 |
$75,881,582.00 |
|
Nevada | I-580 Freeway Near Winters Ranch to Near Mt. Rose Highway - Package B. Construction | $381,622,543.70 |
$443,275,930.01 |
|
Nevada | I 580, WASHOE COUNTY, FROM MT ROSE INTERCHANGE TO 0.131 MILES N OF THOMAS CREEK, MP WA 14.97 TO MP WA 18.558 | $10,095,871.84 |
$25,757,040.00 |